| December
30 |
Federal
Acquisition Circular (FAC) 2005-48
has been published. It includes the following four items:
Item
I (FAR
Case 2011-005), entitled "Repeal of the Small
Business Competitiveness Demonstration Program," is a
final rule effective January 31, 2011, which removes subpart
19.10 of the FAR in order to comply with the requirements of
section 1335 of the Small Business Jobs Act of 2010.
Item
II (FAR
Case 2009-027), entitled "Personal Identity
Verification of contractor Personnel," is a final rule
effective January 31, 2011, which amends the FAR to
provide additional regulatory coverage to reinforce the
requirement of collecting from contractors all forms of
Government-provided identification once they are no longer
needed to support a contract.
Item
III (FAR
Case 2009-031), entitled "Terminating
Contracts," is a final rule effective January 31, 2011,
which amends the FAR to clarify which procedures for
terminating contracts apply to contracts for commercial
items.
Item
IV (FAR
Case 2009-018), entitled "Payrolls and Basic
Records," is a final rule, effective today, adopting the
interim rule (with one change) that amends the FAR's "Payrolls
and Basic Records" clause in order to implement a
Department of Labor rule that protects the privacy of workers. |
| December
29 |
DFARS
Case 2009-D015 (Organizational Conflicts of Interest in
Major Defense Acquisition Programs) is a final rule amending
the DFARS to
implement section 207 of the Weapon Systems Acquisition Reform
Act of 2009, which addresses organizational conflicts of
interest in major defense acquisition programs.
DFARS
Case 2009-D012 (Foreign Participation in Acquisitions in
Support of Operations in Afghanistan) is a final rule amending
the DFARS (i) to waive section
302(a) of the Trade Agreements Act of 1979, as amended (which
prohibits acquisitions of products or services from
nondesignated countries) in order to allow acquisition from
the nine South Caucasus/Central and South Asian (SC/CASA)
states; and (ii) to determine the inapplicability of the
Balance of Payments Program evaluation factor to offers of
products (other than arms, ammunition, or war materials) from
the SC/CASA states to support operations in Afghanistan.
The
Prompt Payment Act interest
rate has been set at 2 5/8% for the period January 1
through June 30, 2011.
FTR
Bulletin 11-03 establishes the privately-owned vehicle mileage
reimbursement rates for calendar year 2011. |
| December
25 |
The
facts and legal issue underlying the CBCA's decision in W.
G. Yates & Sons Construction Co. are very interesting
(at least to me). I'm going to fictionalize the numbers for
the sake of simplicity, so bear with me. The contractor had a
fixed-price construction contract incorporating a Davis-Bacon
Act wage determination, which required a wage rate of $10 per
hour. Part of the contract price was a subcontract, which was
bid on the basis of an estimated 5,000 hours of labor covered
by the wage determination. After award, the Government
discovered it had used the incorrect wage determination in the
contract, so it retroactively incorporated a revised wage
determination that called for wages of $20 per hour. The
subcontractor ended up incurring 10,000 hours to do the job.
The contractor submitted a claim under the Changes clause on
behalf of its sub for 10,000 hours (the sub's total
performance hours) times the $10 difference between the
erroneous and revised wage determination hourly rates, plus
associated profit and overhead. The Government argued that (i)
the claim should only be for the originally estimated 5,000
hours times the $10 difference and (ii) it should not include
any added overhead and profit. The case involves
questions concerning the proper measurement of an equitable
under the Changes clause and whether the Changes clause was
even the appropriate vehicle for recovery. The Board chose the
contractor's calculation.
in
Nu-Way
Concrete Co., the CBCA denied claim for extra work under
constructive change and implied ratification theories because
(i) the Contracting Officer did not require or ratify the
extra work allegedly ordered by the inspectors and warned the
contractor not to do it; and (ii) the contractor's proof of
quantum conflicted with its certification of costs and was
"inconsistent, incredible, and incomprehensible." |
| December
24 |
The SBA's
OHA has published a bunch of new decisions.
In Size
Appeal of Ecotope Environmental Services, Ltd., the
OHA affirmed the Area Office's finding that the protested firm
was other than small based upon an adverse inference after the
protested firm failed to file SBA Form 355 as requested by the
Area Office.
In Size
Appeal of TLC Catering, the OHA reversed the Area
Office's finding of a violation of ostensible subcontractor
rule where the subcontractor made sandwiches and the prime
provided all other box-lunch ingredients, and assembled,
delivered, and served the box lunches.
In Size
Appeal of PTL Contracting Corp., the OHA dismissed an
appeal to the OHA because it was not filed within the required
15 days of receipt of the Area Office's determination.
In Size
Appeal of Space Concepts, LLC, the OHA remanded the
case to the Area Office for further investigation whether the
company awarded a small business set-aside contract complied
with nonmanufacturer rule or was merely an
assembler/distributor for the product of a large business.
In Size
Appeal of Sunshine Kids Services, Inc., the OHA
concluded that the Area Office properly dismissed a protest as
untimely despite the protester's contention that the agency's
notice of award was not sufficient to give it notice of its
protest grounds because it did not identify the separate
members of the JV awardee. The OHA noted that the applicable
regulations only require notice of the awardee, not its
constituents.
In Size
Appeal of Aero-Graphics, Inc., the OHA dismissed an
appeal for lack of jurisdiction because the contract at issue
had been awarded and the protest allegation (violation of the
ostensible subcontractor rule) was contract-specific.
In Size
Appeal of Sabre88, LLC, the OHA affirmed the Area
Office's finding of affiliation through the newly organized
concern rule because one firm's Managing Member was a key
employee of the other, and there was no clear evidence of
fracture .
In Size
Appeal of LGS Management, Inc., the OHA affirmed the
Area Office's determination that a common address was
not enough to establish affiliation between two firms,
especially in light of other evidence that argued against
affiliation.
In Size
Appeal of Service Disabled Veteran Contractors LLC,
the OHA affirmed the Area Office's dismissal of the protest as
untimely because it was not filed within five days of the
notice of award.
In Size
Appeal of Beltsville Industries Group, Inc.-Desbuild
Incorporated Joint Venture, the OHA affirmed the Area
Office's conclusions that (i) the members of a mentor-protégé
that formed four joint ventures, no single one of which
violated the 3 offers in 2 years rule, were not affiliated
with one another, and (ii) the various joint ventures were not
affiliates.
In Size
Appeal of LOGMET, LLC, the OHA reversed the Area
Office's size determination that firms were affiliated based
on the identity of interest and ostensible subcontractor
rules; the OHA found that the subcontracts did not rise to
level of economic dependence and that the prime contractor had
the capacity to perform the entire contract and only chose to
assign a portion of the work to the subcontractor.
In Size
Appeal of Cummings Construction, the OHA affirmed the
Area Office's finding of affiliation based upon identity of
interest (via economic dependence) with the 49% owner.
The
new OHA NAICS decisions are the top seven entries under the
NAICS section of my SBA
OHA Decisions page. The most interesting of the bunch is the
NAICS
Appeal of McKissack & McKissack, in which the OHA
dismissed the appeal as premature (because only a
presolicitation notice had so far been issued) and for lack of
jurisdiction (because the procurement at issue will be
unrestricted).
The
new OHA VET decisions are the top nine decisions under the VET
section of my SBA
OHA Decisions page. The most interesting of the bunch is Matter
of Airborne Services, LLC, which overrules the prior
decision in Matter
of United Medical Design Builders, LLC,
SBA No. VET-197 (2010)
and states in part as follows:
I
hereby overrule United Medical to the extent it holds
that the SBA has an obligation to adjudicate protests brought
in relation to VAAR Part 819 procurements. The SBA currently
has no authority or obligation to decide SDVO SBC status
protests filed in connection with procurements issued under
VAAR Part 819, and the SBA’s decision to reject jurisdiction
for such protests is consistent with the statutes and
regulations at issue. Consequently, SDVO SBC status protests
relating to VAAR Part 819 must be decided by the VA OSDBU
until an interagency agreement is executed between the VA and
the SBA to allow the SBA D/GC to decide such protests under
VAAR § 819.307.
|
| December
22 |
DFARS
Case 2009-D043 (Reporting of Government-Furnished
Property) is a proposed rule to amend the DFARS (i) to
revise and expand reporting requirements for
government-furnished property to include items uniquely and
nonuniquely identified and (ii) to clarify policy for
contractor access to government supply sources.
Comments are due by February 22, 2011. |
| December
21 |
Acrow
Corp. of America contains a detailed analysis of the
standards the Court of Federal Claims will use to decide
whether to permit supplementation of the administrative record
in a bid protest. |
| December
19 |
The
Bureau of Industry and Security has amended the EAR to
implement changes to the Entity
List on the basis of the annual review of that list
conducted by the End-User Review Committee. Specifically, the
rule removes five entities from the Entity List under Russia
and makes twenty-one modifications to the Entity List
(consisting of modifications to eighteen Chinese entries and
three Russian entries currently on the Entity List) by adding
additional addresses, aliases and/or clarifying the names for
these twenty-one entities. |
| December
17 |
In YRC,
Inc., the Court of Federal Claims held it lacked
jurisdiction over a subcontractor's claim against the
Government for payments a defaulted contractor failed to make
to it because there was no express or implied-in-fact contract
between the plaintiff and the Government and because the
federal officials who dealt with plaintiff and made
arrangements to make some payments to it had no authority to
contract on behalf of the Government.
In
BLR
Group of America, the court denied the contractor's motion
for partial reconsideration of the court's prior
decision (dismissing the suit for lack of a CDA
claim) because neither the contractor's comments
disagreeing with the Government's performance assessment
report nor the contractor's counsel's email to the Contracting
Officer attempting to convince her to withdraw or change the
Government's evaluation constituted a CDA claim. The decision
involves my pet peeve: the failure of the CDA, itself, to
define a claim and the myriad disputes that failure continues
to provoke. Here, the court notes that two inquiries beyond
examining the regulatory definition of a claim are required:
"First, in determining whether a contractor’s
submission constitutes a CDA claim, the court must examine the
intent of the contractor as expressed in the submission. . . .
Second, the court is required . . . to look beyond the
[regulatory] definition of a CDA claim and take into account
the particular facts of the case." Imagine how much time
has been wasted on those two endeavors since 1980. |
| December
16 |
In
Arctic
Slope Native Ass'n, the Court of Appeals for the Federal
Circuit affirmed the CBCA and held that (i) the
contractor was not entitled to reimbursement for costs that
exceeded available appropriations because the contract
contained explicit "subject to the availability of
appropriated funds" and "not to exceed"
language; and (ii) the Government did not breach the contract
by failing to request additional appropriations because there
was no contractual requirement that it do so. The court also
rejected the contractor's argument that the statutory funds
were sufficient to reimburse its costs, alone. The court noted
that, if it were to allow this approach, and all similarly
situated contractors also used it, the result would be total
reimbursements exceeding the available appropriations, which
would circumvent the explicit cap included in the statute,
itself.
In Joyce
Terry d/b/a Shirt Shack, the Court of Federal Claims held
that, although it lacked 28 U.S.C. 1491(b) jurisdiction over
protests of AAFES procurements (because AAFES is a
non-appropriated fund instrumentality or "NAFI")
and also lacked jurisdiction over the CDA count in plaintiff's
complaint (because no claim had been submitted to the
contracting officer), the court (in what it calls a case of
first impression), nevertheless, has 28 U.S.C. 1491(a)(1)
jurisdiction over a protest that AAFES acted arbitrarily
and capriciously by awarding a concessionaire contract despite
the awardee's alleged failure to comply with a material
solicitation requirement (even though the protester had only
pled section 1491(b)). Interestingly, the court noted, without
further comment, that the protester had filed suit seven
months after its agency protest had been denied.
FASAB has
released an exposure drafts entitled "Implementation
Guidance on the Accounting for the Disposal of General
Property, Plant & Equipment," and "Implementation
Guide for Estimating the Historical Cost of General Property,
Plant and Equipment."
I caught
and corrected a broken link to the Link Government Services
protest described in the November 6 entry below. |
| December
15 |
In The
Boeing Co., the CBCA held that the contractor was not
entitled to recover its "common costs" of a defense
against a False Claims Act suit, i.e., those costs
attributable to both the successful and unsuccessful portions
of its defense.
In
the
original (PlanetSpace
I) decision (see the May 2 entry below), the Court
of Federal Claims found the SSA's rationale for an award
decision ambiguous and ordered the agency to provide an
explanation. After having received and reviewed a sworn
declaration from the SSA, the court denies
the protest because the SSA's declaration evidences a rational
trade-off analysis that did not amount to a
non-responsibility determination concerning the protester's
proposal.
In
Harris
Patriot Healthcare Solutions, the protester originally
filed suit at the Court of Federal Claims when the agency
indicated it intended to override a CICA stay during a GAO
protest, but, after the agency decided to take corrective
action and the GAO dismissed the protest as academic, the
court concluded the suit concerning the override was moot,
despite the protester's suspicions that the agency would
use another contractual vehicle to circumvent maintaining the status
quo pending the outcome of the corrective action. |
| December
14 |
The ASBCA
published several decisions.
Parsons
Global Services is difficult to summarize, but, basically,
the Board dismissed the appeal for lack of CDA jurisdiction
because the contractor had omitted all the normal steps for
determining (and invoicing the Government for) its
subcontractor's indirect costs, and, therefore, Government had
never been in a position to dispute any of these costs.
The Board
dismissed an appeal by Tefirom
Insaat Enerji Sanayi ve Ticaret A.S. because the
contractor failed to provide a CDA certification.
In
Kelly-Ryan,
the Board denied the Government's motion to dismiss as
premature (or, alternatively to stay proceedings concerning)
an appeal from a deemed denial of a $36 million claim of more
than 3,500 pages after the Contracting Officer had informed
the contractor that a decision would require a year from the
time the claim was originally submitted. The Board found that
time period to be unreasonable; I'm not so sure.
DoD
has issued an interim final rule amending 32 C.F.R. Part 241
to implement section
1110 of the National Defense Authorization Act for Fiscal Year
2010, which authorizes DoD to establish a Pilot
Program for the Temporary Exchange of Information
Technology (IT) Personnel under which there may be temporary
assignments of DoD IT employees to private sector
organizations and vice versa. Comments are due by
February 14, 2011. |
| December
11 |
Federal
Acquisition Circular (FAC) 2005-47
has been published and includes the following six items (plus
technical amendments):
Item
I (FAR
Case 2010-006), entitled "Notification of Employee
Rights Under the National Labor Relations Act," is an
interim rule to implement Executive Order 13496
(as previously implemented by the DOL), which requires
contractors to display a notice to employees of their rights
under Federal labor laws, including (as the DOL has
determined) the National Labor Relations Act. Comments
are due by February 11, 2011.
Item
II (FAR
Case 2006-005), entitled "HUBZone Program
Revisions," is a final rule effective January 12, 2011,
which implements revisions to the SBA's HUBZone
Program and requires that (i) for award of a HUBZone contract,
a HUBZone small business concern must be a HUBZone small
business concern both at the time of its initial offer and at
the time of contract award; and (ii) for general construction
or construction by special trade contractors, a HUBZone small
business concern must spend at least 50 percent of the cost of
contract performance incurred for personnel on its own
employees or subcontract employees of other HUBZone small
business concerns. (The 50 percent requirement may be waived
in some circumstances.)
Item
III (FAR
Case 2008-032), entitled "Preventing Abuse of
Interagency Contracts," is an interim rule amending FAR
subpart 17.5 to implement section 865 of the Duncan
Hunter National Defense Authorization Act for Fiscal Year
2009, by (i)
broadening the scope of coverage to address all interagency
acquisitions (with limited exceptions), rather than just those
conducted under the Economy Act; (ii) requiring agencies to
support the decision to use an interagency acquisition with a
determination that such action is the "best procurement
approach"; (iii) directing that assisted acquisitions be
accompanied by written agreements between the requesting
agency and the servicing agency documenting the
responsibilities of the respective parties, including the
planning, execution, and administration of the contract; (iv)
requiring the development of business cases (concerning which
OMB is developing additional guidance, which will be
referenced in the FAR once it is issued) to support the
creation of multi-agency contracts; and (v) requiring the
senior procurement executive for each executive agency to
submit an annual report on interagency acquisitions to the
Director of OMB. Comments are due by February 11,
2011.
Item
IV (FAR
Case 2009-019), entitled "Small Disadvantaged
Business Self-Certification," is an interim rule designed
to conform the FAR to revisions in the SBA's regulations and
to clarify that (i) small disadvantaged business (SDBs) may
provide written statements to primes self-certifying their
status as SDBs and (ii) primes may rely on these statements in
awarding subcontracts to SDBs. Comments are due by February
11, 2011.
Item
V (FAR
Case 2009-036), entitled "Uniform Suspension and
Debarment Requirement," is an interim rule amending the
FAR to implement section 815 of the National Defense
Authorization Act for Fiscal Year 2010, which extends the
flowdown of the restriction on subcontracting to lower tier
subcontractors that have been suspended or debarred, with some
exceptions for contracts for the acquisition of commercial
items and commercially available off-the-shelf items. Comments
are due by February 11, 2011.
Item
VI (FAR
Case 2008-031), entitled "Limitation on Pass-Through
Charges," is a final rule (adopting the prior interim
rule with changes), effective January 12, 2011, amending the
FAR (i) to implement section 866 of the Duncan Hunter
National Defense Authorization Act (NDAA) for Fiscal Year 2009
(which applies to executive agencies other than DoD) and
section 852 of the John Warner NDAA for FY 2007, (which
applies to DoD) and (ii) to minimize excessive pass-through
charges by contractors from subcontractors, or from tiers of
subcontractors, that add no or negligible value, and to ensure
that neither a contractor nor a subcontractor receives
indirect costs or profit/fee (i.e., pass-through
charges) on work performed by a lower-tier subcontractor to
which the higher-tier contractor or subcontractor adds no or
negligible value. |
| December
10 |
As part of
the President’s export control reform initiative, the State
Department's Directorate of Defense Trade Controls (i)
solicits public comments on revisions to the United States
Munitions List that would make it a "positive
list" of controlled defense articles (i.e., a
list that describes controlled items using objective criteria
rather than broad, open-ended, subjective, or design
intent-based criteria), and (ii) requests that the public (a)
"tier" defense
articles based on the Administration’s three-tier control
criteria and (b) identify those current defense articles that
the public believes do not fall within the scope of any of the
criteria’s tiers. Comments
are due by February 8. The State
Department proposes to revise Category
VII (tanks and military vehicles) of the Munitions List in
the ITAR (22 C.F.R. Part 121) to provide more accurate
descriptions of the products included in that category.
Comments are due by February 8, 2011.
The CBCA
published several decisions, including the following
two:
In Lockheed
Martin Aspen Med Services, the
Board held it had CDA
jurisdiction over the appeal from a denial of a claim filed by one
member of a Contractor Team Arrangement because, according to
the solicitation's terms, each team member was in privity of
contract with the Government. (Note--this will not be the
result under all teaming agreements).
In Macrosystems,
the Board dismissed an appeal for lack of CDA jurisdiction
because the contractor did not file a claim following a
termination for convenience.
The Court
of Federal Claims denied all construction contract defective
spec, extra work, and delay claims by Delhur
Industries because of a complete failure of proof by the
contractor at trial.
In
Pyramid
Real Estate Services, LLC v. United States, No. 10-599C (Dec.
9, 2010), the court assessed monetary sanctions against an
attorney in a bid protest for disclosing material under a
protective order to its client in order to file a separate bid
protest. |
| December
9 |
The Bureau
of Industry and Security ("BIS") has proposed an
extensive set of changes to the CCL by adding a new exception
(Strategic
Trade Authorization or "STA") to the EAR, which
would allow exports, reexports and transfers (in-country) of
specified items to destinations that pose little risk of
unauthorized use of those items so long as notification,
destination control statement and consignee statement
requirements are met. Comments are due by February 7, 2011.
The BIS
also is requesting comments by February 7 concerning how the
CCL could be more clear, positive, and tiered, including
comments on the degree to which a controlled
item provides the United States with a critical,
substantial, or significant military or intelligence advantage
and the availability of the item outside certain groups of
countries.
DFARS
Case 2009-D038 (Business Systems--Definitions and
Administration): DoD has extended the comment period to
January 10, 2011. |
| December
8 |
DFARS
Case 2006-D029 (Restriction on Ball and Roller Bearings)
is a final rule amending the DFARS to implement DoD annual
appropriations act requirements and to require
that each ball or roller bearing be manufactured in the United
States, its outlying areas, or Canada, and that the cost of
the bearing components manufactured in the United States, its
outlying areas, or Canada, exceed 50 percent of the total cost
of the bearing components of that ball or roller bearing.
DFARS
Case 2010-D004 (Restrictions on the Use of Mandatory
Arbitration Agreements) is a final rule (adopting a prior
interim rule with changes as a results of comments received
from the public ) which prohibits the use of funds
appropriated or otherwise made available by the DoD
Appropriations Act for Fiscal Year 2010 for any contract for
noncommercial items (including task or delivery orders and
bilateral modifications adding new work) in excess of $1
million, if the contractor restricts its employees to
arbitration for claims under title VII of the Civil Rights Act
of 1964, or torts related to or arising out of sexual assault
or harassment, including assault and battery, intentional
infliction of emotional distress, false imprisonment, or
negligent hiring, supervision, or retention.
Effective
December 23, DoD is
waiving the requirements of 10 U.S.C. 2354 for the
following defense items produced in the United Kingdom (which
will permit procurement from sources in the United Kingdom): (i)
air circuit breakers; (ii) welded shipboard anchor and mooring
chain with a diameter of four inches or less; (iii)
gyrocompasses; (iv) electronic navigation chart systems; (v)
steering controls; (vi)
pumps; (vii)
propulsion and machinery control systems; and (viii) totally
enclosed lifeboats.
Civilian
Personnel Per Diem Bulletin 272 lists revisions in the per
diem rates prescribed for U.S. Government employees for
official travel in Alaska, Hawaii, Puerto Rico, the Northern
Mariana Islands and Possessions of the United States, while
AEA changes announced in Bulletin Number 194 remain in
effect. |
| December
7 |
In
Bona
Fide Conglomerate (a successful post-award request for a
TRO under a procurement by the GSA and
the Committee for Purchase From People Who Are Blind or
Severely Disabled pursuant to the AbilityOne Program, formerly
known as the Javits-Wagner-O’Day Act) the Court of Federal
Claims found the plaintiff had raised significant factual
questions concerning the agency's failure to follow the
evaluation scheme and possible bias, but required a $50,000
bond to enter the TRO.
The
ASBCA published several decisions.
In
Kellogg
Brown & Root Services, the Board denied a government
motion to dismiss (for lack of subject matter jurisdiction
under CDA) a claim for unpaid invoices on a contract
unilaterally transferred by the Corps of Engineers to the
Interim Iraqi Government and thereafter funded by Development
Fund for Iraq funds, which are nonappropriated funds. The
Board was forced to look to the Restatement of Contracts for
guidance concerning assignments and delegations since neither
the Anti-Assignment Act nor any other similar federal law
covers a government transfer of a contract.
In another
Kellogg
Brown & Root Services decision published the
same day, the Board denied government motions to stay appeals
pending resolution of a suit under the False Claims Act
because (i) there was insufficient similarity between the
actions; (ii) the Government did not establish there would be
prejudice to its suit from proceeding with the board appeals;
and (iii) the indefinite length of requested stay weighed
against granting it.
In Smart
Power Systems, the Board granted the Government's motion
for summary judgment and upheld a default termination for
failure to make progress because the contractor failed to cure
its performance after (or provide an adequate response to) a
cure notice.
In Western
Plains Disposal, the Board denied a government motion to
dismiss an appeal for lack of jurisdiction because the Board
found that submission of a Certification of Current Cost of
Pricing Data instead of a CDA certification was a correctable
error.
In Cardinal
Maintenance Service, the Board dismissed the portions of
the contractor's claims time barred by the CDA's six-year
statute of limitations.
The CBCA
denied Arun
Enterprises' appeal
from a
GSA claim for unpaid rent and capital improvement deposits
under a building lease because the contractor presented no
credible evidence to support its contention that it was
entitled to adjustments to the building rental. |
| December
4 |
In Matt
Martin Real Estate Management LLC, an unsuccessful
post-award protest, the Court of Federal Claims held, inter
alia, that HUD had a rational basis for assigning all five
proposals an overall rating of "Good" after
analyzing the ratings under each individual evaluation factor,
even though the offerors' individual ratings were not
identical. |
| December
3 |
The GAO
published decisions sustaining two protests.
NCS
Technologies convinced the GAO that solicitation
provisions requiring (i) computers and monitors to be from the
same manufacturer and (ii) computers to have Intel-based
microprocessors were unduly restrictive of competition.
CIGNA
Government Services won its protest because (i) the agency
failed to conduct meaningful discussions where it determined
that certain of the protester's proposed costs were
understated and adjusted the most probable cost estimate
associated with the protester's costs upwards rather than
reopening discussions to allow it an opportunity to address
the issue; (ii) the agency evaluated the past performance of
the awardee's minor subcontractor where the solicitation
provided for the consideration of the past performance only of
"significant" or "critical"
subcontractors; and (iii) the agency presented no rational
basis for its less favorable evaluation of the protester's
proposal for one of the awards contemplated under the
solicitation than for another, essentially identical
proposal submitted by the protester for a different award
under the same solicitation.
DFARS
Case 2009-D038 (Business Systems--Definition and
Administration) is an lengthy, extensive set of proposed
changes to the DFARS designed to improve the effectiveness of
DoD oversight of contractor business systems, and, after
receiving 370 comments on the original proposed rules, the DoD
has published revised proposed rules. Comments on the latest
proposals are due by January 3, 2011.
DFARS
Case 2009-D008 (Government Property) is a proposed rule to
revise DFARS
part 245, Government Property,
to reflect recent revisions to FAR part 45, Government
Property. |
| December
2 |
Two ASBCA
decisions have been published.
In AmerescoSolutions,
the Board denied the contractor's motion for summary judgment
in a default termination appeal because the contractor did not
establish the Government had waived the due date under the
"unusual circumstances" legal standard required to
establish waiver in a construction contract default
termination appeal.
In J.
A. McAmis, the Board held that the contractor was entitled
to recover increased haul costs and delay costs after haul
routes to the site became unavailable due to a local ordinance
passed after award (and rejected the Government's attempts to
rely on the "Permits and Responsibilities Clause"
and the sovereign acts doctrine to avoid this result); but the
contractor was not entitled to recover its costs of the
rejection of rock that complied with the specifications
because the contractor did not establish the Government had
rejected the rock. |
| November
30 |
DFARS
Case 2010-D023 (Definition of Sexual Assault): A proposed
would would amend the DFARS to ensure that contractor
employees who are authorized to accompany U.S. Armed Forces
deployed outside the United States are
aware (i) of the DoD definition of ‘‘sexual assault’’
as defined in DoD Directive 6495.01, Sexual Assault Prevention
and Response (SAPR) Program and (ii) that such offenses are
covered under the Uniform Code of Military Justice. Comments
are due by January 31, 2011.
In a
nonprecedential decision that is, nevertheless, interesting,
the Court of Appeals for the Federal Circuit reversed the
Court of Federal Claims and held that Norma
C. Sullivan and Donald E. Sullivan (who were injured by
car driven by Postal Service contractor's employee) could not
maintain an action against the Postal Service for breach of
contract as third party beneficiaries for the Postal Service's
failure to enforce a contract provision requiring the
contractor to obtain additional insurance because that failure
was not a breach of the contract (which did not require the
Postal Service to enforce that provision). |
| November
27 |
The GAO
sustained two protests. Marine
Hydraulics International won because the agency made
several erroneous upward adjustments to the protester's cost
proposal during the cost realism evaluation. DRS
ICAS, LLC is another example of an agency's stubborn
insistence on finding ways to stick with its original awardee
after taking corrective action, and DRS won because (i)
several technical weaknesses assessed by the agency's
evaluators lacked a rational basis; (ii) the agency should
have considered additional performance under a related
contract that occurred between the time of the original
evaluation and the reevaluation; and (iii) the agency
improperly assessed a weakness for failing to explain an an
MTBF calculation when neither the solicitation nor the
specifications required such an explanation. |
| November
24 |
The
following DFARS final and proposed rules have been issued.
DFARS
Case 2008-D027 (Cost and Software Data Reporting System)
is a final rule to amend the DFARS to address DoD
Cost and Software Data Reporting system requirements for Major
Defense Acquisition Programs and Major Automated Information
Systems.
DFARS
Case 2009-D034 (Contract Authority for Advanced Component
Development or Prototype Units) is a final rule (adopting the
prior interim rule with only a minor change) amending
the DFARS to implement section 819 of the National Defense
Authorization Act for Fiscal Year 2010, which places
limitations on certain types of line items and contract
options that may be included in contracts initially awarded
pursuant to competitive solicitations.
DFARS
Case 2010-D025 (Services of Senior Mentors) (i) implements
previously issued DoD memoranda on Senior Mentors (retired DoD
personnel that provide training to active DoD personnel) and
(ii) has no impact on the general public.
DFARS
Case 2009-D025 (Contractor Insurance/Pension Review) is a
final rule adopting, without any changes, the proposed rule to
remove and relocate the requirements for conducting a
Contractor Insurance/Pension Review from Procedures, Guidance,
and Information (PGI) to the DFARS.
DFARS
Case 2009-D011 (Annual Representations and Certifications)
is a proposed rule to amend the DFARS to conform to FAR
requirements concerning Annual Reps and Certs. Comments are
due by January 24, 2011.
DFARS
Case 2010-D013 (Discussions Prior to Contract Award) is a
proposed rule (recommended by the DoD Source
Selection Joint Analysis Team) to strongly encourage
discussions prior to award for source selections of
procurements estimated at $100 million or more. Comments are
due by January 24. |
| November
23 |
The
GAO sustained the protest of Missouri
Machinery & Engineering Co. because the agency did not
establish that a solicitation requirement for vendors to be an
original equipment manufacturer's authorized repair facility
was necessary to meet the agency's needs.
In D'Andrea
Brothers, LLC, the Court of Federal Claims denied the
Government's summary judgment motion to dismiss a claim that
it had violated its obligation of good faith and fair dealing
under a CRADA by "bad-mouthing" HooAH! energy bars.
In
a very interesting decision in several respects, Bilfinger
Berger AG Sede Secondaria Italiana won its protest at the
Court of Federal Claims due to the agency's inappropriate
reliance on an Italian legal opinion (concerning a certificate
required by applicable Italian law) as the basis for a
negative responsibility determination. The court rejected the
Government's contention that the claim was barred by laches
because the contractor had waited a number of weeks for the
publication of the redacted version of the GAO's decision on
its earlier protest before proceeding in federal court. The
court also discussed the plaintiff's standing, i.e.,
its contention that it would have had a substantial chance for
award if the errors it alleged were remedied. |
| November
19 |
Mobile
Medical International Corp. lost its post-award protest at
the Court of Federal Claims because (i) it did not establish
it would have had a substantial chance for award if its
protest were sustained and, therefore, lacked standing and
(ii) its allegedly proprietary information had not been
improperly disclosed because plaintiff, itself, had already
disclosed it in the public domain. |
| November
17 |
In Henry
Housing Limited Partnership, the Court of Federal Claims
denied the Government's Rule 12(c) motion to dismiss the Fifth
Amendment takings portion of a contractor's claims based on
the Government's abrogation of the prepayment term of a
Farmers Home Administration loan contract. |
| November 12 |
DFARS
Case 2009-D039 is an interim rule amending the DFARS to
implement section 823 of the National Defense Authorization
Act for Fiscal Year 2010, which requires contracting officers
to consider reducing or denying an award fee if actions by a
contractor or subcontractor jeopardize the health or safety of
government personnel. Comments are due by January 11, 2011. |
| November 10 |
Effective
December 10, the DOE is amending sections of the DEAR related
to socioeconomic
programs to conform them to the FAR. to remove outdated
coverage, and to update references.
FTR
Bulletin 11-02: The GSA has updated the Fly America Act information on
the GSA web site with recent changes to the new US–EU Open
Skies agreement signed June 24, 2010. |
| November 9 |
I
always enjoy a good tug of war between the GAO and the
procuring agency. Early this year, the GAO sustained a protest
by PMO
Partnership Joint Venture after the DOT had found the
accounting system proposed by the JV for a cost reimbursable
contract unacceptable simply because the proposal was based on
using the individual indirect rates of the JV partners. The
GAO thought this was a matter of responsibility rather than
responsiveness, rejected the agency's unsupported conclusion
that CAS 401 demanded a single overhead rate for the JV, and
found no other rational basis for the agency's conclusion.
Undaunted, the agency then decided that the joint venture's
proposal should be rejected because it was noncompliant with
cost or pricing data requirements in FAR 15.408. PMO protested
again, and the GAO has now sustained
this latest protest, too, because the solicitation did not
require cost or pricing data and was not subject to the cost
or pricing data requirements of FAR Part 15.
The
ASBCA published seven decisions--
In
A.
Montano Electrical Contractor, the Board held it lacked
CDA jurisdiction over a direct claim by a subcontractor for
monies allegedly owed it by its prime contractor where the
sub's claim was not sponsored by the prime or a surety.
In Utility
Construction Co., the Board held that a claim, which
stated the amount being claimed, satisfied the CDA requirement
for a sum certain, even though the Government complained it
could not ascertain how the delay portion of the claim had
been calculated.
In MAC
International FZE, the Board held it lacked CDA
jurisdiction over claims for payment pursuant to orders under
an ID/IQ contract between the contractor and the Coalition
Provisional Authority ("CPA") in Iraq (funded with
Iraqi funds) because the CPA was not U.S. government agency
subject to the CDA.
David
J. Needham discusses various categories of allowable and
unallowable costs in a convenience termination claim after the
termination of an aircraft lease with a nonappropriated fund
instrumentality.
In Genome-Communications,
the Board denied a motion for summary judgment because there
were factual issues as to whether the contractor was entitled
to payment for providing training materials for an
instructional seminar and whether the materials complied with
the contract requirements.
In United
Healthcare Partners, the Board denied the Government's
motion motion for reconsideration (of the Board's prior
decision denying the Government's request for summary
judgment) because (i) the Board had not held that the
solicitation was an RFQ and (ii) under the parol evidence
rule, the instructions to bidders in a solicitation may be
used to interpret the subsequent contract.
In American
AquaSource, Inc., the Board denied the contractor's motion
for reconsideration of the prior
decision denying contractor's motion for summary judgment
as to the propriety of a termination. |
| November 7 |
In Malinda
Baldwin, the Court of Federal Claims held that failing to
submit a written demand to the Contracting Officer and to
specify a sum certain are not "harmless errors" that
can be overcome by reference to the plaintiff's
"intent," but, rather, are fatal CDA jurisdictional
flaws. |
| November 6 |
In its
latest decision in the winning Sheridan
protest, the Court of Federal Claims permanently enjoined the
Government from resoliciting revised proposals where the
agency's needs had not changed:
The Court finds the MCII Generator
case particularly relevant to the present case. In both
situations, the "defect" identified by the
Government had no relation to the proposed corrective action.
The record in both cases suggests that the respective agencies
made the correct award decisions, and that if any flaws in the
process existed, such flaws occurred during the evaluation of
the properly submitted proposals. In such circumstances, a
reevaluation of the proposals may be warranted, but a
resolicitation of the proposals compromises the integrity of
the procurement system, especially where the winning price has
been disclosed to the public.
Defendant argues that this case can
be distinguished from Delaney, MCII Generator, and other cases
because here, the resolicitation is on identical terms. The
Court finds this position entirely illogical. Instead, the
fact that the agency conducted the resolicitation on identical
terms further strengthens Plaintiff’s argument that a
resolicitation was improper and unnecessary. Where the terms
of the RFP remain unchanged and the initial proposals were
properly submitted, there is no rational basis for the agency
to resolicit proposals that it already received under a
properly conducted solicitation. The only conceivable reason
to permit resolicitation would be to allow the unsuccessful
offerors an opportunity to beat the now disclosed price of the
winning proposal. Such a result is impermissible and would
severely damage the integrity of the procurement process.
Exactly so, Your Honor,
exactly so.
Linc
Government Services lost its protest against multiple
types of alleged errors in the technical, price, past
performance, and trade-off evaluations, but, as a preliminary
matter, the court described the three-pronged analysis that
may be required to establish the necessary element of
"prejudice" in any bid protest:
[B]id protest jurisprudence writ
large can be seen as evolving into a three-step
analysis. First, in order to demonstrate allegational
prejudice, a plaintiff must show that it would have had a
substantial chance of being awarded the contract but for the
combined impact of all agency decisions alleged to be
unlawful. . . . Second, and only if the plaintiff makes
this threshold showing of prejudice, the court determines
whether the challenged agency decisions were contrary to law. .
. . And third, in order to demonstrate APA
prejudice, the plaintiff must show that it would have had a
substantial chance of being awarded the contract but for the
combined impact of any agency decisions adjudged to be
unlawful. . . .
To be sure, the second prejudice
inquiry (the third step in the above analysis) is not always
required. If all alleged procurement errors ultimately
withstand the court’s scrutiny—i.e., if the court upholds
as lawful every agency decision challenged by a plaintiff—the
need for a second prejudice inquiry will be obviated. . . . By
the same token, if none of the challenged agency decisions
survives judicial review—i.e., if all decisions alleged to
be unlawful are adjudged to be so—a second prejudice inquiry
would simply duplicate the first and would thus be redundant.
. . . However, where a plaintiff succeeds on the merits of
some but not all of its allegations, a second examination of
prejudice becomes necessary. This is because the plaintiff’s
success in demonstrating allegational prejudice in such cases
does not guarantee its success in demonstrating APA prejudice.
. . . Specifically, the plaintiff in such cases may be able to
satisfy the substantial chance test based upon the combined
impact of all allegedly unlawful agency decisions, but may
fail to do so based upon the cumulatively lesser impact of
those decisions that the court ultimately determines to be
unlawful. . . . [citations omitted]
The interesting thing about the
past performance evaluation in this procurement is the lengths
the evaluators went to in order to ascertain that seemingly
negative past performance information concerning the eventual
awardee was not actually relevant. The issue was whether the
evaluators' efforts amounted to commendable diligence or bias
(as the protester alleged). |
| November 5 |
Effective
December 6, the DOE is amending Subchapter I of the DEAR at 48
C.F.R. Part 970 (concerning Management
and Operating Contracts) to conform it to the FAR.
Effective
November 22, the SBA is is granting a class waiver of
the Nonmanufacturer Rule for Woven and Knit Impregnated with
Flat Dipped Rubber/Plastic Gloves, under NAICS code 315992
(Glove and Mitten Manufacturing). |
| November 4 |
EREH
Phase I won its post-award protest at the Court of Federal
Claims because the GSA's finding that the property offered by
awardee did not lie within a flood plain was arbitrary and
capricious (and just plain wrong); but the court also held
that the equities did not favor an injunction; so the
protester was limited to recovering its bid preparation costs.
In the court's heavily-redacted decision in Pyramid
Real Estate Services, the protester failed to timely
protest solicitation terms and alleged ambiguities in the
solicitation and lost its protest against various conclusions
by the evaluators (because the court would not not substitute
its judgment for those of the evaluators and because the
protester failed to meet the high burden of proof required to
establish the evaluators' bias). |
| November 3 |
DFARS
Case 2010-D027 (Prohibition on Interrogation of Detainees
by Contractor Personnel) is an interim rule to
implement section 1038 of the National Defense Authorization
Act for Fiscal Year 2010 (Pub. L. 111–84), which prohibits
contractor personnel from interrogating detainees under the
control of the Department of Defense, but also allows the
Secretary of Defense to waive the prohibition for a limited
period of time, if determined necessary to the national
security interests of the United States. Comments are due by
January 3, 2011.
FTR
Case 2010-303: This interim rule, effective March 3, 2011,
amends the FTR by (i) adding terms and definitions for
"Dependent," "Domestic
partner," and "Domestic partnership," and (ii)
revising the definition of "Immediate family" to
include "Domestic partner" and children, dependent
parents, and dependent brothers and sisters of the Domestic
partner as named members of the employee’s household, and
(iii) adding references to domestic partners and
committed relationships, where applicable, in the FTR.
Comments are due by December 20. |
| November 2 |
In Kenney
Orthopedic, the Court of Federal Claims ruled on a slew of
discovery disputes involving, among other things, the VA's
back-up, preservation, recovery, and production of electronic
records. |
| October 31 |
Hostetter,
Keach & Cassandra Construction won its GAO protest
against the rejection of its bid as nonresponsive where,
although there was a discrepancy in names of bidder and bid
bond principal, the record showed that they were the same
entity and that the principal would be liable on the bonds if
the bidder defaulted.
The ASBCA
dismissed Sygnetics'
appeal for lack of CDA jurisdiction because the original
certification was not signed.
In AECOM
Government Services, the Board granted the Government's
motion for summary judgment that the contractor was not
entitled to recover F.I.C.A. taxes on offshore subsidiaries
first imposed by the HEART Act six months after the award of
its fixed-price contract, at least based on the contractor's
theory of breach of the implied warranty of good faith and
fair dealing. The Board noted that the contractor's
alternative theory of mutual mistake was not involved in the
summary judgment motion.
In Inchcape
Shipping Services, the Board analyzed whether the claims
before it involved maritime contracts, and, therefore,
admiralty jurisdiction.
In Systems
Development Corp., the Board dismissed a claim as barred
by the CDA's statute of limitations because it
"accrued" more than six years before it was
submitted to the Contracting Officer for a decision. |
| October 29 |
Angelika
Textile Services won its protest at the Court of Federal
Claims because the Contracting Officer, in violation of the
Veterans Benefits Act and its implementing regulations (the
New Guidelines), did not consider whether SDVOSBs or VOSBs
were available to meet a requirement prior to placing a firm
on the AbilityOne Procurement List so that she could award it
a sole source contract, all this despite the fact that the GAO
had previously dismissed the protest as frivolous because it
did not spot the issue.
DFARS
Case 2010-D016 (Continuation of Contracts--Deletion of
Redundant Text): This final rule eliminates the now redundant
text of DFARS 209.405–1, which limits the placement of
orders against contracts with contractors that have been
debarred, suspended, or proposed for debarment, because, on
December 11, 2003, the final rule published under FAR Case
2002–010 (68 FR 69250) incorporated these restrictions into
the FAR.
DFARS
Case 2009-D017 (Continuation of Essential Contractor
Services): This final rule, adopts, with changes the interim
rule amending the DFARS to add policy and a contract clause (DFARS 252.237–7023) requiring
that contractors providing essential contractor services, as
determined by the requiring activity, shall be prepared to
continue such services during periods of crisis.
DFARS
Case 2009-D029 (Safety of Facilities, Infrastructure, and
Equipment for Military Operations) is an interim rule designed
to implement
section 807 of the National Defense Authorization Act of 2010,
which requires that facilities, infrastructure, and equipment
that are intended for use by military or civilian personnel of
the DoD, in current or future military operations, should be
(i) inspected for safety and habitability prior to use and
(ii) brought into compliance with generally accepted standards
for the safety and health of personnel to the maximum extent
practicable consistent with the requirements of military
operations and the best interests of DoD to minimize the
safety and health risk posed to such personnel. Comments are
due by December 28.
DFARS
Case 2009-D040 (Trade Agreements--New Thresholds): This
final rule adopts as final (without change) the interim
rule that amended the DFARS to incorporate increased
thresholds for application of the World Trade Organization
Government Procurement Agreement and the Free Trade
Agreements, as determined by the United States Trade
Representative.
DFARS
Case 2009-D041 (Balance of Payments Program Exemption for
Commercial Information Technology--Construction Material):
This final rule amends the DFARS to implement the exemption from the Balance of
Payments Program for construction material that is commercial
information technology. |
| October 28 |
The
SBA has announced the availability of a compliance
guide for the Women-Owned Small Business (WOSB) Program,
which sets forth in plain language the requirements for
participation in the WOSB program and is intended to help
small businesses understand the regulation and how it affects
them. The guide is available here. |
| October 27 |
In
the Weston
Solutions protest, the Court of Federal Claims ordered the
procuring agency to review and clarify its ambiguous rankings
of A-E firms and then to make a new determination of final
rankings on the record. |
| October 26 |
Several
Court of Federal Claims decisions have been published. In United
Constructors, the court denied (i) a Type I Differing Site
Conditions claim because the conditions were reasonably
foreseeable at time of bidding and (ii) a constructive
acceleration claim because contractor's own actions
contributed to the delay. In Environmental
Safety Consultants, the court (pursuant to Rules 12(b)(1)
and 12(b)(6)) dismissed PPA, takings, and punitive damages
claims, as well as (i) a claim first submitted when the firm
was no longer a contractor with the United States and (ii) a
claim barred by the CDA's statute of limitations. PMTech
is noteworthy not so much for its specific holding (denying
the plaintiff's challenge to the Government's override of the
automatic stay during a bid protest) but rather for its
thorough discussion of the legislative history, case law,
and standards for deciding whether an override decision
is justifiable. CRAssociates
succeeded in convincing the court that there were a number
of prejudicial errors in the agency's price, technical, and
past performance evaluations that justified an injunction even
though the protester lost on several other grounds of its
protest (e.g., OCI, flawed responsibility determination,
misplaced price information in the technical proposal). |
| October 25 |
DFARS
Case 2009-D002 (the companion case to FAR Case 2005-040)
is an interim rule amending DFARS 219.708 and 252.219 to
provide DoD-specific procedures and policies related to DoD’s
implementation of the Electronic Subcontracting Reporting
System (eSRS). Comments are due by December 27.
DFARS
Case 2007-D002 is an interim rule amending the DFARS to
implement section 3504 of the National Defense Authorization
Act for Fiscal Year 2009, which addresses requirements (e.g.,
holding either a transportation security card or a Merchant
Mariner's Document and/or passing a background check) that
apply to riding gang members (i.e. foreign nationals
who perform work while the ship is underway beyond standard
vessel maintenance and repair) and other
DoD-exempted individuals performing work on U.S. flag vessels
under DoD contracts for transportation services. Comments are
due by December 27. |
| October 21 |
In JRS
Management, the ASBCA held that laches barred a
contractor's claim even though the CDA's statute of
limitations was not applicable.
HUD's
Federal Housing Finance Agency has issued final rules
implementing the EAJA
for eligible prevailing parties in adjudications against it. |
| October
20 |
OMB's OFPP
proposes to amend 48
C.F.R. Part 9903 to eliminate an exemption from the Cost
Accounting Standards for contracts executed and performed
entirely outside the United States, its territories, and
possessions. Comments are due by December 20. |
| October 16 |
In Tekkon
Engineering Co. , the ASBCA held that (i) the contractor
did not prove the elements required to establish a prior
course of dealing; (ii) the contractor was not entitled to
adjustments under the EPA clause, in part because there were
no established prices on which to base those adjustments;
(iii) the contractor's subjective, unexpressed reading of the
contract, which was never communicated to the Contracting
Officer, could not form the basis for its interpretation; and
(iv) because the Government was not required to place any
orders during an option period (and did not do so), the
contractor could not recover costs associated with that option
period. |
| October 15 |
The GAO
sustained Total
Health Resources' protest that a
solicitation requirement for two years' experience by the
prime was unduly restrictive because the agency could not
establish the requisite experience by a subcontractor or team
member would not be sufficient. |
| October 14 |
The
GAO sustained the protest of Douglas
County Fire District #2 because the agency unreasonably
rated the protester's proposal as "fail" in the
"geographic coverage" evaluation factor even though
(i) it offered to provide the same geographic coverage as it
had successfully provided under the predecessor contract and
(ii) its proposal language was similar to the awardee's, which
the agency rated as "pass."
FTR
Case 2010-306: Effective November 15, the GSA is revising
the FTR by (i)
removing section 301–50.8, which contains language regarding
limitations on travel arrangements for common carriers,
commercial lodging, and car rental usage; (ii) revising (a)
section 301–10.105 regarding the basic requirements for
using common carrier transportation and (b) section 301–10.450
to provide guidance to travelers regarding renting vehicles
under the Defense Travel Management Office’s (DTMO) U.S.
Government Car Rental Agreement; (iii) revising section 301–11.11
to provide guidance to travelers who choose to obtain
commercial lodging under a government lodging agreement; and
(iv) updating references in section 301–73.106 and Appendix D to Chapter
301 to change "Surface Deployment Distribution
Command" (SDDC) to "Defense Travel
Management Office" (DTMO). |
| October 13 |
The
Court of Federal Claims held that The
Marquardt Co. was not entitled to either CDA or PPA
interest on the time required for Government to make payments
under a global settlement agreement of various underlying
contracts because the agreement was not a contract within the
meaning of those statutes, because it did not provide for a
definite time for payment to be made, and because it provided
a different remedy if payment were not made.
In
United
Partition Systems, after concluding that the contractor
was entitled to an EAJA award because the Government's
position in the litigation was not "substantially
justified," the court noted that the "precise
question at hand is whether an expenditure listed as a 'cost'
under 28 U.S.C. § 1920 is recoverable as an 'expense' under
28 U.S.C. § 2412(d)(1)(A), particularly in an instance where
'costs' were not awarded to the plaintiff." The court
held that it is.
In
International
Industrial Park, the court held that because a barter
agreement for the relocation of an easement in return
for an undertaking to pave roads on the easement was not a
contract within meaning of the CDA, the plaintiff was not
required to file a claim with the Contracting Officer prior to
filing suit in court. |
| October 11 |
In System
Planning Corp., the Court of Federal Claims held that the
Tucker Act's six-year Statute of Limitations does not apply to
claims by a contractor who has elected to proceed under the
CDA. |
| October 8 |
In Powerhouse
Design Architects & Engineers, the GAO sustained a set
of protests because the VA failed to follow the requirements
of the Veterans Benefits, Health Care, and Information
Technology Act of 2006, which required it to set aside
architect-engineering services procurements for SDVOSBs. |
| October 7 |
In a final
rule published today, and effective February 4, 2011, the SBA
is making extensive amendments to (i) 13 C.F.R. Part 127,
currently entitled ‘‘Women-Owned
Small Business Federal Contract Assistance Procedures,’’
and (ii) other parts of the SBA's regulations affected by
these changes, all in order to implement procedures authorized
by the Small Business Act (Pub. L. 85–536, as amended) to
help ensure a level playing field on which Women-Owned Small
Businesses can compete for federal contracting opportunities.
As revised, Part 127 will be entitled "Women-Owned Small
Business Federal Contract Program."
FAR
Case 2009-041 (Sudan Waiver Process): A proposed rule
would amend FAR section 25.702 (Prohibition on Contracting
with Entities that Conduct Restricted Business Operations in
Sudan) to add specific criteria an agency must address in a
waiver request and a waiver consultation process regarding
foreign policy aspects of the waiver request for
consultations. This information will be provided, in a waiver
request, to the President or his appointed designee for
consideration of whether the prohibition on awarding a
contract to a contractor that conducts business in Sudan
should be waived. Comments are due by December 6. |
| October 6 |
As
part of a comprehensive review that will eventually cover all
its size standard categories, the SBA today has published
final rules revising its size standards in multiple categories
within each of three NAICS sector groups: 44-45
(Retail Trade); 72
(Accommodations and Food Services); and 81
(Other Services).
In
Thorington
Electrical and Construction Co., the ASBCA granted the
Government's motion for summary judgment because an
unambiguous release barred the contractor's claim. |
| October 5 |
In Vero
Technical Support, the Court of Federal Claims discussed
the definition of "pending" in applying 28 U.S.C.
1500 to decide whether it had jurisdiction (it did not) over a
bid protest when a prior suit based on the same operative
facts had been dismissed by, but was still within the appeal
period in, a federal district court. |
| October 4 |
The
Small Business Jobs Act of 2010, inter alia, closes
the loophole that had favored HUBZone business during set
asides, and places HUBZone, SDVOSB, and women-owned small
businesses in parity with one another in such situations,
which, in the future, should eliminate GAO and court decisions
like those in the Rice Services protests discussed at the
September 20 entry below. |
| October 1 |
DoD is
proposing to update current policies and procedures to reflect
the
DoD FOIA Program as prescribed by Executive Order 13392.
The changes are intended to ensure appropriate agency
disclosure of information and offer consistency with the goals
of 5 U.S.C. § 552. Comments are due by November 29.
DFARS Case
2009-D037: DoD is proposing to amend the DFARS to to make
electronic distribution procedures a routine part of order
issuance by adding a new "Ordering"
clause (and associated prescription) to establish a
standard method for issuing orders via electronic means.
Comments are due by November 30. |
| September 29 |
Information
Ventures won its GAO protest because the record did not
support the Contracting Officer's determination to make only
one ID/IQ award, rather than multiple awards, under a
solicitation for support services.
In L.A.
Ruiz Assocs., the Court of Federal Claims held it lacked
jurisdiction over a contractor's counterclaim in response to
an affirmative claim by the Government because there was no
showing the two claims arose from the same set of operative
facts, and the contractor had not submitted its counterclaim
to the Contracting Officer for a decision; the court, however,
did find jurisdiction over the contractor's claim for a
declaratory judgment to the effect that Government's
affirmative claim against the contractor was null and void.
In
FloorPro,
the same court found a case was not barred by the Statute of
Limitations because the contractor had diligently pursued its
rights even though circumstances had conspired to drag things
out for many years.
Federal
Acquisition Circular (FAC) 2005-46 has been issued. It
includes the following seven items:
Item I (FAR
Case 2009-007), entitled "Equal Opportunity for
Veterans," is an interim rule amending the FAR to
implement DOL regulations on equal opportunity provisions for
various categories of military veterans. This rule sets forth
revised coverage and definitions of veterans covered under the
Vietnam Era Veterans’ Readjustment Assistance Act of 1972 (VEVRAA)
and includes new reporting requirements established under the
VEVRAA and the Jobs for Veterans Act (JVA). Comments are due
by November 29.
Item II (FAR
Case 2010-012), entitled "Certification Requirement
and Procurement Prohibition relating to Iran Sanctions,"
is an interim rule amending the FAR to implement section 102
and partially implements section 106 of the Comprehensive Iran
Sanctions, Accountability, and Divestment Act of 2010. Section
102 requires certification that each offeror, and any person
owned or controlled by the offeror, does not engage in any
activity for which sanctions may be imposed under section 5 of
the Iran Sanctions Act of 1996, as amended (the Iran Sanctions
Act). Section 106 imposes a procurement prohibition relating
to contracts with persons that export certain sensitive
technology to Iran.. Comments are due by November 29.
Item III (FAR
Case 2008-016), entitled "Termination for Default
Reporting," is a final rule, effective October 29, to
establish procedures for contracting officers to provide
contractor information, such as terminations for cause or
default and defective cost or pricing data, into the Past
Performance Information System (PPIRS) and Federal Awardee
Performance and Integrity Information System (FAPIIS) module
within PPIRS.
Item IV (FAR
Case 2008-008), entitled "Award-Fee Language
Revision," is a final rule, effective October 29,
adopting, with changes, the interim rule amending the FAR to
implement section 814 of the John Warner National Defense
Authorization Act for Fiscal Year 2007 (Pub. L. 109-364), section 867 of the Duncan
Hunter National Defense Authorization Act for Fiscal Year 2009
(Pub. L. 110-417), and the OFPP Policy guidance memorandum
dated December 4, 2007, entitled "Appropriate Use of
Incentive Contracts."
Item V (FAR
Case 2009-020), entitled "Offering a Construction
Requirement--8(a) Program," is a final rule effective
October 29 which revises FAR subpart 19.8, Contracting with
the Small Business Administration (The 8(a) Program), to
conform to SBA regulations, by changing the location for
submitting offering letters to the SBA for a construction
requirement for which a specific offeror is nominated.
Item VI (FAR
Case 2009-028), entitled "Encouraging Contractor
Policies to Ban Text Messaging While Driving," is an
interim rule amending the FAR to implement Executive Order
13513, issued on October 1, 2009, entitled ‘‘Federal
Leadership on Reducing Text Messaging while Driving,’’
which was issued to demonstrate federal leadership in
improving safety on the nation’s roads and highways, and to
enhance the efficiency of federal contracting by preventing
the unsafe practice of text messaging by federal contractors
while driving in connection with government business and by
promoting economy and efficiency in federal procurement, and
by seeking to prohibit the disruption of government business
and federal
procurement, as a result of unsafe text messaging practices. . Comments are
due by November 29. You've got to be kidding me.
Item VII (FAR
Case 2009-039), entitled "Buy American Exemption for
Commercial Information Technology--Construction
Material," is an interim rule amending the FAR to
implement section 615 of Division C, Title VI, of the
Consolidated Appropriations Act, 2010 (Pub. L. 111–117),
which authorizes an exemption from the Buy American Act for
the acquisition of information technology that is a commercial
item. Comments are due by November 29. |
| September 28 |
In Shawview
Cleaners , the ASBCA held that the contractor was not
entitled to rely on alleged representations by government
employees that the wage determination attached to contract was
just a suggestion and not mandatory.
In Bruce
E. Zoeller, the ASBCA denied the contractor's motions for
sanctions against the Government for failing to produce
discovery documents that the Government was unable to locate. |
| September 27 |
In Charleston
Marine Containers, the CBCA granted the contractor summary
relief based on its interpretation of FAR 52.247-64
("Preference for Privately-Owned, U.S.-Flag Commercial
Vessels") and DFARS 252.247-7023 ("Transportation of
Supplies by Sea") because neither of those clauses nor
anything else in the contract mentioned the possibility that
the contractor would be required to use Priority Two (P2)
service, which is what the Government had demanded of it. |
| September 25 |
DFARS
Case 2010-D015: A new DFARS clause 252.203-7003 (entitled
"Agency Office of the Inspector General") has been
added, which reads as follows: "The agency office of the Inspector
General referenced in paragraphs (c) and (d) of FAR clause
52.203–13, Contractor Code of Business Ethics and Conduct,
is the DoD Office of the Inspector General at the following
address: DoD Office of
the Inspector General, Investigative Policy and Oversight, 400
Army Navy Drive, Suite 1037, Arlington, VA 22202–4704, Toll
Free Telephone: 866–429–8011."
DFARS
Case 2008-D047: This
final rule establishes a standard DoD method of specifying
Government-assigned serial numbers contractually and requires
(i) the contractor (a) to associate these serial numbers with
the Unique Item Identifier (UII) assigned by the contractor
and (b) to register them in the DoD Item Unique Identification
(IUID) Registry along with the UII and (ii) the Government and
the contractor to reach an agreement prior to use of the
serial numbers in constructing the end item UII.
DFARS
Case 2008-D040: This final rule adopts, with changes, the
prior interim rule that implements section 884 of the National
Defense Authorization Act for Fiscal Year 2009, which requires
DoD to ensure that, to the maximum extent practicable, in all
carriage contracts in which a fuel-related adjustment is
provided for, any fuel-related adjustment is passed through to
the person who bears the cost of the fuel to which the adjustment relates.
DFARS
Case 2010-D001 ("Patents, Data, and Copyrights")
is a proposed rule to update text on patents, data, and
copyrights in order to (i) remove text and clauses that are
obsolete or unnecessary; (ii) relocate and integrate the
coverage for computer software and computer software
documentation with the coverage for technical data to
eliminate redundant coverage for these subjects; (iii)
eliminate or combine the clauses associated with technical
data and computer software, consistent with the revised and
streamlined regulatory coverage; (iv) relocate, reorganize,
and clarify the coverage for rights in works; and (iv)
relocate to the DFARS companion resource, Procedures,
Guidance, and Information (PGI), text that is not regulatory
in nature and does not impact the public. Comments are due by
November 26.
FAR
Case 2009-043 ("Time-and-Materials (T&M) and
Labor-Hour (LH) Contracts for Commercial Items"): This
proposed rule would amend the FAR to implement recommendations
of GAO
Report 09–579 ("Minimal Compliance with New
Safeguards for Time-and-Materials Contracts for Commercial
Services and Safeguards Have Not Been Applied to GSA Schedules
Program") Comments are due by November 26.
FTR
Case 2010-305: This final rule amends the FTR by (i) updating statutory
references in a number of sections, (ii) providing additional
guidance for determining distance measurements when traveling
by privately owned aircraft, (iii) clarifying provisions
regarding the use of personally owned vehicles for official
travel, (iv) updating the addresses to which per diem review
requests should be sent, and (v) changing the method by which
agencies must report the use of government aircraft to carry
senior federal officials and non-federal travelers.
In DLT
Solutions , the CAFC reversed the prior
ASBCA decision and held that, following the termination of
the contractor, the Government did not replace contracted-for
software in violation of a delivery order's Non-Substitution
clause. |
| September 24 |
In the latest decision in the Turner
Construction Co. OCI case, the Court of Federal Claims
denied the intervenor's request to stay the injunction issued
in the court's
prior decision pending an appeal to the Federal Circuit. |
| September 23 |
Vanguard
Recovery Assistance, Joint Venture won its GAO protest
because the agency's past performance evaluation was
based on a numerical scoring system that reduced the offeror's
overall rating because it submitted additional information on
two less relevant contracts, even though it received the
highest adjectival rating on each of the individual contracts
it submitted. |
| September 22 |
FAR
Case 2009-034 ("TINA Interest Calculations"): A
proposed rule would amend the FAR to revise the
clauses at FAR 52.214–27, 52.215–10 and 52.215–11 to
require compound
interest calculations be applied to government
overpayments as a result of defective cost or pricing data.
Comments are due by November 22.
Effective
October 22, the DOE is amending the DEAR to implement E. O.
13514 (Federal Leadership in Environmental, Energy and
Economic Performance) to utilize agency acquisitions to foster
markets for sustainable
technologies and energy efficient and environmentally
sustainable materials, products, and services. |
| September 21 |
Regarding
an EAJA application in Infiniti
Information Solutions, the Court of Federal Claims held, inter
alia, that government contract law was not a legal
specialty justifying an increase in the statutory cap on
hourly attorney rates recoverable under the EAJA. Although
this is not the first court decision to so conclude, I remain
offended. :) The decision includes other interesting issues,
including whether the fact that the GAO originally dismissed
the protest proved the Government's position was substantially
justified (it did not). The court, on its own motion (and with
shaky and speculative reasoning, it seems to me), decided to
reduce the claim for the amount of time one attorney recorded
preparing for oral argument: "The vast majority of work
throughout the case had been undertaken by [two other
attorneys], who were undoubtedly substantially more familiar
with the matter than [the attorney who actually made the oral
argument] was. The court infers that much of [the latter
attorney's] time in preparation for oral argument was spent
becoming familiar with the facts and law of the case for the
first time. Because no explanation was given for why [the
other two attorneys] could not deliver the argument
themselves, the court finds that half of the 23.3 hours spent
in preparation for oral argument were not 'reasonably
expended.' " |
| September 20 |
The SBA's
OHA has issued one new NAICS code decision and two size
decisions. In Brian
Scott, the OHA decided that NAICS code 113310 (Logging)
rather than 561760 (Landscaping Services) was appropriate for
a forestry services contract for harvesting wood products.
In
Gulf-Shred, Inc. dba Shred-It Mobile/Biloxi, the OHA
reversed the Area Office's determination because the indemnity
provision in a franchise agreement did not create an
affiliation between the franchisor and the franchisee and
because the franchise agreement did not give the franchisor
the power to control the franchisee. In Southeastern
Protective Services, the OHA rejected a firm's attempt to
ignore certain income stated on its tax returns based on its
erroneous allegation that it was engaged in a joint venture
rather than a prime/sub relationship, which is what all the
documents (and its own prior admissions) established.
Rice
Services won two GAO protests, each in summary fashion,
because the Air
Force and the Defense
Commissary Agency failed to consider whether an SDVOSB
set-aside should be reserved for HUBZone concerns. |
| September 18 |
The
GAO is requesting public comments (by November 22) on proposed
changes to the exposure draft of proposed revisions to Government
Auditing Standards (GAGAS) (also known as the Yellow Book). |
| September 17 |
DFARS
Case 2009-D023: A proposed rule would amend DFARS Appendix F (Material Inspection and
Receiving Report) to incorporate procedures for using the
electronic Wide Area Workflow Receiving Report required for
use in most contracts in lieu of the DD Form 250, Material
Inspection and Receiving Report. Comments are due by November
16.
CS-360,
LLC filed a pre-award protest claiming that the agency
unreasonably delayed restoring it to the VIP database of
eligible firms after it resolved the agency's concerns with
its status, but the Court of Federal Claims held that the
agency's subsequent determination that the plaintiff was not
eligible as an SDVOSB on different grounds meant the plaintiff
lacked standing because it was not eligible for consideration
for award, and, therefore, the court lacked jurisdiction. |
| September 15 |
Biblia
won its GAO protest because the agency did not document the
basis for its "best value" evaluation.
The Court
of Federal Claims rejected the Madison
Services' motion for post-judgment relief from the prior
adverse decision on its protest: "Throughout the
proceedings in this case, plaintiff has doggedly employed a
shotgun approach (unfortunately a trend in modern litigation)
spraying about as many arguments as can be made no matter the
worth. It is as if plaintiff is following Mason Cooley’s
aphorism: 'If you at first don’t succeed, try again, and
then try something else.' . . . Clearly, quantity does not
always equate with quality. The second motion before the court
is plaintiff’s self-styled 'Motion to Compel Production of a
Complete Administrative Record.' . . . Therein, plaintiff is
essentially moving for post-judgment discovery so as to lay a
foundation to support the rickety edifice of the [affidavit in
support of its first motion] and plaintiff’s unsupported
attorney arguments. However, no matter how lucrative the catch
might be, the law will not support a fishing
expedition." [citations omitted]
The court
rejected arguments by Chenega
Management that the evaluators were biased, that they did
not evaluate offerors on a fair and equal basis, that they
were unqualified as evaluators, and that an illegal gratuity
had been accepted by a cognizant government
official.
The
Sheridan Corporation fared much better in its protest when
the court found that the agency's proposed corrective action
in response to a GAO protest had been filed was improper.
Though the agency's requirements had not changed, the agency
proposed to broaden the former competitive range and
solicit revised proposals. The court found the corrective
action prejudiced the original awardee after its prices had
been exposed and was unnecessary. |
| September 11 |
The
Department of Homeland Security (DHS) is considering a lengthy
set of proposed changes to its acquisition
regulation (HSAR), 48 C.F.R. Parts 3001-3053, to align existing content with the
FAR; to implement Section 695 of the Post-Katrina Emergency
Management Reform Act of 2006; to clarify agency acquisition
regulations; to provide editorial corrections; and to comply
with the statutory change restricting the length of certain
noncompetitive contracts entered into by DHS to facilitate the
response to or recovery from a natural disaster, act of
terrorism, or other manmade disaster. Comments are due by
November 12. |
| September 10 |
In an
interesting CDA decision, the CBCA denied the Government's
motions to dismiss for lack of jurisdiction in Rockies
Express Pipeline. The Board found that a duly executed
"Precedent Agreement" (in which the Government
agreed to execute transportation contracts with the contractor
if the contractor would build a pipeline) was a contract
within the meaning of the CDA. The Board also found that a
Disputes clause purporting to give exclusive jurisdiction in
federal district court "to the fullest extent allowed by
law" must give way to the CDA's choice of forums.
In Wackenhut
Services, the GAO caught the agency trying to make a silk
purse from a sow's ear by evaluating a management approach
prohibited by the solicitation as an attribute that exceeded
the solicitation's requirements. |
| September 9 |
In Ceres
Gulf, Inc., the Court of Federal Claims denied a protest
by the prior awardee after the court found that the Army's
decision to take corrective action in response to a GAO
protest (by rescinding the original award, revising the
solicitation, and then soliciting another round of offers) had
a rational basis because it was reasonable to conclude the
agency had not engaged in meaningful discussions due (in part)
to ambiguities in the original solicitation.
Powersolv
won its GAO protest because the evaluation of the protester's
project manager was inconsistent with solicitation's
evaluation scheme and because there was no evidence in the
record to demonstrate that the agency meaningfully evaluated
price in making its award decision. |
| September 8 |
Several
DFARS changes have been published.
DFARS
Case 2009-D028 ("Guidance on Personal Services")
is an interim rule that
revises DFARS Parts 211 and 237 to enable further
implementation of section 831 of the Duncan Hunter National
Defense Authorization Act for Fiscal Year 2009, which requires
DoD to develop guidance related to personal services
contracts. Comments are due by November 8.
DFARS
Case 2009-D014 ("Acquisition Strategies To Ensure
Competition Throughout the Life Cycle of Major Defense
Acquisition Programs") adopts as final, without changes,
the interim rule amending Part 207 of the DFARS to implement
the Weapon Systems Acquisition Reform Act of 2009, to improve
the organization and procedures of DoD for the acquisition of
major weapon systems.
DFARS
Case 2008-D023 ("Additional Requirements Applicable
to Multiyear Contracts") adopts as final, with only minor
editorial corrections, the interim rule amending subsections
217.170 and 217.172 of the DFARS to implement the National Defense
Authorization Act for Fiscal Year 2008, section 811, entitled
"Requirements Applicable to Multiyear Contracts for the
Procurement of Major Systems of the Department of Defense."
DFARS
Case 2009-D035 ("Payment of Costs Prior to
Definitization--Definition of Contract Action")
adopts as final, without change, the interim rule amending
Part 217.7401(a) of the DFARS by changing the definition of
"contract action" to include task orders and
delivery orders.
DFARS
Case 2008-D039 ("Government Rights in Design of DoD
Vessels") adopts as final, without change, the interim
rule amending Parts 227 and 252 of the DFARS to implement section 825 of the Duncan
Hunter National Defense Authorization Act for Fiscal Year 2009
and the Vessel Hull Design Protection Amendments of 2008,
which clarifies the Government’s rights in technical data in
the designs of a DoD vessel, boat, craft, or components
thereof.
FAR
Case 2009-029 ("Clarification of Standard Form
26--Award/Contract") is a proposed rule to amend the FAR
to to revise (i) the header for blocks 17 and 18 and
(ii) block 18 of the Standard Form 26 to clarify that block 18
should not be used when awarding a negotiated procurement and
should only be checked when awarding a sealed-bid contract.
Comments are due by November 8.
The Bureau
of Industry and Security ("BIS") is seeking public
comments by October 8 on how existing foreign policy-based
export controls have affected exporters and the general public
as part of the BIS's review of the foreign policy-based export
controls in the Export
Administration Regulations to determine whether they
should be modified, rescinded or extended. |
| September 6 |
Effective
September 7, the Department of Commerce's Bureau of Industry
and Security (BIS) is revising the Commodity Control List
(CCL) of the Export Administration Regulations (EAR) to
implement changes made to the Wassenaar
Arrangement’s List of Dual Use Goods and Technologies
(Wassenaar List) maintained and agreed to by governments
participating in the Wassenaar Arrangement on Export Controls
for Conventional Arms and Dual Use Goods and Technologies at
the December 2009 WA Plenary Meeting (the Plenary).
Specifically, the new rule revises the EAR by amending certain
entries that are controlled for national security reasons in
Categories 1, 2, 3, 4, 5 Part I (telecommunications), 6, 7,
and 9, revising reporting requirements, and adding, removing
and amending EAR Definitions. The changes agreed to at the
Plenary that pertain to Export Control Classification Numbers
(ECCNs) 5A002, 5D002, 6A002, 6A003, 8A002 and all related
ECCNs will be implemented in a separate rule. Moreover, the
changes agreed to at the Plenary that pertain to raising the
Adjusted Peak Performance (APP) for digital computers in ECCN
4A003 will be implemented in another separate rule when
the President’s report for High Performance Computers has
been sent to Congress that sets forth the new APP in
accordance with the National Defense Authorization Act for
FY1998.
In
Presidential Determination 2010-13, dated September 2,
President Obama continued for one year the exercise of certain
authorities under the Trading with the Enemy Act with respect
to Cuba,
as implemented by the Cuban Assets Control Regulations at 31
C.F.R. Part 515.
The DoD's
Civilian Personnel Per
Diem Bulletin Number 270 lists revisions in the per diem rates
prescribed for U.S. Government employees for official travel
in Alaska, Hawaii, Puerto Rico, the Northern Mariana Islands
and Possessions of the United States. |
| September 1 |
Nova
Group lost its ASBCA appeals of (i) its Type I and Type II
Differing Site Conditions claims due to insufficient evidence
and (ii) its delay claim because it did not comply with a
contract requirement to present a CPM analysis to support it.
The ASBCA also concluded it lacked jurisdiction to enforce
unilateral modifications the Government had issued to
recoup amounts paid to the contractor because those mods were
not the subject of the contractor's claims or a Contracting
Officer's decision.
Sometimes
the handwriting is on the wall long before the decision on the
merits. In Eyak
Technology, the CBCA denied DHS' motion to dismiss an
appeal for lack of jurisdiction. The Government had relied on
the fact that the complaint requested, inter alia,
specific performance and injunctive relief. The Board replied:
"DHS neglects to refer to Eyak’s prayer for damages
resulting from DHS’s actions. We may grant or deny Eyak’s
request for an equitable adjustment to the contract resulting
from DHS’s actions in this matter. While this alone provides
a basis to deny DHS’s motion, we note that we are not
limited to granting only the relief sought in the complaint. .
. . .In reaching the decision on damages, the Board is likely
to interpret the contract and determine the validity of the
three contract modifications in issue. The net effect of a
favorable determination for Eyak could well provide the relief
that Eyak desires. The failure of Eyak to properly articulate
the remedy available from the Board does not deprive us of
jurisdiction over this matter." You get the drift, DHS? |
| August 31 |
FAR
Case 2009-038: The FAR Council plans to hold tribal
consultation and outreach meetings in October to discuss
rulemaking associated with section 811 of the National Defense
Authorization Act for FY 2010, Public Law 111-84, which addresses requirements
for the justification and approval of sole-source contracts
over $20 million under the 8(a) small business development
program.
Homesource
lost its protest because the Court of Federal Claims found it
failed to establish prejudice (and, therefore, lacked
standing). Specifically, the protester's evaluation scores
were so low that it would not have been in line for award even
if it had prevailed on the merits. Just to be safe, the court
also examined the protest on the merits and denied the
protester's challenges to the past performance and technical
evaluations. |
| August 30 |
The SBA's
OHA has issued several new decisions:
In Reese
Goel JV, the OHA held it lacked jurisdiction to hear an
appeal from determination by the VA's Office of Small and
Disadvantaged Business Utilization.
In Colamette
Construction Co., the OHA reversed the Area Office's
finding of a violation of the ostensible subcontractor rule:
"[T]here is
no evidence of unusual reliance because [the alleged
ostensible subcontractor] is performing only 3% of the
anticipated value of the contract. Second, other than the
evidence concerning the shared indemnity, and perhaps the
evidence that [the alleged ostensible subcontractor] provided
limited assistance with Appellant’s bid preparation, I can
find no evidence that is even arguably probative that [the
alleged ostensible subcontractor] may be Appellant’s
ostensible subcontractor for the instant procurement. When I
weigh [the alleged ostensible subcontractor's] agreement to
indemnify the surety against Appellant’s extensive industry
experience and [the alleged ostensible subcontractor's]
limited role in performing the . . . contract, I find the
issue of indemnification to be an outlier and thus not
probative of a violation of the ostensible subcontractor
rule." The OHA also found that the Area Office had
confused general affiliation tests with an ostensible
subcontractor analysis: "[T]he fact that Appellant leases
office space or receptionist services from [the alleged
ostensible subcontractor] is irrelevant under an ostensible
subcontractor rule analysis."
In another
interesting size appeal, the OHA held in The
Clement Group that the Area Office's finding of
affiliation through negative control was improper because,
under Alabama law, the 51% owner could remove directors for
cause if they attempted to prevent action by refusing to
attend meetings, thereby denying a quorum.
In Speegle
Construction, the OHA upheld the Area Office's finding of
affiliation due to identity of interest between family members
because there was insufficient evidence of a clear fracture
(the challenged family member was a Vice President with, among
other things, the power to control the firm upon the absence
or inability of its President).
The GSA
has published Per
Diem Bulletin 11-01 updating per diem travels rates for
CONUS for fiscal 2011.
DFARS
Case 2009-D018 ("Warranty Tracking of Serialized
Items") is a proposed rule to amend the DFARS to
implement a policy memorandum of the Undersecretary of Defense
for Acquisition, Technology, and Logistics dated February 6,
2007, that required definition of the requirements to track
warranties for items subject to Item Unique Identification in
the Item Unique Identification registry as an aid to
enforcement of warranties, which is essential to the
effectiveness of DoD’s material readiness. Comments are due
by October 29.
FAC
2005-45 has been published and includes the following
three items:
FAR
Case 2008-024 ("Inflation Adjustment of
Acquisition-Related Thresholds") is a final rule
effective October 1 amending the FAR to implement section 807
of the Ronald W. Reagan National Defense Authorization Act for
Fiscal Year 2005, which requires an adjustment every 5 years
of acquisition-related thresholds for inflation using the CPI
for all urban consumers, except for Davis-Bacon Act, Service
Contract Act, and trade agreements thresholds. The FAR
Councils have used the same methodology to adjust nonstatutory
FAR acquisition-related thresholds in 2010.
FAR
Case 2005-036 ("Definition of Cost or Pricing
Data") is a final rule effective October 1 amending the
FAR to clarify the distinction between "certified cost or
pricing data" and "data other than certified cost or
pricing data," and to clarify the requirements for the
submission of cost or pricing data.
FAR
Case 2009-008 ("American Recovery and Reinvestment
Act of 2009--Buy American Requirements for Construction
Materials") is a final rule effective October 1,
adopting, with changes, an interim rule amending the FAR to
implement section 1605 of the American Recovery and
Reinvestment Act of 2009. |
| August 27 |
DFARS Case
2008-D011: DoD has delayed
confirmation of the interim rule discussed in the August 20
entry below as a final rule to allow consideration of public
comments that had been misplaced.
The SBA is
considering granting a class waiver of the nonmanufacturer
rule for woven and knit impregnated with flat dipped
rubber/plastic gloves, under NAICS
code 315992 (Glove and Mitten Manufacturing). Comments are
due by September 13.
The SBA
also is considering granting a class waiver of the
nonmanufacturer rule for Optical Instrument and Lens
Manufacturing, specifically GEN II and GEN III Image
Intensifier Tubes, Product Service Code (PSC) 5855, and Night
Vision Equipment, Emitted and Reflected Radiation, under NAICS
code 333314 (Optical Instrument and Lens Manufacturing).
Comments are due by September 13.
The State
Department has issued an amendment to the ITAR to clarify that
an exemption
for technical data includes technical data, regardless of
media or format, sent or taken by a U.S. person who is an
employee of a U.S. corporation or a U.S. Government agency to
a U.S. person employed by that U.S. corporation or to a U.S.
Government agency outside the United States.
The State
Department also amended the ITAR to remove the requirements
for prior
approval or prior notification for certain proposals to
foreign persons relating to significant military equipment. |
| August 24 |
In its
latest decision in the long-running L-3
Communications Integrated Systems protest (based on the
Druyun fiasco), the Court of Federal Claims denied the
Government's motion to dismiss the protester's claim for
breach of the implied contract of fair dealing. Specifically,
the court held that, contrary to the Government's view, the
Federal Circuit's recent decision in Resource
Conservation Group did not "preclude a plaintiff
either from claiming a breach of the implied contract of fair
dealing in a bid protest or from relying on [28 U.S.C.] §
1491(a) as a predicate for jurisdiction in a bid protest
involving a procurement." |
| August 23 |
The
Department of Education is proposing to reissue its acquisition
regulation (the "EDAR") to update it to comply
with current FAR and Education Department policies and
requirements. Comments are due by September 22.
Executive
Order 13549 of August 18, 2010, establishes (and provides
details of) a Classified
National Security Information Program designed to
safeguard and govern access to classified national security
information shared by the Federal Government with State,
local, tribal, and private sector entities.
The CBCA
denied Springcar's motion
to re-open the record and reconsider the Board's prior
decision because (i) the Board could rely on a
quantum exhibit in the record to which the contractor had not
objected, especially when the contractor had the opportunity
to, and did not, question a hearing witness about its
methodology, and (ii) and the fact that the contractor
allegedly had been "surprised" by testimony at the
hearing did not excuse its failure to pursue the subject at
the time, especially because the person identified in the
testimony had been on the Government's discovery list. |
| August 21 |
In Pitney-Bowes
Government Solutions, the Court of Federal Claims
denied the protester's challenges to various aspects of
the evaluation: the protester did not establish bias from a
COTR's past friendly relationship with awardee; the evaluators
could use their personal knowledge of the incumbent's past
performance issues in making their evaluation; and recovery of
improperly destroyed evaluation materials from back-up tapes
was sufficient to overcome an allegation of spoliation. |
| August 20 |
FMR
Case 2010-102-2: The GSA has amended the Federal Management Regulation (FMR) by updating its coverage on transportation
management.
DFARS
Case 2008-D011: DoD has adopted as final (without changes)
the interim rule that amended the DFARS to implement sections
805 and 815 of the National Defense Authorization Act for
Fiscal Year 2008 by specifying when time-and-materials or
labor-hour contracts may be used for the acquisition of
commercial items, and revising the language to address the
conditions under which major weapon systems or subsystems may
be treated as commercial items. [However, subsequently, the
DoD delayed the final adoption--see August 27 entry
above]
DFARS
Case 2003-D028: DoD has issued a final rule extensively
updating and revising Part 247 ("Transportation") of
the DFARS concerning transportation issues under DoD
contracts. |
| August 18 |
In Navarro
Research and Engineering, the Court of Federal claims held
that 41 U.S.C. 253j(d)'s requirement for a post-award
debriefing (and other enhanced competition procedures) on
solicitations for large task order contracts does not apply to
GSA FSS solicitations.
In
BLR
Group of America, on reconsideration of its prior
decision, the Court of Federal Claims dismissed the
contractor's suit for lack of jurisdiction because the
contractor's written objections to an unfavorable CPAR did not
constitute a CDA claim. There was no demand for a decision by
the Contracting Officer, and the Contracting Officer
reasonably interpreted the submission as comments submitted
pursuant to FAR § 42.1503(b). It should be noted that the case does not stand for
the proposition that an objection to a CPAR evaluation can
never be a CDA claim--only that the contractor's submission in
this case was not sufficient to identify itself as a such a
claim.
Two
PSBCA decisions have
been published. In an unusual default termination appeal, the
Board upheld the termination of a mail deliverer because,
basically, he could not get
along with other Postal employees. |
| August 17 |
FAR Case
2009-023: a proposed rule would standardize the use of Unique
Procurement Instrument Identifiers (PIIDs) throughout the
Government and extend the requirement for using PIIDs to all
solicitations, contracts, and related procurement instruments.
Comments are due by October 18. |
| August 16 |
In the DGR
Associates protest, the Court of Federal Claims castigated
the Air Force in the strongest possible language for ignoring
the GAO and court's views and the applicable statute in
awarding a contract as an 8(a) set-aside without considering
giving preference to a HUBZone procurement when there was a
reasonable likelihood that two or more qualified
HUBZone firms would submit offers and award could be made at a
fair and reasonable price. The court overturned
the award and required to agency to consider the HUBZone
procurement before proceeding further. The court also rejected
the agency's allegation that the protest was untimely under Blue
& Gold, Fleet because it was filed after proposals
were due. The court noted that the protester (i) had initially
filed a timely GAO protest, which satisfied the timeliness
requirement and (ii) was in court only because the agency had
ignored the GAO's decision in favor of the protester. |
| August 14 |
DFARS Case
2006-D057 (Excessive Pass-Through Charges): a correction
has been issued to the final rule (discussed at the August 10
entry below), which had incorrectly removed and reserved two
C.F.R. sections. |
| August 13 |
The ASBCA
published its July decisions in a bundle.
In Kaman
Precision Products, the Board refused the Government's
request to stay proceedings on an appeal from a default
termination (and related claims) during the pendancy of an FCA
claim against the contractor in district court. The Board
reasoned that the stigma associated with a default termination
that did not involve the allegations in the FCA suit
outweighed the Government's interest in the stay. (The Board
did permit a brief stay on one issue directly related to the
FCA suit).
The Board
dismissed Corners
and Edges' appeal on the bases of res judicata and
collateral estoppel. It also denied the Government's motion
for reconsideration in Job
Options because the Government merely rehashed arguments
it already had made.
In The
Minesen Co., the Board dismissed an appeal because the
agency's allegedly continuing failure to cure an alleged
breach at issue in another pending appeal did not create new
claim that could be appealed separately.
In Thorington
Electrical and Construction Co., the Board denied a
performance and payment bond surety's motion to intervene in
an appeal because the surety was not a contractor with respect
to the claims involved in the appeals.
In J.
P. Donovan Construction., the Board dismissed the entire
claim as lacking a sum certain because the contractor stated
it would be adding an approximate amount of G&A expenses
onto its subcontractor's sum certain claim.
In United
Healthcare Partners, the Board held that, despite the fact
that a solicitation was labeled as an "RFQ,"
repeated and clear language in the document indicated the
requested quote would become part of a bilateral contract. The
Board noted that the Government's contrary view would result
in an unreasonable interpretation that would permit it to
order a significant number of increased services for free.
Senate
Builders & Construction Managers involves a
construction contract and issues of contract
interpretation, as well as a finding that the contractor
failed to make timely inquiry concerning a patent ambiguity in
the specifications.
In Northrop
Grumman Systems Corp, Space Systems Division, the Board
held that (i) an alternative legal theory first raised in
post-hearing briefs but based on the same operative facts as
the theory in original claim was not a new claim; (ii) it
lacked jurisdiction over an "improper exercise of
option" claim because that claim was not encompassed by
the claim submitted to the Contracting Officer; and (iii) a
portion of an appeal involving allegations not stated in a sum
certain was severable from the remainder of claim and,
therefore, did not require dismissal of the entire claim.
Turning to the merits, the Board found that no government
actions or inactions (including remaining silent and nodding
during the contractor's presentation and shaking hands with
him afterwards) created a binding contract.
In General
Dynamics Ordnance and Tactical Systems, the ASBCA held it
had the authority to (and, therefore, did) grant appellant's
request for a protective order allowing it access to certain
discovery materials involving trade secrets, but then stayed
that decision for 60 days to allow the Government to assess
its litigation options, including a possible appeal to the
Federal Circuit.
Anybody
else remember the good old days (around the time I routinely
walked ten miles to school barefoot in the snow) before the
"improvements" wrought by the CDA, when the vast
majority of board decisions were on the merits? |
| August 12 |
The
Interior Department has adopted as final an interim rule
amending its Acquisition Regulation (the
"DIAR") at 48 C.F.R. Chapter 14.
GSAR
Case 2008-G511: Effective September 13, the GSA is
amending GSAR Part 541 (Acquisition of Utility Services) by
adding two clauses specific to utility services: the
"Availability of Funds" clause, which replaces the corresponding
FAR clause, and the "Disputes" clause, which
supplements the FAR clause. |
| August 11 |
The State
Department proposes to amend the ITAR to relax requirements
placed on end-users to include information concerning
employment of dual-nationals
and third-country nationals in export licenses. Comments
are due by September 10.
The SBA
has issued a final rule to permanently adopt the current
temporary size standard implemented under the American
Recovery and Reinvestment Act that is now in effect through
September 30, 2010 for the Surety
Bond Guarantee Program, which provides that a business
concern is small if such concern, combined with its
affiliates, does not exceed the size standard for the NAICS
code that corresponds to the primary industry of the business
concern combined with its affiliates. |
| August 10 |
DFARS Case
2008-D034 (Management of Unpriced Change Orders) is a final
rule that adds new policy to address section 812 of the
National Defense Authorization Act for Fiscal Year 2010
by amending the DFARS to make requirements for DoD
management and oversight of unpriced
change orders consistent with those that apply to other
undefinitized contract actions.
DFARS Case
2006-D057 (Excessive Pass-Through Charges) is a final rule to delete the interim
DFARS language implementing section 852 of the National
Defense Authorization Act for Fiscal Year 2007 (which requires
that pass-through
charges on contracts or subcontracts that are entered into
for or on behalf of DoD are not excessive in relation to the
cost of work performed by the relevant contractor or
subcontractor) because the interim language was made obsolete
with the publication of the FAR interim rule at 74 FR 52853 on
October 14, 2009.
DFARS Case
2009-D024 (Reporting of Commercially Available Off-the-Shelf
Items that Contain Specialty Metals--Deletion of Obsolete
Clause) is a final rule amending the DFARS to delete the requirement for contractors to
report commercially available off-the-shelf items that contain
foreign
specialty metals and are incorporated into noncommercial
end items.
In its
decision on quantum, the Court of Federal Claims awarded Englewood
Terrace Limited Partnership contract damages for HUD's
breach of a housing assistance payment (HAP) contract but
rejected the contractor's claim for "lost equity
damages" for failure of proof. In Peninsula
Group Capital Corp., the same court found it lacked
jurisdiction over a dispute because the parties had never
finalized a written contract at the conclusion of
negotiations. In Croman
Corp., the court refused to allow the Government to
re-open discovery six months after it had closed, in order to
explore possible fraud counterclaims the Government claimed it
belatedly noticed in reviewing responses to the original
discovery requests. |
| August 7 |
In PAI
Corp. v. United States , the Court of Appeals for the
Federal Circuit affirmed the Court of Federal Claims' opinion
and denied a claim that the procuring agency had failed to
follow applicable regulations in documenting and mitigating
organizational conflicts of interest because the Contracting
Officer reasonably determined (after certain corrective
actions had been completed) that no "significant"
conflict of interest remained. |
| August 6 |
Effective
September 20, the SBA is extensively revising its rules
of practice at 13 C.F.R. 134 for cases before the SBA's
Office of Hearings and Appeals, inter alia: (i)
to codify the OHA’s longstanding practices on access to
appeal files and protective orders as well as its practice of
citing its prior decisions as precedent; (ii) to permit the
filing and service of pleadings by e-mail; (iii) to limit the
number of pages for each appeal petition unless the OHA
approves otherwise in advance; (iv) to clarify the time period
for filing an appeal; and (v) to
promote the use of alternative dispute resolution procedures.
The DoD has
published Civilian Personnel Per Diem Bulletin Number
269, which lists revisions in the per diem rates
prescribed for U.S. Government employees for official travel
in Alaska, Hawaii, Puerto Rico, the Northern Mariana Islands
and Possessions of the United States.
Is the Court of
Federal Claims going soft on us? I still remember the clerk
rejecting one of my filings in the first case I ever tried at
the CoFC's predecessor in the early 80s simply because he did
not approve the aesthetics of the way I bound it. Now, in Gonzalez-McCaulley
Investment Group, the court (over the Government's
objection) has granted one plaintiff leave to amend a
complaint that failed to include many of the jurisdictional
allegations required by the rules for both a CDA claim and a
bid protest. P.S. I finally found a binding that
satisfied the clerk and made the filing on time . . . on my
third try.
In FAS
Support Services, the Court of Federal Claims held that
the Government did not err in refusing to reinstate a bidder
to a competition after the bidder had been (i) suspended and
dropped from the competition because its 49% owner was
de-barred but then (ii) removed from the suspension list after
it divested itself of the de-barred firm. The court noted, inter
alia, that the post-divestiture firm was a significantly
different entity, which was too big a change for the
Government to be required to re-assess in mid-competition.
In Tenderfoot
Equipment Services , the CBCA held it lacked CDA
jurisdiction over appeal based on Government's refusal to
offer services to a firm under an emergency equipment rental
agreement because the agreement was a BPA, which, without
more, is not a contract. |
| August 4 |
Effective
August 19, the SBA is granting a class waiver of the
Nonmanufacturer Rule for Not-Portable, Liquid Chromatography
Mass Spectrometry (CS–MS) Systems, High Performance Liquid
Chromatography (HPLC) Systems, Gas Chromatography Mass
Spectrometry (GC–MS) Systems, and, Inductively Coupled
Plasma Mass Spectrometry (ICP–MS) Systems under Product
Service Code (PSC) 6640 (Laboratory Equipment and Supplies),
under North American Industry Classification System (NAICS)
code 334516
(Analytical Laboratory Instrument Manufacturing).
The State
Department is amending the ITAR to require electronic
submission of a request for a commodity jurisdiction
determination using "Commodity Jurisdiction (CJ)
Determination Form" (Form DS–4076). |
| July 31 |
In the
latest Todd
Construction decision, the Court of Federal Claims held
that, although contractors may have CDA claims against
government performance evaluations that do not comply with FAR
36.201, Todd failed to allege a causal connection between the
Government's alleged procedural flaws in conducting the
evaluation and any injury to Todd (i.e., an error in
the final evaluation rating). The court also concluded there
was no abuse of discretion by the Government in its ultimate
finding that plaintiff's performance was unsatisfactory.
A
mere two and a half weeks after I revised all the case links
on my CAFC contract disputes and bid protest pages to reflect
the web address changes on the court's re-designed website, I
finally realized that I also needed to change all the affected
links in my 2007-present blogs and my 2007-present procurement
reviews. I've now done that. (I've never claimed to be the
quickest draw in the West). |
| July 30 |
Two
Court of Federal Claims decisions on bid protests were
published. In Infiniti
Information Solutions, the court denied a government
motion for relief from the court's prior
decision sustaining a bid protest and directing the
Government to set-aside an improper contract award (the
Government apparently having ignored that prior decision and
having failed to request reconsideration or to appeal within
the required time periods). In Diversified
Maintenance Systems, a protest of an award on a HUBZone
set-aside, the court discussed the standards for allowing
discovery in a bid protest and permitted limited discovery
concerning the issue whether the awardee qualified as a
HUBZone business.
The SBA's
OHA published three size decisions. In Silver
Enterprises Assocs., the OHA affirmed an Area Office size
determination because the probative value of signed statements
provided under penalty of perjury by the challenged firm
outweighed the general allegations of the protester. In Incisive
Technology, the OHA found that a firm's almost total
dependence on subcontracts with one large firm for
revenues created affiliation through economic dependence.
In Condor
Reliability Services, the OHA concluded the Area Office
was correct in finding affiliation by identity of interest
among family members absent evidence of a clear line of
fracture.
The OHA
also decided in United
Medical Design Builders, LLC, that a firm was not
qualified as an SDVOSB because, under its operating agreement,
the service-disabled veteran could not be considered the
managing member of the LLC and did not control its management
and daily business operations. |
| July 29 |
In denying
the Government's motion for summary judgment in ALK
Services, the CBCA noted that ordering the minimum
quantity in an ID/IQ contract does not automatically insulate
the Government from a claim of breach of the covenant of good
faith and fair dealing for failure to consider the
contractor for additional work.
In Scott
Timber, the Court of Federal Claims decided to allow
testimony from a remote site via videoconference from a
witness who was too far from Washington to travel easily to
the hearing. The court also granted a motion to exclude all
other persons from the room from which the witness would be
testifying to avoid any possible prejudice from having
representatives of one party, but not the other, present
during the testimony. |
| July 27 |
AMEC
Earth & Environmental won its GAO protest because the
agency failed to conduct meaningful discussions and treated
offerors unequally in its evaluation. Specifically, the agency
failed to apprise the protester of weaknesses in its proposal
to the same extent the agency did so with all other offerors
and failed to evaluate other offerors' neglect to identify an
issue required by the solicitation that the protester had
reasonably identified based on publicly available information. |
| July 24 |
In G
& R Service Co. , the CBCA dismissed an appeal for
lack of jurisdiction because the underlying demands for
"not-to-exceed" amounts did not constitute a CDA
claim for a sum certain. |
| July 23 |
The GAO
sustained a protest by System
Engineering International because the agency only included
two higher-rated, higher-priced quotations in its
price/technical tradeoff analysis when lower-priced,
lower-rated quotations were technically acceptable.
The Office
of Federal Contract Compliance Programs (OFCCP) is inviting
the public to provide input on how OFCCP can strengthen the
affirmative action requirements of the regulations
implementing section 503 of the Rehabilitation Act of 1973, as
amended in order to help increase the employment
opportunities of people with disabilities in the federal
contracting sector. Comments are due by September 21.
The SBA's
OHA published five size decisions. In Judson
Builders, it affirmed the decision of the Area Office
because, as required by the applicable regulation, the Area
Office relied on tax returns filed by a firm before it
self-certified, instead of amended returns filed after the
initiation of a size determination. In PMTech,
the OHA remanded a case to Area Office for additional findings
because it had not included sufficient information in its
original size determination to enable the OHA to evaluate the
Area Office's conclusions concerning the total average
employee count of the protested firm and its affiliates. In
Specialized
Veterans, the OHA upheld a finding of affiliation through
the totality of circumstances, including the provision of
technical and financial assistance, e.g., enabling the
protested firm to obtain required bonding. In Glen/Mar
Construction, the OHA found a firm whose offer had been
eliminated from competition as technically unacceptable lacked
standing to protest the awardee's size. Similarly, in Reams
Enterprises , a firm whose offer had been eliminated from
competition for reasons unrelated to size lacked standing to
protest the awardee's size. |
| July 22 |
In Office
Design Group, the
SBA's OHA upheld an SBA decision that a firm was not eligible
for the 8(a) business development program because the
disadvantaged individual on whom it based its claimed status
did not hold its highest officer position and a
non-disadvantaged officer received higher compensation than
did the disadvantaged individual. |
| July 21 |
The SBA's
OHA issued one size decision and three VET decisions. In Forterra
Systems, the OHA found affiliation based on the
presumption of ownership and control by two shareholders
holding 28.74% and 17.32% of voting stock (pursuant to 13
C.F.R. 121.103(c)(2)). In the belatedly published, but still interesting,
NEIE
Medical Waste Services, the SBA had dismissed an SDVOSB
eligibility protest as untimely because it was not submitted
within five days of bid opening in a sealed bid procurement.
The OHA remanded the case for a determination whether the
protester was correct in its allegation that, regardless how
the acquisition was labeled, it was not conducted according to
sealed bid procedures. The OHA noted that, if the protester's
allegations were correct, the timeliness rule would not apply.
On the other hand, in Excelsior
Defense, the OHA affirmed a dismissal (as untimely) of a
protest in a negotiated procurement filed more than five
days after receipt of notice from the Contracting Officer of
the apparently successful offeror. |
| July 20 |
Effective
August 4, the SBA is granting a class
waiver of the nonmanufacturer rule for Configured Tape
Library Storage Equipment, Product Service Code (PSC) 7025
Automated Data Processing (ADP) Input/Output and Storage
Devices, PSC 7035 ADP Support Equipment, and PSC 7045 ADP
Supplies, under the North American Industry Classification
System (NAICS) code 334112 (Computer Storage Device
Manufacturing).
The Bureau
of International Labor Affairs in the Department of Labor has updated
the list required by Executive Order No. 13126, entitled
"Prohibition of Acquisition of Products Produced by
Forced or Indentured Child Labor," in accordance
with the "Procedural Guidelines for the Maintenance of
the List of Products Requiring Federal Contractor
Certification as to Forced or Indentured Child Labor," to
set forth the latest list of products, by country of origin,
which the Departments of Labor, State and Homeland Security
have a reasonable basis to believe might have been mined,
produced, or manufactured by forced or indentured child labor.
Federal contractors who supply products on this list are
required to certify, among other things, that they have made a
good faith effort to determine whether forced or indentured
child labor was used to produce the item. |
| July 18 |
In the
important Turner
Construction Co. bid protest decision, the Court of
Federal Claims held that the agency lacked a rational basis
for following a GAO recommendation that the court considered
irrational. The GAO had concluded that an awardee should have
been disqualified for an organizational conflict of interest,
and the agency decided to follow that recommendation. The
awardee then filed suit, and the court found that the GAO had
impermissibly substituted its judgment for the agency's
original judgment concerning the absence of a conflict of
interest. The court's decision is instructive for its
discussion of the various types of OCIs and for its analysis
of the standard of review the GAO should use in assessing an
agency's determination concerning an OCI and the court's
standard of review in assessing both a GAO recommendation and
an agency's decision to follow that recommendation. This one
is headed to the Court of Appeals for the Federal Circuit--see
the September 24 entry above. |
| July 16 |
The Court
of Appeals for the Federal Circuit has re-designed its website,
including the web addresses for its imbedded pages and for the
decisions to which it links, which meant I had to do some
tedious revisions to most of the links to cases on my Federal
Circuit bid
protest and contract
disputes pages, as well as my Courts
page--ugh. I think the updated links are correct, but, if you
spot any link errors, please let me know.
When NASA
complied with the Court of Federal Claims' decision in the
original Wackenhut
protest and corrected errors in the evaluation, it awarded the
contract to Wackenhut. The original awardee, Coastal
International Security, then protested, but failed to
convince the court (i) that the agency's use of a staffing
benchmark instead of an independent government staffing
estimate for part of the technical evaluation was improper or
(ii) that the SSA was required to follow the details of the
SEB's findings. |
| July 15 |
Effective
August 16, the GSA is revising Part
516 ("Types of Contracts") of the GSAR to
clarify the requirements for the use of each type of contract.
HSAR
Case 2009-003 ("Lead System Integrators") is an
interim rule amending the Homeland Security Acquisition
Regulation (HSAR) to implement section 6405 of the U.S. Troop
Readiness, Veterans’ Care, Katrina Recovery, and Iraq
Accountability Appropriations Act, 2007, which restricts
contractors from acting as lead system integrators in the
acquisition of DHS major systems if they have direct financial
interests in the development or construction of any individual
system or element of any system of systems they integrate
(subject to stated exceptions). Comments are due by August 16.
The Bureau
of Industry and Security is issuing a final
rule that (i) updates and clarifies export and reexport
license requirements on striking weapons, restraint devices,
shotguns and parts, optical sighting devices, and electric
shock devices and (ii) adds equipment designed for the
execution of humans to the Commerce Control List. |
| July 14 |
Effective
July 29, the SBA is granting a waiver of the nonmanufacturer
rule for Herbicides,
Insecticides, and Fungicides (PSC 6840, under NAICS code
325320).
The GSA
has issued a proposed rule revising Part 102-38 of the Federal
Management Regulation (FMR) by amending the provisions for the
sale of personal property through Federal
Asset Sales (FAS) Sales Centers. Comments are due by
August 13.
The State
Department's Bureau of Verification, Compliance, and
Implementation has published a list of foreign persons and
firms banned from selling to the Government, receiving FMS
items or services, or obtaining items on the Munitions Control
List because of violations involving the Iran,
North Korea, and Syria Nonproliferation Act. |
| July 13 |
DFARS
Case 2009-D020 is an interim rule amending the DFARS to
bring DoD into compliance with the OMB's implementation of the
Prompt Payment Act by exempting military contingencies, and
certain payments related to emergencies and the release or
threatened release of hazardous substances. Comments are due
by September 13.
DFARS
Case 2009-D036 is an interim rule amending the DFARS
to implement section 814 of the National Defense Authorization
Act for Fiscal Year 2010 (Pub. L. 111–84), which requires
agency heads to notify the congressional defense committees
within 30 days after making any determination to award a task
or delivery order exceeding $100 million to a single source.
In addition, if the task or delivery order concerns DOD
intelligence activities, the agency head also is required to
provide notification within 30 days of the determination to
the Permanent Select Committee on Intelligence of the House of
Representatives if the order relates to tactical intelligence
and intelligence related activities, and to the Select
Committee on Intelligence of the Senate and the Permanent
Select Committee on Intelligence of the House of
Representatives if the order relates to intelligence and
intelligence-related activities other than those activities
previously mentioned. Comments are due by September 13.
DFARS
Case 2009-D033 is an interim rule amending the DFARS to
implement section 820 of the National Defense Authorization
Act for Fiscal Year 2010, entitled ‘‘Publication of
Notification of Bundling of Contracts of the Department of
Defense,’’ which requires DoD contracting officers (i) to
publish a notification consistent with the requirements of FAR
10.001(c)(2) on FedBizOpps.gov, or any successor site, at
least 30 days prior to the release of a solicitation for a
bundled acquisition and (ii) if the DoD agency has determined
that measurably substantial benefits are expected to be
derived as a result of bundling, to include within the
notification a brief description of those benefits. The
acquisitions covered by section 820 are defined at 820(b) as
those that are funded entirely by DoD funds and covered by FAR
7.107. Comments are due by September 13. |
| July 9 |
Three CBCA
decisions were published. In Walsh/Davis
Joint Venture, the CBCA denied the Government's motion to
reconsider the Board's earlier decision refusing to dismiss a
claim for lack of jurisdiction. The Government argued that it
had not been presented to the Contracting Officer for a
decision. The Board concluded it was based on the same
operative facts as a claim that had been. In Pearson
E. Dubar, which the Board described as nonprecedential,
the CBCA dismissed an appeal for lack of jurisdiction because
there was no underlying contract--oral assurances by a
government official who was not a Contracting Officer did not
create a contract. In Global
Ship Systems, the Board dismissed an appeal because the
Government fulfilled terms of a settlement agreement even
though it applied amount owed to contractor to offset the
contractor's debt on another contract. |
| July 8 |
In Lasmer
Industries, the ASBCA held that the Government's
rescission of a claim, which resulted in the Board's dismissal
of the contractor's appeal, did not make the contractor a
"prevailing party" entitled to and EAJA award.
In Colonna's
Shipyard, the ASBCA distinguished what it cannot do (grant
a request for specific performance or injunctive relief, e.g.,
by ordering the Government to change a contractor's
performance rating) from what it can do (determine whether a
particular performance rating breached a contract requirement
or provision).
In ALKAI
Consultants, the ASBCA determined some of the types of
costs that are recoverable under the commercial items
"Termination for Convenience" clause (FAR 52.212-4).
FAC
2005-44 has been published. It includes one item:
FAR
Case 2008-039, entitled "Reporting Executive
Compensation and First-Tier Subcontract Awards," is an
interim rule (whose reporting requirements will be implemented
in phases) that amends the FAR to implement section 2 of
Federal Funding Accountability and Transparency Act of 2006
(Pub. L. 109-82), as amended by section 6202 of the Government
Funding Transparency Act of 2008 (Pub. L. 110-252), which
requires the OMB to establish a free, public, website
containing full disclosure of all federal contract award
information. This interim rule eventually will require
contractors to report executive compensation and first-tier
subcontract awards on contracts and orders expected to be
$25,000 or more (including all options), except classified
contracts and contracts with individuals. This information
will be available to the public. The phased reporting
requirements are as follow. Until September 30, 2010, any
newly awarded subcontract must be reported if the prime
contract award amount was $20,000,000 or more. From October 1,
2010, until February 28, 2011, any newly awarded subcontract
must be reported if the prime contract award amount was
$550,000 or more. Starting March 1, 2011, any newly
awarded subcontract must be reported if the prime contract
award amount was $25,000 or more. Comments are due by
September 7. |
| July 7 |
Allied
Technology Group won a preliminary skirmish in its protest
at the Court of Federal Claims, but lost the war. The court
rejected the Government's argument that the protester lacked
standing because its proposal had been evaluated as
technically disqualified. However, the company lost on the
merits because it was not prejudiced by any of the alleged
errors in the procurement (i.e., it would not have been in
line for award because of its huge price disadvantage). |
| July 6 |
I have
added a page providing an introduction to GAO
protests, including links to successful protests of each
of the most common grounds for protest. |
| July 2 |
FAC
2005-43 has been published. It includes the following five
items:
Item I
(FAR Case 2008-011) entitled "Government Property"
is a final rule effective August 2 amending FAR
Part 45 (Government Property) and its associated contract
clauses.
Item II
(FAR Case 2008-035) entitled "Registry of Disaster
Response Contractors" is a final rule effective August 2
adopting, without changes, the prior interim rule amending the
FAR to implement the Department of Homeland Security
Appropriations Act, 2007, section 697, which requires the
establishment and maintenance of a registry
of disaster response contractors.
Item III
(FAR Case 2010-008) entitled "Recovery
Act Subcontract Reporting Procedures" is an interim
rule revising the FAR clause at 52.204-11 to (i) to require
first-tier subcontractors with Recovery Act funded awards of
$25,000 or more, to report jobs information to the prime
contractor for reporting
into http://FederalReporting.gov
and (ii) to require the prime contractor to submit its first report on or before the
10th day after the end of the calendar quarter in which the
prime contractor received the award, and quarterly thereafter.
Comments are due by August 31.
Item IV
(FAR Case2008-023) entitled "Clarification of Criteria
for Sole Source Awards to Service-disabled Veteran-owned Small
Businesses" is a final rule effective August 2 that
revises the language in FAR 19.1306(a)(1), which deals with
sole source awards to HUBZone small business concerns based on
15 U.S.C. 657a(b), to match the language in FAR 19.1406(a)(1)
to alleviate confusion on the appropriate use of the criteria
needed to conduct a sole source SDVOSB concern
acquisition.
Item V
(FAR Case 2009-040) entitled "Trade Agreements
Thresholds" is an interim rule amending the FAR to
incorporate increased
thresholds for application of the World Trade Organization
Government Procurement Agreement and the Free Trade
Agreements, as determined by the United States Trade
Representative. Comments are due by August 31. |
| July 1 |
The SBA is
considering granting a class waiver of the Nonmanufacturer
Rule for Liquid Chromatography Mass Spectrometry Systems (CS–MS),
High Performance Liquid Chromatography (HPLC) Systems, Gas
Chromatography Mass Spectrometry (GC–MS) Systems, and
Inductively Coupled Plasma Mass Spectrometry (ICP–MS)
Systems under Product Service Code (PSC) 6640 (Laboratory
Equipment and Supplies), under NAICS
code 334516 (Analytical Laboratory Instrument
Manufacturing). Comments are due by July 16.
The DOE is
proposing to (i) remove its Contract
Appeals regulation, which implements DOE’s contract
appeals procedures and (ii) amend the DEAR Subchapters
A--General, B--Acquisition
Planning, and C--Contracting
Methods and Contract Types, to make changes to conform to the
FAR, remove out-of-date coverage, and update references.
Comments are due by August 2. |
| June 30 |
The BIS
proposes to amend the EAR by adding ECCN 6A981 to the CCL to
control passive
infrasound sensors because of their military and
commercial utility. Items under this new ECCN will be
controlled for Regional Stability (RS) and Anti-Terrorism (AT)
reasons. In addition, BIS proposes to control technology and
software for the development, production, or use of these
items for RS and AT reasons under revised ECCNs 6D991 and
6E991, respectively. Comments are due by August 30.
For the
period July 1 through December 31, the Prompt
Payment Act interest rate is 3 1/8%.
The ASBCA
denied the request for reconsideration by American
Renovation and Construction Co. concerning the Board's
earlier decision upholding the Government's revocation of
acceptance of the contractor's work despite its claims of
defective specifications. |
| June 28 |
The Bureau
of Industry and Security has made more changes to the EAR
as a result of its comprehensive review of the CCL.
The
Information Security Oversight Office of the National Archives
and Records Administration has published a Directive as a
final rule implementing E.O. 13526 regarding classifying,
safeguarding, and declassifying national
security information.
In Ron
Anderson Construction Co., the CBCA denied the
Government's motion to dismiss the contractor's appeals for
lack of subject matter jurisdiction. The Board concluded from
the "totality of the circumstances" that a request
for a decision by the Contracting Officer was implied in the
contractor's original cost proposals. |
| June 24 |
Three
ASBCA decisions were published. In Qatar
International Trading Co., the Board denied the
contractor's claim for fraudulent phone charges on illegal
clones of satellite phones the contractor had provided to the
Government. In DWBH
Services, the Board denied a claim that maintaining lawns
in areas where housing was demolished during contract
performance was outside the scope of the contract. The Board
also rejected a contractor's request for a mistrial
based on its contention that the Government, inter alia,
had tampered with the hearing transcript. |
| June 23 |
DFARS Case
2010-D010: DoD has issued an interim rule implementing
revisions to DoD Directive-Type Memorandum 09–019, entitled
"Policy Guidance for Foreign Ownership, Control, or
Influence (FOCI)," which revises the description of communications
security material that is "proscribed information." |
| June 22 |
The GAO
sustained two protests. Contrack
International won its protest because the agency knew of
adverse past performance information concerning the awardee
but failed to consider it. The GAO also sustained a protest
by Brican
Inc. because the agency failed to credit it in the areas
of past performance and experience for proposing the same
subcontractor that the awardee had been rewarded for
proposing. |
| June 21 |
The
CBCA was unpersuaded by a contractor's contentions that its
change of counsel and its counsel's illness excused its
failure to file a timely request to reconsider an order
dismissing an appeal for failure
to prosecute.
DFARS
Case 2008-D024: DoD is adopting as final, with changes, an
interim rule amending the DFARS to implement
determinations made by the Under Secretary of Defense for
Acquisition, Technology, and Logistics with regard to the
acquisition of items containing para-aramid
fibers and yarns manufactured in foreign countries that
have entered into a reciprocal defense procurement memorandum
of understanding with the United States.
DFARS Case
2008-D006 is an interim rule implementing section 828 of the
National Defense Authorization Act for Fiscal Year 2008, which
authorizes the Secretary of Defense to enter into a contract
for a period not to exceed 10 years for the purchase of
electricity from sources of renewable
energy. Comments are due by August 20. |
| June 18 |
In M.
Maropakis Carpentry, the Court of Appeals for the Federal
Circuit, over a vigorous dissent, affirmed the Court of
Federal Claims and held "that a contractor seeking an adjustment of
contract terms must meet the jurisdictional requirements and
procedural prerequisites of the CDA, whether asserting the
claim against the government as an affirmative claim or as a
defense to a government action." More than 30 years after
the effective date of the CDA, we still are embroiled in
disputes like this because the CDA's authors neglected to
define its key term, i.e., a "claim."
In Paradigm
Learning, the Court of Federal Claims held it had CDA
jurisdiction over a claim that the Government breached a
schedule contract by disclosing proprietary information
included in delivered items under the contract in violation of
the contract and a related nondisclosure agreement. In Allstar
Mayflower , the court held that a claim for reimbursement
of PowerTrack Fees under transportation services contracts was
governed by the three-year statute of limitations of the
Interstate Commerce Act rather than by the six-year statute of
the CDA. |
| June 16 |
Federal
Acquisition Circular (FAC) 2005-42 has been published. It
includes the following 11 items plus technical amendments:
Item I
(FAR Case 2009-012) entitled "American
Recovery and Reinvestment Act of 2009--Whistleblower
Protections" is a final rule adopting (with changes)
the interim rule amending the FAR to implement section 1553 of
Division A of the Recovery Act ("Protecting State and
Local Government and Contractor Whistleblowers") by
prohibiting non-Federal employers from discharging, demoting,
or discriminating against an employee as a reprisal for
disclosing information.
Item II
(FAR Case 2005-040) entitled "Electronic
Subcontract Reporting System (eSRS)" is a final rule
amending the FAR to require that contractors’ small business
subcontract reports be submitted using the Electronic
Subcontracting Reporting System (eSRS), rather than Standard
Form 294 - Subcontract Report for Individual Contracts and
Standard Form 295 - Summary Subcontract Report.
Item III
(FAR Case 2009-010) entitled "American
Recovery and Reinvestment Act of 2009--Publicizing Contract
Actions" is a final rule adopting (with changes) an
interim rule amending the FAR to implement OMB Memorandum
M-09-10, entitled "Initial
Implementing Guidance for the American Recovery and
Reinvestment Act of 2009," (the Recovery Act) with
respect to publicizing contract actions, which has since been
supplemented, amended, and clarified by Memorandum M-09-15.
Item IV
(FAR Case 2008-003) entitled "Public
Disclosure of Justification and Approval Documents for
Noncompetitive Contracts--Section 844 of the National Defense
Authorization Act for Fiscal Year 2008" is a final
rule adopting (with changes) an interim rule amending the FAR
to implement section 844 of the 2008 National Defense
Authorization Act, which details the requirements for the
public availability of justifications and approvals after the
award of of a federal contract.
Item V
(FAR Case 2008-007) entitled "Additional
Requirements for Market Research" is an interim rule
amending the FAR to implement section 826 of the National
Defense Authorization Act for Fiscal Year 2008, which
established additional requirements in subsection (c) of 10
U.S.C. 2377 that, as a matter of policy, are extended to all
executive agencies. Specifically, the head of the agency must
conduct market research before issuing an ID/IQ task or
delivery order for a noncommercial item in excess of the
simplified acquisition threshold, and a prime contractor with
a contract in excess of $5 million for the procurement of
items other than commercial items is required to conduct
market research before making purchases that exceed the simplified acquisition threshold for or on
behalf of the Government. Comments are due by August 16.
Item VI
(FAR Case 2009-011) entitled "American
Recovery and Reinvestment Act of 2009--GAO/IG Access"
is a final rule adopting (with changes) an interim rule
amending the FAR to
implement sections 902, 1514, and 1515 of the Recovery Act.
Item VII
(FAR Case 2009-014) entitled "New
Designated Country--Taiwan" is a final rule adopting
(without change) an interim rule amending the FAR to add
Taiwan as a designated country, due to the its accession to
membership in the World Trade Organization Agreement on
Government Procurement.
Item VIII
(FAR Case 2009-013) entitled "Nonavailable
Articles" is a final rule amending the FAR to revise
the list of articles determined to be domestically
nonavailable.
Item IX
(FAR Case 2009-025) entitled "Disclosure
and Consistency of Cost Accounting Practices for Contracts
Awarded to Foreign Firms" is an interim rule amending
the FAR to align it with the revised CAR Board clause entitled
"Disclosure and Consistency of Cost Accounting
Practices--Foreign Firms." Comments are due by August 16.
Item X
(FAR Case 2009-026) entitled "Compensation
for Personal Services" is an interim rule amending
the FAR to align it with revised CAS 412 ("Cost Accounting Standard for
composition and measurement of pension cost") and 415
("Accounting for the cost of deferred compensation"). Comments are due by August 16.
Item XI
(FAR Case 2009-018) entitled "Payrolls
and Basic Records" is an interim rule revising the
FAR "Payrolls and Basic Records" clause to implement
a DOL rule to protect the privacy of workers. Comments are due
by August 16.
In Northrop
Grumman Computing Systems, the Court of Federal Claims
denied cross motions for summary judgment in a dispute
involving an alleged government breach of a contract to lease
surveillance software to the Department of Homeland Security. |
| June 15 |
The DOE is
proposing to amend the DEAR
to (i) make changes to conform to the FAR, (ii) remove
out-of-date coverage, and (iii) update references. Comments
are due by July 15.
DoD is extending
the comment period to July 21 on its proposed rule to amend
the DFARS to implement section 207 of the Weapons System
Acquisition Reform Act of 2009.
The Bureau
of Industry and Security (BIS) has issued a final rule making
technical amendments to the EAR to delete references
concerning federal
court jurisdiction for judicial review of final decisions
and orders issued in BIS export control administrative
enforcement proceedings and in administrative appeals of BIS
temporary denial orders. |
| June 14 |
Pursuant
to President Obama's April 26 Memorandum regarding enhancing
the use of small businesses in federal contracting (see
entry at April 29 below), interested parties are invited to
offer their views concerning (i) removing barriers to small
business participation in federal contracting; (ii) using
innovative strategies and technologies to increase
opportunities for small business contractors; and (iii)
identifying successful agency and private sector outreach
practices for matching small businesses with contracting and
subcontracting opportunities. A public meeting on these issues
will be held on June 28 in the auditorium of the Department of
Commerce at 1401 Constitution Avenue NW, Washington, D.C. |
| June 11 |
DFARS Case
2009-D010: The DoD
has adopted, as final, an interim rule amending the DFARS to
add Taiwan
as a designated country, due to the accession of Taiwan to
membership in the WTO's Government Procurement Agreement.
DFARS Case
2009-D025: The DoD proposes to relocate the requirements for
conducting a Contractor
Insurance/Pension Review from Procedures, Guidance, and
Information to the DFARS. Comments are due by August 10.
The Navy
is withdrawing the notice it previously published announcing a
Preferred
Supplier Program. See entry at May 25 below.
The Air
Force lost its appeal to the Federal Circuit of the ASBCA's
decision in the Lockheed
Martin case concerning whether the F-22 contract was an
"affected CAS-covered contract" within the meaning
of FAR 30.602(3)(1993) concerning a change in cost accounting
practices. |
| June 10 |
GSAR Case 2008-G503: The GSA has published a
final rule revising Part 505 of the GSAR, entitled "Publicizing
Contract Actions."
Pitney
Bowes Government Solutions convinced the Court of Federal
Claims to allow additional discovery in its protest because
the court was satisfied Pitney Bowes had shown there were
indicia of bias and favoritism by the head of the TEP and
because the Government had violated FAR Subpart 4.8 by
destroying the individual TEP evaluators' worksheets.
The SBA's
OHA has published numerous decisions, including seven new size decisions,
five of which reverse decisions by the Area Office. For
example, in PRO
SERVICES--Teltara Joint Venture, the OHA decided the Area
Office did not adequately investigate indicia of affiliation.
The SBA
also issued two VET
decisions, in one
of which it decided that a protest alleging that an owner was
not a service-disabled veteran should not have been dismissed
as insufficiently specific. In another, the OHA concluded an Operating
Agreement did not establish 51% unconditional and direct
ownership by a service-disabled veteran. The SBA also issued
two BDP
decisions and a NAICS
decision. |
| June 9 |
JER 370
Third Street won its GAO protest because the agency lacked
rational basis for canceling the solicitation.
The
DOE proposes to amend the DEAR on
Management
and Operating Contracts to make changes to conform to the
FAR, remove out-of-date coverage, and update references.
Comments are due by July 9.
The DHS
adopted the amendments to its Homeland Security Acquisition
Regulation that were issued under an interim rule on August
17, 2009, as final, without change, to implement a statute
limiting the acquisition of products containing textiles
from sources outside the United States.
In HSAR
Case 2009-005, entitled "Limitations on Subcontracting in
Emergency Acquisitions," the DHS proposes a rule to
implement a statutory requirement limiting the use of subcontractors
on cost-reimbursement type contracts entered into by the
Department to facilitate the response to or recovery from a
natural disaster or act of terrorism or other man-made
disaster. Comments are due by August 9. |
| June 8 |
Several
interim, final, and proposed DFARS regulations have been
published--
DFARS Case
2009-D040, entitled "Trade
Agreements Thresholds," is an interim rule to
incorporate increased thresholds for application of the World
Trade Organization Government Procurement Agreement and the
Free Trade Agreements, as determined by the United States
Trade Representative. Comments are due by August 9.
DFARS Case
2009-D034, entitled "Contract
Authority for Advanced Component Development or Prototype
Units," is an interim rule to implement section 819
of the National Defense Authorization Act for Fiscal Year
2010, which places limitations on certain types of line items
and contract options that may be included in contracts
initially awarded pursuant to competitive solicitations and,
in certain circumstances, limits the dollar value, period of
performance, and time for exercise of such contract line items
or contract options. Comments are due by August 9.
DFARS Case
2009-D027, entitled "Limitations
on Procurements with Non-Defense Agencies," is an
interim rule to implement section 806 of the National Defense
Authorization Act for Fiscal Year 2010 authorizing the placing
of contracts for property and services in excess of the
simplified acquisition threshold by certain non-DoD agencies
for the performance of a joint program conducted to meet the
needs of DoD and the non-DoD agency. Comments are due by
August 9.
DFARS Case
2009-D022, entitled "Finland--Public
Interest Exception to the Buy American Act," is a
final rule issued to reflect a determination by the Secretary
of Defense that it is inconsistent with the public interest to
apply the restrictions of the Buy American Act to the
acquisition of articles, materials, and supplies produced or
manufactured in Finland.
DFARS
Case 2007-D011, entitled "Letter
Contract Definitization Schedule," is a final rule
adopting, without changes, a proposed rule amending the DFARS
to to clarify requirements regarding definitization of letter
contracts and to specify that DoD letter contracts will be
definitized using the DFARS procedures applicable to all other
undefinitized contract actions.
DFARS Case
2007-D009, entitled "Ground
and Flight Risk Clause," is a final rule amending the
DFARS to revise
and combine contract clauses addressing assumption of risk of
loss under contracts that furnish aircraft to the Government
so that the requirements will apply consistently to all
contract types.
DFARS Case
2009-D041, entitled "Balance
of Payments Program Exemption for Commercial Information
Technology," is a proposed rule that would amend the
DFARS to implement
the exemption from the Balance of Payments Program for
construction material that is commercial information
technology. Comments are due by August 9.
The SBA
has granted a waiver of the nonmanufacturer rule for Liquid
Propane Gas, NAICS Code 325120, PSC 6830. |
| June 7 |
The SBA is
considering granting a class waiver of the nonmanufacturer
rule for Configured
Tape Library Storage Equipment, PSC 7025 ADP Input/Output
and Storage Devices, 7035 ADP Support Equipment, and 7045 ADP
Supplies, under NAICS code 334112 (Computer Storage Device
Manufacturing). Comments are due by June 22.
The Bureau
of Industry and Security has proposed various changes to the DPAS
regulations. Comments are due by July 7. |
| June 4 |
Effective
July 6, the Bureau of Indian Affairs in the Interior
Department and the Indian Health Service in HHS are making
belated technical amendments to their joint regulations
governing contracts and annual funding agreements under the Indian
Self-Determination and Education Assistance Act to
reflect, among other things, the dissolution of the Interior
Board of Contract Appeals in favor of the CBCA.
In Shell
Oil, the Court of Federal Claims held that neither the
Anti-Deficiency Act nor settlement agreements closing out
certain WWII gas production contracts in the late 1940s
insulated the Government from liability for CERCLA clean-up
costs. The court based its finding on the contracts'
"Taxes" clause, which required the Government to
reimburse the contractors for "any new or additional
taxes, fees, or charges, other than income, excess profits, or
corporate franchise taxes, which Seller may be required to pay
by any municipal, state, or federal law in the United States
or any foreign country to collect or pay by reason of the
production, manufacture, sale or delivery of the
[avgas]." The court concluded CERCLA clean-up costs were
a "charge" within the meaning of that clause. The
court concluded that the CERCLA costs could not have been
within the contemplation of the close-out settlement
agreements because CERCLA costs did not exist at the time
those agreements were executed. If that's valid reasoning,
then how could CERCLA costs have been within the contemplation
of the "Taxes" clause? If they didn't exist for
purposes of one provision, they weren't within the
contemplation of the other either, were they? ;) |
| June 3 |
The
fortuitously named (and successful) Magnum
Opus protest involves a passel of fascinating issues. The
Court of Federal Claims granted a tailored injunction to the
protesters after it decided it had bid protest jurisdiction to
hear a protest that the Government's decision to exercise
options in only four of six ID/IQ contracts was improper
because, by eliminating the contracts' NTE pricing from the
option awards, the Government did not evaluate the options as
exercised as part of the original evaluation, as required by
CICA and FAR 17.207(f) (which the court found confers a cause
of action upon potential competitors). The court addressed a
variety of other issues, including, inter alia, the standing
of a firm to proceed with a protest absent its joint venture
partner; timeliness and waiver issues; and the parameters for
a limited injunction.
The
court awarded plaintiffs approximately $9,000,000 in the Fireman's
Fund case, which concerned construction at the Montgomery
Point Lock and Dam Project on the White River in eastern
Arkansas and various claims involving defective
specifications, breach of the covenant of good faith and fair
dealing, the responsibility for labor shortages and resulting
increased wages, critical path analyses, delay claims, and
government counterclaims. |
| June 2 |
I have
added the protests for 2005 to the Recent Court of Federal
Claims Bid Protests page so that it now covers January
2005 to the present. |
| May 28 |
USfalcon
lost its post-award protest at the Court of Federal Claims
because the court concluded there was a rational basis for the
agency's decision to eliminate the firm from the competitive
range on the ground that the firm's response to a sample task
was unacceptable. The court stressed it would not second guess
the technical evaluation, itself.
In
Technical
Innovation, the agency decided to take corrective action
after which the original awardee tried to convince the court
to keep the protest on the docket so that it might review that
corrective action. The Court of Federal Claims, however,
dismissed the original action as moot and concluded the
awardee, who was not the original protester, had no standing
to keep it alive.
In
Benefits
Consulting Associates, another post-award protest, the
court found that the agency did not engage in misleading
discussions with the protester or fail to adequately apprise
it of the weaknesses in its proposal.
In
Retirement
Communities, the court held that a firm's "hope"
as to how a lease would be interpreted was not sufficient to
vary its plain meaning.
The
SBA's OHA published several size
decisions, the most interesting one of which is CWU,
Inc., in which the OHA upheld the Area Office's
determination that a firm violated the ostensible
subcontractor rule because, inter alia, it "(1)
hired the incumbent contractor; (2) proposed giving the
incumbent 49% of the work; (3) did not delineate tasks it
would perform or that [the incumbent] would perform on either
a task or a cost basis; and (4) proposed to keep all of the
incumbent‘s on-site management employees in the same
positions as under the previous contract." The OHA
concluded "there is little evidence that Appellant
planned to contribute anything to the contract other than its
size." Ouch.
Busy day.
Apparently the Government did not want me to start my holiday
weekend early.
The CBCA
published two decisions,
one of which merits inclusion here.
In Sigal
Construction Corp. , the CBCA granted the contractor's
motion for summary judgment only as to entitlement, finding
the contractor entitled to recover lost profits when, after
award, Government did not provide it with all the
contractually-required, unit-priced work but, instead, sought
a better price from another contractor. The Board wrote in
part: "The
parties agree that by precluding Sigal from performing some of
the unit price work, GSA constructively terminated for
convenience a portion of the contract. One of the few
limitations on the Government’s right to terminate for
convenience is that the Government may not terminate simply to
get a better price for performing needed work. [citation
omitted] That is what GSA did here. It was a breach of the
contract." |
| May 27 |
The GAO
sustained the protest of Ewing
Construction Co. because, in taking corrective action on
Ewing's prior protest by reevaluating proposals without
further discussions, the agency improperly determined that
part of Ewing proposal rendered the firm ineligible for award
when, under the solicitation's evaluation scheme, such a
deficiency should only have resulted in the proposal being
downgraded. |
| May 26 |
Effective
June 25, the DOE is amending the DEAR
Subchapters E (General Contracting Requirements), F (Special
Categories of Contracting), and G (Contract Management) to
make changes to conform to the FAR, remove out-of-date
coverage, and update references. |
| May 25 |
The Deputy
Assistant Secretary of the Navy, Acquisition and Logistics
Management, is soliciting comments that the Department
of the Navy may use in drafting a policy that will establish a
Preferred
Supplier Program (PSP) under which contractors that have
demonstrated exemplary performance at the corporate level, in
the areas of cost, schedule, performance, quality, and
business relations would be granted Preferred Supplier Status
and would, thereby, receive more favorable contract terms and
conditions in DON contracts. Comments are due by July 15. |
| May 24 |
FAR Case
2009-027 ("Personal
Identity Verification of Contractor Personnel"): A
proposed rule would revise the FAR to provide additional regulatory
coverage in Subpart 4.13 and in clause 52.204–9 to reinforce
the requirement of collecting from contractors all forms of
government-provided identification once they are no longer
needed to support a contract. Comments are due by July 23.
The DOE is
proposing to amend the DEAR to (i) revise the applicability
and the policies and procedures involving the access
to and ownership of records; (ii) to amend various
contract clauses for consistent inclusion in all applicable
contracts (not just M&O contracts) based on the type of
work being performed, to ensure preservation and Government
ownership of records; and (iii) to address inconsistencies
relating to DOE contractor and subcontractor efforts in
managing records in accordance with DOE retention
requirements. Comments are due by June 23..
The GAO
published a report
entitled "Service-Disabled Veteran-Owned Small Business
Program: Fraud Prevention Controls Needed to Improve Program
Integrity." |
| May 20 |
FAR Case
2009-031 ("Terminating
Contracts"): A proposed rule would amend
the FAR to, inter alia, clarify the FAR 49.502(a)
prescription for the "Termination for Convenience of the
Government (Fixed Price) (Short Form)" clause to apprise
contracting officers that there are alternative clauses that
can be used for terminations up to the simplified acquisition
threshold.
The SBA's OHA published three
size decisions and two VET decisions. ONS21
Security Services succeeded in its size protest because
the Area Office had no authority to change the NAICS code
assigned to a procurement in response to a size protest, at
least absent a NAICS code protest, and the protested firm's
receipts clearly exceeded the limit established by the NAICS
code in the solicitation. It appears the Area Office really dropped
the ball in the size
appeal of DynaLantic
Corp. because the OHA vacated the Area Office's denial of
the size protest and remanded for further investigation of a
host of possible violations of the clear fracture and
ostensible subcontractor rules and other matters related to
possible affiliation. In Corners
Construction, the OHA affirmed the determination a firm
was not an eligible SDVOSB because its General Partnership
Agreement was ambiguous on relevant points, and its
service-disabled veteran was not shown to have sufficient
experience to control the firm. |
| May 19 |
The
SBA is considering waiving the nonmanufacturer rule for herbicides,
insecticides, and fungicides, under PSC 6840, under NAICS
code 325120. Comments
are due by June 3.
The SBA
has decided not to issue a class waiver for Improved
Outer Tactical Vests and related accessories under Product
Service Code (PSC) 8470 (Armor Personal) under North American
Industry Classification System (NAICS) code 339113 (Surgical
Appliance and Supplies Manufacturing).
DFARS
Case 2010-D004: The DoD has issued an interim rule to
implement Section
8116 of the FY 2010 DoD Appropriations Act (Pub. L. 111–118),
which prohibits the use of funds appropriated or
otherwise made available by the Act for any contract
(including task or delivery orders and bilateral modifications
adding new work) in excess of $1 million, if the contractor
restricts its employees to arbitration for claims under title
VII of the Civil Rights Act of 1964, or torts related to or
arising out of sexual assault or harassment, including assault
and battery, intentional infliction of emotional distress,
false imprisonment, or negligent hiring, supervision, or
retention. The interim rule does not apply to the acquisition
of commercial items, including commercially available
off-the-shelf items.
The ASBCA
issued three decisions:
In Inchcape
Shipping Services, the Board denied the Government's
motion to remove a set of nine appeals from the Rule 12.3
accelerated docket because the choice to use accelerated
procedures under the CDA is exclusively the contractor's.
In Versar,
Inc., the Board held it (i) lacked jurisdiction to decide
the contractor's request that Board order specific performance
(i.e., that the Government rescind a "red"
performance rating) but (ii) had jurisdiction to decide
whether the rating was appropriate.
In Whiting-Turner
Contracting Co., which principally involved questions of
accord and satisfaction and the interpretation of releases in
bilateral modifications, the Board held that the contractor
was not entitled to interest on claims because its contract
was with a nonappropriated fund instrumentality. |
| May 17 |
DGR
Associates won its GAO protest against the terms of a
solicitation because the procuring agency failed to consider
whether the conditions for a HUBZone set-aside existed before
proceeding with an 8(a) set-aside.
In Electronic
Data Systems, the Court of Federal Claims found that the
agency (i) made a clear and significant error in allowing a
pricing proposal from the awardee that was not compliant with
the solicitation's requirements and (ii) failed to notify all
offerors that such an approach was acceptable. Nevertheless,
the court found the protester had not established that it was
prejudiced by this error because the source selection
authority (i) attempted to adjust for it in the final
evaluation and (ii) concluded that, even if all the costs at
issue were eliminated from the protester's offer, it still
would have been significantly higher than the awardee's. Maybe
so, but decisions like this make me nervous. Instead of
permitting the agency to make a self-serving, after-the-fact
guesstimate of what the bids would have been had the error not
occurred, it would seem preferable to require the agency to
correct it and then find out for certain by requiring the
submission of revised proposals. |
| May 14 |
The GAO
sustained the protest of J2A2JV
because the awardee failed to meet the solicitation's
definitive responsibility criterion of five years relevant
experience as a general contractor. |
| May 13 |
FAR Case 2009-004 ("Enhancing
Contract Transparency"): Comments are sought by July 12
concerning how best to amend the FAR to enable public
posting of contract actions, should such posting become a
requirement in the future, without compromising contractors’
proprietary and confidential commercial or financial
information. |
| May 12 |
OMB is
soliciting public comments (by July 12) on the advisability of
adopting the Economic Classification Policy Committee’s
recommendations for NAICS
updates for 2012.
The SBA's
OHA has published two size
decisions, one belatedly. |
| May 11 |
The ASBCA
published two new decisions. The Board found AST
Anlagen-und Sanierungstechnik GmbH entitled to an EAJA
recovery and remanded for a determination of quantum. In Lasmer
Industries, the Board refused to dismiss an appeal from a
deemed denial of a claim for a "no cost" termination
based on allegedly impossible specifications. |
| May 8 |
The DoD is
proposing revisions to the FAR 52.219-7 class
deviation regarding partial small business set-asides for
DLA DESC bulk fuel solicitations in order to, inter alia,
clarify that a
small business will not be awarded a set-aside portion at a
price higher than its offer price under the non-set-aside
portion. Comments are due by July 9.
The
OFPP CAS Board is proposing to harmonize CAS
412 and 413 with the Pension Protection Act (PPA) of 2006
(which amended the minimum funding requirements for defined
benefit pension plans) by, inter alia, recognizing a
"minimum actuarial liability" consistent with the
PPA minimum required contribution, which should lessen the
difference between the amount of pension cost reimbursable to
the contractor in accordance with CAS and the amount of
pension contribution required to be made by the contractor as
the plan sponsor. Comments are due by July 9.
The DOT
proposes to improve administration of the Disadvantaged
Business Enterprise Program by increasing accountability
for recipients with respect to good faith efforts to meet
overall goals, modifying and updating certification
requirements, adjusting the personal net worth threshold for
inflation, providing for expedited interstate certification,
and adding provisions to foster small business participation
and improve post-award oversight. Comments are due by July 9. |
| May 7 |
The
ASBCA published three decisions.
In Hanley
Industries, the Board decided that a letter from the
Contracting Officer revoking acceptance of items under the
"Inspection" clause and reserving the Government's
right to quantify the amount it associated with this action at
a later date was not a CDA claim and, therefore, could not be
appealed by the contractor.
In PGDC/Teng,
Joint Venture, the Board granted the Government's motion
to dismiss the contractor's claim for contract reformation
because there was no basis for its theories of (i) breach of a
duty to disclose superior knowledge, (ii) mutual mistake, or
(iii) unilateral mistake.
In Starwin
Industries, the Board decided it lacked jurisdiction over
the quantum portion of an appeal from a default termination
because no quantum claim had been submitted to the Contracting
Officer for a decision.
Five
proposed DFARS revisions have been published. Comments on each
of the following proposals are due by July 6.
DFARS
Case 2008-D042 ("Preservation of Tooling for Major
Defense Acquisition Programs") would amend the DFARS to
implement section 815 of the Duncan Hunter National Defense
Authorization Act for Fiscal Year 2009, which requires
acquisition plans for major weapons systems to include a plan
for the preservation and storage of special
tooling associated with the production of hardware for
major defense acquisition programs through the end of the
service life of the related weapons system.
DFARS
Case 2008-D050 ("Marking of Government-Furnished
Property") would require contractors to tag,
label, or mark items of government-furnished property
identified in the contract when the government-furnished material and government-furnished property are
subject to serialized item management.
DFARS
Case 2007-D003 ("Presumption
of Development at Private Expense") would amend the
DFARS to implement section 802(b) of the National
Defense Authorization Act (NDAA) for Fiscal Year (FY) 2007 and
section 815(a)(2) of the NDAA for FY 2008 by establishing
special requirements and procedures related to the validation
of a contractor’s or subcontractor’s asserted restrictions
on technical data and computer software.
DFARS
Case 2008-D027 ("Cost
and Software Data Reporting System") would add a new
subpart 234.71 to the DFARS to set forth DoD Cost and
Software Data Reporting system requirements for major defense
acquisition programs and major automated information system
programs.
DFARS
Case 2006-D029 ("Restriction
on Ball and Roller Bearings") would amend the DFARS
to revise the domestic source restriction on
acquisition of ball and roller bearings from the current rule
(which requires that the bearings and the main bearing
components be manufactured in the U.S. or Canada and is based
on 10 U.S.C. 2534(a)(5), which expired on October 1, 2005) to
a rule that interprets the annual defense appropriations act
domestic source restriction on the acquisition of these items
in a manner similar to the domestic source restriction of the
Buy American Act. |
| May 6 |
In the
latest decisions in the Raytheon
and General
Electric segment closing cases, the Court of Federal
Claims granted the Government's motions for partial summary
judgment and held that (i) Raytheon's post retirement
benefit costs are not pension costs under CAS 412 and cannot
be included in segment closing adjustments under CAS 413 and
(ii) General Electric's Pay-As-You-Go post-retirement benefit
costs are not covered by CAS 413 and cannot be included in
segment closing adjustments. |
| May 5 |
FTR
Case 2010-302: Effective June 4, the GSA is amending the
FTR by (i) adding new terms and definitions for
"official travel" and "transit system";
(ii) clarifying reimbursement for transportation at an
official station while en route to and/or from an authorized
TDY location; (iii) clarifying reimbursement for
transportation expenses within the surrounding area of a TDY
location and provisions for payment under the FTR; and (iv)
specifying when the government contractor-issued travel charge
card must be used while on official travel.
Civilian
Personnel Per Diem Bulletin 267: The DoD has published
revisions in the per diem rates prescribed for government
employees for official travel in Alaska, Hawaii, Puerto Rico,
the Northern Mariana Islands and Possessions of the United
States.
The SBA's
OHA has issued eight
VET decisions and a cautionary size decision, dismissing
an appeal alleging a lack
of specificity in another size protest because the
appellant had not raised that argument until it filed its
appeal with the OHA. |
| May 2 |
In
the PlanetSpace
protest, the Court of Federal Claims gave up trying to figure
out what, if any, trade-off analysis the SSA had conducted and
stayed the case to give the SSA an opportunity to submit a
sworn statement articulating the trade-off evaluation.
One of the Government's arguments was that the protest was
barred by laches because the protester had waited for three
months before filing its suit after it had lost its GAO
protest. The court said that laches cannot shorten a statute
of limitations absent extraordinary circumstances, and that
the statutory period for bid protests at the court is the
Tucker Act's six-year statute of limitations. Anybody out
there have a protest you wish you had filed a few years ago?
Maybe it's not too late. ;) The courts have not hesitated to
adopt the GAO's rule that protests against solicitation
requirements must be filed before proposals are due. I wonder
why the six-year statute of limitations governs only one type
of bid protest. |
| May 1 |
I
have posted the 2010
Procurement Review (through May 1), and I will
continue to update it throughout the remainder of the year. |
| April 30 |
DFARS
Case 2008-D032 ("Service Contract Surveillance") is
a final rule amending the DFARS to ensure that (i)
the requirement for a
quality assurance surveillance plan is addressed for each
contract with a dollar value above the simplified acquisition
threshold and (ii) contracts for services have appropriate
performance management or surveillance plans prepared for the
work being performed under the contracts.
DFARS Case
2008-D047 ("Government-Assigned Serial Number
Marking") is a proposed rule that would require
contractors to apply government-assigned
serial numbers in human-readable format on major end
items, when required by law, regulation, or military
operational necessity. Comments are due by June 29.
DFARS Case
2008-D049 ("Reporting of Government Property Lost,
Stolen, Damaged, or Destroyed") is a proposed rule to
amend the DFARS to require contractors to report loss, theft,
damage, and destruction of government property to the
DCMA "eTools" application. Comments are due by June 20.
DFARS Case
2006-D021 ("Award Fee Contracts") is a proposed rule
to amend the DFARS to address award-fee
contracts, including eliminating the use of provisional
award-fee payments. Comments are due by June 29. |
| April 29 |
The
President has issued memoranda establishing interagency task
forces to increase federal contracting opportunities for (i) small
businesses and (ii) veteran-owned
and service disabled veteran-owned small businesses.
The
Court of Federal Claims held Shamrock
Foods lacked standing because it had not bid on the
protested solicitation and had waited until after bids were
submitted (long after award, actually) to file a protest. |
| April 28 |
In Jones
Automation, the Court of Federal Claims came within a
whisker of holding that it lacked jurisdiction over a protest
that a bridge contract should be extended, especially absent
any showing that the plaintiff would be excluded from the
follow-on competition. However, the court contented itself
with concluding the plaintiff had not established the
requisite elements for a TRO and invited it (dared it,
actually) to let the court know whether it was still
interested in pursuing injunctive relief.
I
hesitate to quarrel with a decision again so soon after
fussing about Milani
Construction, but the ASBCA's decision in the Dixie
Construction Co. case seems flat out wrong to me. The
contractor had a requirements contract, which included the
standard "Order Limitations" clause (FAR 52.216-19).
That clause provided, inter alia, that the contractor
was not required to accept an order in excess of $500,000
(paragraph (b)) and that the Government was not required to
order part of a requirement from the contractor if the whole
requirement was more than $500,000 (paragraph (c)). The
Government had placed several orders in excess of $500,000
with the contractor under both the predecessor contract and
the current contract (and the contractor routinely had
accepted such orders). The contractor filed a breach claim
when the Government ordered one such large job from another
firm without giving the contractor a chance to at accept
it. The Board granted summary judgment in favor of the
Government, reasoning that paragraph (c) of the "Order
Limitations" clause meant the Government was free to
bypass the contractor for any order exceeding $500,000. Au
contraire! Read together (and in the contexts of (i) a
requirements contract and (ii) the course of dealing between
these parties), paragraphs (b) and (c) meant that the
Government should have offered the contractor a shot at the
above-$500,000 order and, then, if the contractor had refused
the order, the Government would not have been bound to break
the order into smaller pieces for him. It is the Board's
interpretation of the clause that is unreasonable, not the
contractor's. I bet this dispute is headed for the CAFC. |
| April 27 |
Two Court
of Federal Claims decisions on protests conclude the
Government's evaluators had rational bases for excluding the
protesters' offers from the competitive range: ManTech
(which discusses, inter alia, the permissible methods
of conducting a price realism evaluation) and Hyperion.
In U.
S. Home, the same court held it had jurisdiction over
claims for breach of contracts for the sale of real property
but lacked jurisdiction over various claims based on CERCLA
because it is not a money-mandating statute. |
| April 26 |
The SBA's
OHA has published several 8(a)
BDP decisions. For example, in Matter
of Hazzard's Environmental and Trucking Co., the OHA granted the SBA's request to
dismiss an appeal of a termination from the 8(a) program
because of the protester's pattern of failing to provide
required documentation to the SBA to establish its continued
eligibility for the 8(a) program.
The CBCA has published two
decisions, dismissing
one appeal for failure to prosecute and a portion of another
for lack of jurisdiction.
The GAO sustained the
protest of Milani
Construction because the agency concluded the protester's
offered price for a fixed-price contract was unrealistically
low even though the solicitation did not specifically notify
offerors that price realism would be an evaluation factor.
This decision highlights one of my pet peeves. Specifically,
the GAO's oft-repeated axiom (that price realism is not
normally to be evaluated on a fixed-price contract) is
bootstrapped. Anybody interested in testing that assertion
need only trace back the GAO's citations for this proposition
from case to case further and further back in time until
finally you reach a point where the case cited in support of
it does not so hold. As I recall, you have to trace it back
through about six degrees of separation to reach that point,
so the original mis-citation has become firmly entrenched as
the established rule by now. Someday before I die, I'm going
to write an article instead of just whining about the
issue. Of course, a company can make a conscious
decision to "buy in" below cost on a fixed-price
contract, but there should always be an analysis by
every procuring agency as to whether the price being offered
is so far below cost that the offeror clearly hasn't
the foggiest idea of the magnitude of work involved in
performing the contract and will only get itself and the
Government in trouble if it is awarded the contract. |
| April 22 |
DFARS Case
No. 2009-D015: The DoD is proposing to amend the DFARS
to implement section 207 of the Weapons Systems Acquisition
Reform Act of 2009 (Pub. L. 111–23), which requires the DoD
to provide uniform guidance and tighten existing requirements
for organizational
conflicts of interest (OCIs) by contractors in major
defense acquisition programs. Comments are due by June 21. |
| April 21 |
The ASBCA
published three decisions. Several claims by Guy
W. Parker d/b/a Parker International were dismissed/denied
for various reasons: res judicata on a claim related to
the Contracting Officer's authority; the fact that another
claim had not been submitted to the Contracting Officer for a
decision; and a lack of evidence or any contractual basis for
claims related to government property. SUFI
Network Services, Inc., squeezed even more money out of
the Board after the contractor already had seen its recovery
double as a result of the Board's prior
decision on its request for reconsideration. In Yonir
Technologies Inc. , the Board upheld a default termination
based on the contractor's failure of first article testing.
The SBA is considering granting a waiver of
the Nonmanufacturer
Rule for Improved
Outer
Tactical Vests. Comments are due by May 6. |
| April 20 |
The Bureau
of Industry and Security (BIS) has amended the Export
Administration Regulations (EAR) to reflect changes to the Missile
Technology Control Regime (MTCR) Annex that were agreed to
by MTCR member countries at the November 2009 Plenary in Rio de Janeiro, Brazil,
including clarifying the meaning of the term "production
facilities."
In
accordance with 10 U.S.C. 2330a as amended by section 807 of
the National Defense Authorization Act for Fiscal Year
2008, within 60 days, the Defense
Threat Reduction Agency will make available to the public
(at this
website) the first inventory of activities performed
pursuant to contracts for services . |
| April 16 |
The SBA's
OHA published a size decision and three
"VET" decisions. In the Size
Appeal of A1 Procurement, the OHA upheld the Area
Office's determination that a firm ran afoul of
ostensible subcontractor rule because the firm had no
experience in the type of work required by the contract and
planned to use a large business as a subcontractor to perform
an undefined portion of work. In Jordan-Reses
Supply Co., the VA had extended blanket purchase
agreements with several companies, two of which were SDVOSBs,
one a small business, and another a large business. In doing
so, the Contracting Officer indicated that any orders placed
during the extended period should give preferential status to
the SDVOSBs. The small business protested, but the OHA
affirmed the dismissal of the protest on the grounds that it
was speculative (since no contract actions had yet occurred
and) that it raised a non-protestable issue (since it did not
involve an SDVOSB set-aside). |
| April 15 |
Infiniti
Information Solutions won its protest at the Court of
Federal Claims against a direct 8(a) award because HUD ran
afoul of (i) 13 C.F.R. 124.503(e) (by going beyond informal
market assessments, which are permissible, and performing
actual technical evaluations before making the award) and (ii)
13 C.F.R. 504 (by expressing a clear intent to make the
procurement a SDVOSB set-aside prior to offering the
procurement to the SBA for award as an 8(a) contract).
In Nycal
Offshore Development Corp., the Court of Federal
Claims allowed a claim for lost profits by a lessee (based on
a government breach) to proceed despite the fact that
plaintiff's co-lessees had previously elected restitution as
their remedy.
Effective
May 17, the Department of the Interior is issuing an interim
final rule making various administrative
changes to its acquisition regulation to harmonize it with
the FAR and to make other corrections. Comments are due by
June 14. |
| April 14 |
FAR Case
2009-006 ("Labor
Relations Costs"): A proposed rule would amend FAR
31.205-21 to implement Executive Order 13494, Economy in
Government Contracting (issued on January 30, 2009, and
amended on October 30, 2009) by designating as unallowable the
costs of any activities undertaken to persuade employees of
the recipient of federal disbursements or of any other entity
to exercise or not to exercise, or concerning the manner of
exercising, the right to organize and bargain collectively
through representatives of the employee’s own choosing.
Comments are due by June 14. |
| April 13 |
FAC
2005-41 has been published. It contains FAR Case 2009-005
("Use of Project Labor Agreements for Federal
Construction Projects"), a final rule that implements
Executive Order 13502 by amending the the FAR
(i) to provide that an agency may, if appropriate, require
that every contractor and subcontractor engaged in
construction on a federal construction project agree, for that
project, to negotiate or become a party to a project
labor agreement with one or more labor organizations, (ii)
to identify factors that agencies may consider to help them
decide, on a case-by-case basis, whether the use of a project
labor agreement is likely to promote economy and efficiency in
the performance of a specific construction project, and (iii)
to identify multiple strategies for timing the Federal
Government’s receipt of project labor agreements. |
| April 8 |
Several
DFARS regulations have been issued:
DFARS Case
No. 2004-D010--The DoD is adopting as final, with changes, an
interim rule (i) amending the DFARS (Subpart 204.73) to
address contractor responsibilities to comply with
existing Department of Commerce and Department of State export
control laws and regulations and (ii) prescribing a
contract clause (DFARS 252.204-7008) to address those
responsibilities.
DFARS Case
No. 2006-D053--The DoD is adopting as final, without change,
an interim rule that requires the Milestone Decision
Authority for a major defense acquisition program to
select the
contract type for a development program that is consistent
with the level of program risk in accordance with section 818
of the National Defense Authorization Act for Fiscal
Year 2007.
DFARS Case
No. 2008-D002--The DoD is adopting as final, with minor
changes, an interim rule amending the DFARS to implement sections
886 and 892 of the National Defense Authorization Act for
Fiscal Year 2008, which (i) provide authority for
the DoD to limit competition when acquiring products or
services in support of operations in Iraq or Afghanistan and
(ii) address competition requirements for the procurement of
small arms for assistance to Iraq or Afghanistan.
DFARS Case
No. 2009-D004--The DoD is proposing to amend the DFARS to address
requirements for minimizing the use of hexavalent
chromium in defense weapon systems, subsystems,
components, and other items by prohibiting the delivery of
items containing hexavalent chromium under DoD contracts
unless an exception applies. Comments are due by June 7.
In the Allied
Technology Group post-award bid protest, the Court of
Federal Claims denied motions by both the protester and the
intervenor to supplement the administrative record with
affidavits essentially arguing the case and not available to
the Contracting Officer at the time the selection decision was
made. The court did allow supplementation with certain other
factual materials. |
| April 7 |
The GAO
sustained the protest of Irving
Burton Associates because there was no rational
basis for the agency's evaluation of (i) the awardee's
proposal with regard to a transition plan and the requirement
to present program milestones and (ii) the protester's alleged
lack of proposal detail. |
| April 6 |
The
Information Security Oversight Office of the National Archives
and Records Administration has amended National Industrial
Security Program Directive No. 1 to provide guidance to
agencies concerning the release of certain classified
information (specifically, "proscribed
information") to contractors that are owned or under the
control of a foreign interest and have had the foreign
ownership or control mitigated by a Special Security
Agreement. The amendment is effective May 6. |
| April 5 |
In
Paul & Partners,
the GAO
Contract Appeals Board (yes, there is such an animal)
upheld the Government's assessment of the postage costs of
re-mailing items a printing contractor had misprinted even
though those costs greatly exceeded the total value of the
misprinted order. |
| April 4 |
I
prefer to use e-CFR
in researching current regulations, and I link to that site at
the beginning of my Regulations
webpage. However, on that same page, I also provide a link to
the FAR at acquisition.gov.
The web addresses for that main FAR page and for the
individual FAR sections to which it links have changed
(replacing the word "arnet" with
"acquisition"), so I have updated all the
corresponding links on my website. See my pages: FAR 1-15; FAR 16-30; FAR 31-45; FAR 46-53. |
| April 3 |
The
SBA has just published four
"new" size decisions by the OHA. In Precision
Lift (which is dated December 17, 2007, and that's not a
typo), the OHA reversed the Area Office's determination that
an offeror would not be supplying the product of a small
domestic manufacturer. In Jenn-Kans,
the OHA discussed affiliation in the context of
identity-of-interest and clear fracture analysis. |
| April 2 |
In BioFunction,
the Court of Federal Claims denied the plaintiff's claim
because (i) the government employee who allegedly entered a
"side agreement" to a Postal Service contract lacked
contracting authority and, in any event, (ii) the plaintiff
did not establish that the side agreement provided for any
monetary compensation.
I
couldn't resist quoting the following introduction by Judge
Allegra to the decision in the Schortmann
case, which involved allegations that the IRS breached a
settlement agreement:
"To every complicated problem
there is a simple solution, which turns out to be wrong.”
Various temporal limitations are
interwoven into the Federal income tax system. The warp of
that system is the annual accounting principle, famously
described in Burnet v. Sanford & Brooks . . .,
which vertically limits the calculation of income to events
occurring within a given taxable year. Then, there are the
wefts supplied by the limitation provisions in the Internal
Revenue Code . . ., which introduce into the weave finality
principles that horizontally limit, to a prescribed set of
years, the ability of taxpayers and government alike to modify
the computation of income. Meshed together, these concepts
form a tough fabric that resists efforts to reach back and
remedy even the most patent of errors. The necessity for this
resistance makes sense in the broader state of affairs, based,
inter alia, on the paramount need "to produce
revenue ascertainable and payable at regular intervals," Hillsboro Nat’l Bank v. Comm’r
of Internal Revenue . . . . Yet, as attractive as this
rationale might be from a tax policy perspective, it offers
little solace to the individual taxpayer who finds himself on
the wrong side of these limitations. Often he or she perceives
the warp and wefts not as a cohesive body of law, but as an
entangling web of inequity – and sometimes that perception
is reality. [Introductory quotation attributed to H. L.
Mencken; full citations omitted]
I
don't have the slightest idea what that means, but I am
mightily impressed, nonetheless. |
| April 1 |
The DOD
has issued Phase III Final-Draft Business Rules for the
Defense Personal Property Program (DP3) in the Defense
Transportation Regulation (DTR) Part IV (DTR 4500.9R).
Comments are due by June 1.
The
Department of Transportation
is removing the sunset provision from its
rule governing the airport
concessions disadvantaged business enterprise (ACDBE) program.
In the Eskridge
Research Corp. bid protest, the Court of Federal Claims
denied a firm's request for an injunction against the
Government's decision to continue to employ the services of a
contract awardee during the period in which the Government is
accomplishing corrective action in response to the plaintiff's
earlier filed GAO protest. In balancing the equities for an
injunction, the court found that interests of national defense
and security and the plaintiff's lack of urgency in the
timing of both its original GAO protest and its subsequent
court case weighed against granting an injunction.
Specifically, the court noted, inter alia, that the
plaintiff had not filed its GAO protest in time to obtain the
automatic stay (even though the GAO protest had
subsequently been dismissed as moot when the agency undertook
corrective action): "By sitting on its rights and failing
to secure an automatic stay before the GAO or seeking timely
relief in this court, the plaintiff created or exacerbated the
harm it now claims can only be avoided by preliminary
injunction. [The awardee] is performing the current contract
because [the plaintiff] did not timely seek to stop this
performance. In such circumstances, the equities do not favor
the plaintiff." The case is worth a read for several
other issues as well, including the concept of mootness. |
| March 31 |
In
response to the March 4, 2009, Presidential
Memorandum on Government Contracting, the OMB's OFPP has
issued a proposed
policy letter to clarify the circumstances when work must
be reserved for performance by federal government employees
consistent with section 321 of the National Defense
Authorization Act for FY 2009, which requires OMB to (i)
create a single definition for the term "inherently
governmental function" that addresses any deficiencies in
the existing definitions and reasonably applies to all
agencies; (ii) establish criteria to be used by agencies to
identify "critical" functions and positions that should only be
performed by federal employees; and (iii) provide guidance to
improve internal agency management of functions that are
inherently governmental or critical. Comments are due by June
1. |
| March 30 |
In Eagle
Home Medical Corp., the GAO sustained a protest because
the Contracting Officer failed to amend a solicitation to
comply with an SBA OHA decision that the NAICS code assigned
to the procurement was improper. |
| March 29 |
The
Department of State is proposing to amend the ITAR
by removing the requirement for prior approval or prior
notification before proposals for foreign sales of
significant military equipment or defense services to foreign
persons may be made. Comments are due buy May 28.
In Madison
Services, Inc., the Court of Federal Claims denied a
protest after finding that FEMA's cancellation of solicitation
had a rational basis and was not a mere pretext. Moreover, the
protester's allegations of bad faith did not come close to the
standard of clear and convincing evidence needed to overcome
the strong presumption of good faith accorded to agency
decisions.
In
DataMill,
the court held that, under FASA, it lacked jurisdiction over
protest against an agency's decision to conduct a
noncompetitive, sole source procurement via the issuance of a
delivery order under a competitor's contract. In another
decision in the same case, the court declined the
protester's request to supplement the administrative record
and struck an affidavit relied on by the protester in its
arguments to the court because the affidavit contained many
irrelevant statements, some statements repeating evidence
already in the administrative record, and arguments against
the protested agency decision.
The
ASBCA has published several new decisions. In Solid
State Electronics Corp., the Board denied a contractor's
claim for costs of expedited delivery because the government
employee who requested it did not have the authority to change
the contract. In the latest States
Roofing decision, the Board determined the quantum
owed the contractor after the Court of Appeals for the Federal
Circuit reversed
and remanded the Board's prior decision. |
| March 26 |
The SBA's OHA has issued four new BDP
decisions.
The
GAO sustained the protest of Shaw-Parsons
Infrastructure Recovery Consultants because the agency's
evaluators failure to adequately consider narrative responses
in past performance questionnaires.
|
| March 25 |
In IMS
Engineers-Architects , the Court of Federal Claims held
that a contractor knew about Government's improper contract
administration and termination prior to the time it signed a
release, which was, therefore, knowing, valid, and
enforceable.
The
Bureau of Industry and Security has published a final rule
amending the Export Administration Regulations (EAR) to
clarify coverage of concealed
object detection equipment.
The
GSA has published Per Diem Bulletin 10-03 concerning revised
FTR per
diem rates for certain locations in the States of Kansas, New
Mexico, New York, Rhode Island and Texas.
I
have removed the temporary entries that were below for the
last three months of 2009, but the entire 2009 blog can still
be found and searched here. |
| March 24 |
The GAO
sustained two, companion protests (B. L.
Harbert-Brasfield & Gorrie, JV, and McCarthy/Hunt,
JV) because the GAO found two types of organizational
conflicts of interest: one based on "unequal access to
information" and the other on "biased ground
rules."
The DoD
has published the updated
charter of the ASBCA as Appendix A, Part 1 of the DFARS. |
| March 23 |
The ASBCA
has issued several new
decisions. In HMRTECH2,
LLC, the Board held that a contractor's graduation from
the 8(a) program did not give the Government the right to deny
the contractor a fair opportunity to continue to compete for
further task orders for the duration of a multiple-award
schedule contract. In Al-Dhiyaa
Bureau for General Contracting, the Board held that the
Government had established its affirmative defense to the
contractor's claims by proving that payments had been made to
contractor's authorized representatives.
Federal
Acquisition Circular (FAC) 2005-40
has been published. It consists of one item, FAR Case
2008-027, entitled "Federal
Awardee Performance and Integrity Information System,"
a final rule (effective April 22) to implement the Federal
Awardee Performance and Integrity Information System (FAPIIS),
as required by section 872 of the Duncan Hunter National
Defense Authorization Act for Fiscal Year 2009, which is
designed to improve the Government’s ability to evaluate the
business ethics and expected performance quality of
prospective contractors and protect the Government from
awarding contracts to contractors that are not responsible
sources.
The SBA is
considering waiving the nonmanufacturer rule for Liquid
Propane Gas. Comments are due by April 7.
The Bureau
of Industry and Security (BIS) has issued corrections
to a previously published final rule affecting Export Control
Classification Numbers 1A004 and 5A001. The BIS has also
published a final rule to amend the Export Administration Regulations (EAR)
to implement the understandings
reached at the September 2009 plenary meeting of the Australia
Group (AG) and to implement a decision recommended at the 2009
AG Plenary, specifically (i) to add technical notes to
the AG ‘‘Control List
of Dual-Use Chemical Manufacturing Facilities and Equipment
and Related Technology and Software’’ in order to clarify (a) the term
"alloys,"’ as used in reference to the types of
materials from which such equipment is made and
(b) "nominal size,"’ as used in reference to the
valves described on this AG control list and (ii) to amend the
EAR to reflect the AG decision to remove "white
pox" virus from the AG List of Biological Agents for
Export Control. |
| March 21 |
The SBA's
OHA has issued several new decisions on size and NAICS
appeals. For example, in Diverse
Construction Group, the OHA overturned an Area Office
finding of affiliation because there was not enough evidence
to establish such affiliation either under the "totality
of the circumstances" or an "identity of
interest" analysis. The remainder of the decisions can be
found here. |
| March 20 |
In the
important ATK
Thiokol decision, the Court of Appeals for the Federal
Circuit affirmed the Court of Federal Claims and held that,
for purposes of determining whether costs qualify as IR&D
costs, the phrase "required in the performance of a
contract" in the definition of IR&D costs means the
same thing as it does in the definition of B&P costs, i.e.
"costs that are specifically required by the
contract," not "costs that are
necessary in order to perform the contract." |
| March 19 |
In
the Rapiscan
Systems protest, the GAO found that issuance of a purchase
order for items not included in a vendor's FSS contract was
improper where the underlying solicitation had limited
competition to vendors holding FSS contracts.
Federal
Acquisition Circular (FAC) 2005-39
has been published. It includes the following six items, plus
a technical amendment:
Item I (FAR
Case 2009-035), entitled "Extend Use of Simplified
Acquisition Procedures for Certain Commercial
Items," is a final rule revising FAR subpart 13.5, ‘‘Test
Program for Certain Commercial Items,’’ to implement
section 816 of the National Defense Authorization Act for
Fiscal Year 2010 (Pub. L. 111–84) by extending the program
for two more years.
Item II (FAR
Case 2008-012), entitled "Clarification of Submission
of Cost or Pricing Data on Non-Commercial Modifications of
Commercial Items ," is a final rule (adopting the
prior interim rule with few changes) to implement section 814 of the
National Defense Authorization Act for Fiscal Year
2008, which requires alignment of the threshold for cost
or pricing data on noncommercial modifications of commercial
items with the Truth In Negotiation Act (TINA) threshold for
cost or pricing data.
Item III (FAR
Case 2008-040), entitled "Use of Standard Form 26 --
Award/Contract," is a final rule effective April 19
(i) revising
FAR parts 15 and 53 instructions for use of the Standard Form
(SF) 26 to strengthen the prohibition against using block 18
of the form when awarding a negotiated procurement and
to emphasize that block 18 should only be checked when
awarding a sealed bid contract and (ii) revising the final
sentence of the current FAR 53.214 because the updated SF 26,
which was issued in April 2008, makes the sentence
unnecessary.
Item IV (FAR
Case 2008-006), entitled "Enhanced Competition for
Task- and Delivery- Order Contracts--Section 843 of the Fiscal
Year 2008 National Defense Authorization Act," is a
final rule effective April 19, adopting the prior interim rule
with changes and amending the FAR to implement Section 843,
Enhanced Competition for Task and Delivery Order Contracts, of
the National Defense Authorization Act for Fiscal Year 2008.
which contains several requirements regarding enhancing
competition within federal contracting, including: (i)
limitation on single-award task and delivery-order contracts
greater than $100 million; (2) enhanced competition for task
and delivery orders in excess of $5 million; and
(3)restrictions on protests in connection with issuance or
proposed issuance of a task- or delivery-order except for a
protest on the grounds that the order increases the scope,
period, or maximum value of the contract under which the order
is issued, or a protest of an order valued in excess of $10
million.
Item V (FAR
Case 2008-036), entitled "Trade Agreements--Costa
Rica, Oman, and Peru," is a final rule adopting the
interim rule without changes amending the FAR to implement the Dominican
Republic--Central
America--United States Free Trade Agreement with respect to
Costa Rica, the United States-Oman Free Trade Agreement, and
the United States-Peru Trade Promotion Agreement.
Item VI (FAR
Case 2008-015), entitled "Payments under Fixed-Price
Architect-Engineer Contracts," is a final rule
effective April 19 amending
the FAR to revise the withholding of payment requirements
under FAR 52.232–10, a change that was initiated by the
SBA's Advocacy Office, a part of the SBA Office of Advocacy’s
Regulatory Review and Reform Initiative, or r3 initiative,
which was established to help small businesses address the
cumulative federal regulatory burden.
Item VII
is a technical
amendment to FAR 14.202-4.
The DOL
has issued a proposed rule which, in its final form, will
implement Executive Order 13495 regarding the nondisplacement
of qualified workers on service contracts. Comments on the
proposed rule are due by May 18. |
| March 17 |
FTR
Bulletin 10-02: The GSA has published a revised Standard
Mileage Rate for moves within the continental United
States, reducing the prior rate of 24 cents per mile to 16.5
cents. The revised rate is effective for travel during
calendar year 2010.
In C.
R. Pittman Construction Co., the Court of Federal Claims
held that the contract's Damage to Work clause
unambiguously assigned to the contractor the responsibility
for damage to equipment caused by Hurricane Katrina, and,
therefore, the contractor's efforts to rely on various
"course of dealing" arguments to interpret the
clause differently were unavailing. |
| March 15 |
President Obama has issued a memorandum
dated March 10 entitled "Finding and Recapturing Improper
Payments," which directs OMB to develop guidance within
90 days for increased use of Payment Recapture Audits to
identify improper
payments that have been made to contractors.
The GAO
sustained the protest of DynCorp
International LLC because task order solicitations were
outside the scope of the underlying multiple-award contracts.
|
| March 12 |
The GAO has issued the March 10, 2010,
update of the third edition of Principles
of Federal Appropriations Law. |
| March 10 |
The
DoD has issued revised non-foreign
overseas per diem rates for travel in Alaska,
Hawaii, Puerto Rico, the Northern Mariana Islands and
Possessions of the United States.
Three
ASBCA decisions have been published. In Laser
Manufacturing, the Board denied a claim for alleged
changes in inspection and acceptance criteria. In Bernard
Cap Co., the Board dismissed several claims as time barred
by CDA's statute of limitations. In American
Ordnance, the Board found the Government responsible for
excusable and compensable delays resulting from (i) defective
specifications; (ii) withholding of superior knowledge; and
(iii) breach of the implied duties of cooperation and
noninterference. The Board found that the Government's
technical data package was seriously defective, that the
Government failed to communicate its superior knowledge of the
problems to the contractor; that the contractor did not assume
the risk of these issues by, inter alia, entering a
fixed-price contract, and that the Government compounded the
problem by its improper administration of contract performance
as these issues came to light.
Meanwhile,
the SBA's OHA published five decisions in size determination
appeals: (i) dismissing as premature an appeal that a size
determination "might"
affect a firm's 8(a) eligibility; (ii) returning another to
the Area Office and requiring it to explain its rationale
for a finding of affiliation; (iii) concluding there is no
exception for 481(a) income adjustments that counters the
general rule that total income plus cost of goods sold as
stated on a firm's tax return is the basis for calculating annual
receipts for purposes of size determinations;
(iv) denying a petition for reconsideration of its decision in
SIZ-5090
regarding the inclusion of inclusion of conference
management revenues in annual receipts as amounts
collected for another pursuant to 13 C.F.R. § 121.104(a); and
(v) dismissing an appeal both regard to the current
procurement (because it was untimely for that purpose) and for
future procurements (because it lacked the requisite specificity
as to the alleged errors in the Area Office's determination. |
| March 9 |
In Bell
BCI, the Court of Federal Claims held that, when there is
no just reason for a delay, a contractor may obtain immediate
recovery in the form of partial summary judgment on claims
affirmed on appeal without waiting for its remaining claims to
be resolved. |
| March 8 |
In The
Dallas Irrigation District, the Court of Federal Claims
had occasion to address many elements of EAJA awards
including, inter alia, attorney fees, a request for an
enhanced award, COLA, paralegal fees, legal research expenses,
attorney travel expenses, deposition, hearing, and trial
transcript costs.
The CBCA
upheld the default termination of (and subsequent government
claims for liquidated damages and excess reprocurement costs
against) C-Shore
International, rejecting the contractor's contention that
the Government's claims were untimely and dismissing the
contractor's cross complaint for lack of jurisdiction because
that claim had not been submitted to the Contracting Officer
for a decision.
Effective
April 7, the Commerce Department is updating the entire Commerce
Acquisition Regulation to bring it in line with the FAR. |
| March 5 |
DFARS Case
2009-D017: The DoD has issued an interim rule to add
policy and a contract clause requiring that contractors
providing essential
contractor services must be prepared to continue such
services during periods of crisis. Comments are due by May 4.
DFARS Case
2009-D035: The DoD has issued another interim rule to
implement section 812 of the National
Defense Authorization Act for Fiscal Year 2010 (Pub. L. 111–84,
enacted October 28, 2009). Section 812 (entitled "Revision of Defense Supplement Relating to Payment of Costs Prior
to Definitization") makes the limitations
on payment of costs prior to definitization of unpriced
change orders applicable to all categories of undefinitized
contractual actions, "including undefinitized task orders
and delivery orders" and already has been partially
implemented in DFARS Case 2008–D034. The current case
implements the balance of the section by specifically
including the category of "task orders and delivery
orders" in the definition of "contract action"
at DFARS 217.7401. Comments are due by May 4.
Mission
Critical Solutions won its bid protest at the Court of
Federal Claims. As you may recall, the company originally won
its protest
at the GAO against
a sole source award because the agency made the award
without considering whether it could obtain competition from
two or more HUBZone small businesses as required by the
HUBZone statute, the provisions of which the GAO recognized as
"mandatory." The SBA and the Army fought the
protester's position in the protest (but the GAO rejected the
SBA's interpretation). On the SBA's request for
reconsideration, the GAO reaffirmed
its decision and emphasized that HUBZone program set-asides
are mandatory when the statutory conditions are met. However,
shortly thereafter, the OMB issued a memorandum
and then the Office of Legal Counsel of the Department of
Justice issued its own memorandum
concluding the GAO's position was incorrect and directing
executive agencies to disregard it. Mission Critical Solutions
took the fight to the Court of Federal Claims, which has just
held for the company. Why do I think this one ain't over? |
| March 4 |
The bid
protest by White
Hawk Group was dismissed by the Court of Federal Claims
because the offeror had such inferior overall evaluation
scores that any errors by the SBA or procuring agency in
regard to its small business size or joint venture status were
irrelevant and nonprejudicial since it would not have received
award anyway.
The SBA is
proposing changes to 13 C.F.R. Part 127 (entitled "Women-Owned
Small Business Federal Contract Assistance Procedures"),
including eliminating the requirement for an agency-by-agency
determination of discrimination, adopting both ‘‘numbers’’
and ‘‘dollars’’ measures of under-representation, and using the
Fiscal Year 2006 CCR database as the data source for
determining eligible industries under the WOSB Program. |
| March 3 |
The DoD
has proposed adding a new part 157 to 32 C.F.R. to reduce the
use of social
security numbers in forms and systems generated or
maintained by DoD personnel and contractors. Comments are due
by May 3.
DFARS Case
2008-D028: The DoD is seeking comments on potential changes to
the DFARS to add a new subpart and associated contract clauses
for the safeguarding, proper handling, and cyber intrusion
reporting of unclassified
DoD information. |
| March 2 |
The Court
of Appeals for the Federal Circuit cleared up some important
jurisdictional issues in Resource
Conservation Group, holding that the Court of Federal
Claims does not have jurisdiction over nonprocurement
protests under 28 U.S.C. 1491(b)(1), but continues to have
jurisdiction over claims for breach of an implied-in-fact
contract under 1491(a)(1) for claims where the Administrative
Dispute Resolution Act (ADRA) does not provide a remedy. Thus,
according to the court, the ADRA did not repeal the Court of
Federal Claims pre-existing jurisdiction over implied-in-fact
contracts in nonprocurement cases. |
| March 1 |
The SBA's
Office of Hearings and Appeals has published a
slew of VET decisions (regarding the eligibility of
service disabled veteran-owned small businesses). The most
interesting of the bunch is Cooper-Glory
LLC, in which the SBA's OHA determined that a joint
venture owned by two other companies was not qualified as a
SDVOSB and, in doing so, rejected the protester's attempt to
rely on rules from other sections of the SBA's regulations
that encourage joint ventures. In International
Logistics, the OHA found that an ownership interest was
not unconditional because it could not be sold at fair market
value to anyone of the owner's choosing. Two other decisions (Teracore
and Advanced
Environmental Solutions) involved the question whether the
service disabled owner's ownership or work in another firm
impeded his ability to full time manage and operate the SDVOSB
in question. |
| February 27 |
DFARS Case
No. 2008-D023: Effective March 1, the DoD is promulgating an
interim rule adding several requirements to the DFARS related
to the authority and funding requirements for multiyear
contracts for major weapons systems, in order to implement
section 811 of the
National Defense Authorization Act for Fiscal Year 2008 and
section 8008 of the Fiscal Year 2007 Defense Appropriations
Act, and the same language in subsequent DoD appropriations
acts. Comments are due by April 30.
The SBA is
proposing numerous
amendments to its small business size regulations to (i)
clarify the effect, across all small business programs, of
initial and appeal eligibility decisions on the procurement in
question; (ii) increase the amount of time that SBA has to
render formal size determinations; (iii) require that SBA’s
Office of Hearings and Appeals (OHA) issue a size appeal
decision within 60 calendar days of the close of the record,
if possible; (iv) increase the amount of time that SBA has to
file North American Industry Classification System (NAICS)
code appeals; (v) alter the NAICS code appeal procedures to
comply with a federal court decision; (vi) clarify that
contracting officers must reflect final agency eligibility
decisions in federal procurement databases and goal
statistics; (vii) clarify how a contracting officer assigns a
NAICS code and size standard to a multiple award procurement;
and (viii) make other changes to size status protest and
appeal rules. The proposed rule changes would affect 13 C.F.R.
Parts 121, 124, 125, 126, and 134. Comments are due by March
31. |
| February 25 |
General
Dynamics and Unisys won their GAO protest against the
TSA's issuance of a task order to Computer Sciences Corp.
because the agency's price realism evaluation re staffing was
flawed and because the agency credited CSC for proposing an
incentive fee lower than the one the solicitation suggested to
other offerors was mandatory.
There are
a couple of new CBCA
decisions out, both dealing with contract interpretation
issues. |
| February 24 |
The DoD
has published an interim rule amending the DFARS to implement
the provisions of Section 202 of the Weapons Systems
Acquisition Reform Act of 2009, entitled "Acquisition
Strategies to Ensure Competition throughout the Lifecycle of
Major Defense Acquisition Programs," which:
(i) requires that the acquisition strategy for each Major
Defense Acquisition Program (MDAP) include measures to
ensure competition at both the prime contract and subcontract
level of the MDAP throughout its life cycle as a means to
improve contractor performance and adequate documentation of
the rationale for selection of the subcontractor at any tier;
and (ii) requires specified actions to ensure fair and
objective ‘‘make-buy’’ decisions by prime contractors
on MDAPs and (whenever a decision regarding the source of
repair results in a plan to award a contract for performance
of maintenance and sustainment of a major weapon system)
actions to ensure that the contract is awarded on a
competitive basis with full consideration of all sources. The
interim rule is effective today, and comments on it are due by
April 26. |
| February 23 |
In Savantage
Financial Services, the Court of Appeals for the Federal
Circuit affirmed the finding of the Court of Federal Claims
that the agency had a rational basis for the requirements
stated in the solicitation, which were not shown by the
protester to be merely a pretext for ordering the brand of one
particular offeror.
The latest
procedural decision by the Court of Federal Claims in L-3
Communications Integrated Systems (a bid protest based on
the Druyun fiasco) concluded, inter alia, that the
standard to be applied in deciding whether a plaintiff (who is
alleging bad faith by government procurement officials) should
be allowed to supplement the administrative record is not the
"irrefragable proof" required to actually prove the
bad faith on the merits, but rather only that the bad faith
allegations "appear to be sufficiently
well-grounded" to support supplementation. The
court also rejected most of the evidentiary objections raised
by the Government, permitting the supplementation requested by
the plaintiff except as to rough drafts of a final report that
was to be admitted and documents that had not been adequately
identified or authenticated. Stay tuned. |
| February 21 |
The SBA
has published two WBC decisions and several 8(a)
BDP decisions.
Both the
WBC decisions continue the battle regarding the Women's
Venture Fund. The OHA originally
held that the SBA's suspension of the firm from the
program was improper because the suspension had been imposed
without affording the firm a hearing. Subsequently, the SBA
tried unsuccessfully to convince the OHA to reconsider
its decision or to decide sua sponte that the
insistence on the requirement for a hearing was misplaced,
both of which the OHA refused to do. However, unfortunately
for the Fund, the SBA found a way to prevail in the end. It
sent the firm reinstatement papers that included unacceptable
terms and, when the firm did not sign and return them in the
time required, it in effect "relinquished" its
awards. Unfortunately, the OHA had no
jurisdiction to hear an appeal from this situation because
the SBA had not terminated the firm from the program.
In Precision
Pine & Timber, the Court of Appeals for the Federal
Circuit reversed the Court of Federal Claims and held that the
Forest Service did not breach either (i) an express warranty
(because none existed) or (ii) the duty of good faith and fair
dealing (because the Government's actions did not specifically
target the plaintiff) in suspending timber harvesting
contracts in 1996 while the Forest Service reluctantly engaged
in consultations with the Fish & Wildlife Service
(regarding an endangered species--the spotted owl) that were
required by another court in separate litigation. |
| February 18 |
The
Federal Circuit reversed the Court of Federal Claims in the Agredano
case and held the "as is, where is" warnings at a
federal vehicle auction meant the Government bore no
responsibility on a theory of an implied warranty when the
purchasers had to spend a year in a Mexican prison after
hidden marijuana was discovered in the vehicle.
There are
several ASBCA decisions just out:
Todd
Pacific Shipyards discusses (i) the standards for CDA
jurisdiction over "new" and revised claims not yet
presented to a Contracting Officer for decision and (ii) the
time when a claim accrues for purposes of the CDA's statute of
limitations.
On
reconsideration in Wimberly,
Allison, Tong & Goo, the Board affirmed its decision
to dismiss a government claim when the Contracting Officer
rescinded his decision after an appeal had been filed. The
Board reasoned that the government claim was not for a sum
certain and, therefore, that the Board lacked CDA
jurisdiction.
In Symbion
Ozdil Joint Venture, the Board decided that claims for
extra work on a contract that was subsequently terminated for
convenience should be priced at the unit price stated in the
contract specifications rather than at cost pursuant to the
"Changes" clause. |
| February 16 |
Medtek
lost its appeal at the CBCA because it failed to offer
evidence to prove any of its three areas of claimed costs:
extra construction costs; lost profits; and attorneys fees. |
| February 11 |
DFARS Case
2008-D005: Effective March 15, the DoD is modifying Part 217
of the DFARS by adopting as final, with several changes, the
current interim rule (i) to address statutory provisions
relating to interagency
procurements on behalf of DoD, and (ii) to add new policy
(a) to cover the requirements of Section 801(b) of the
National Defense Authorization Act for Fiscal Year 2005
regarding the circumstances under which property and services
in excess of the simplified acquisition threshold can be
acquired through civilian agencies and (b) to expand existing
DFARS definitions. |
| February 10 |
The
Department of Agriculture is proposing (i) to amend the Guidelines
for Designating Biobased Products for Federal Procurement
to designate the following items within which biobased
products would be afforded Federal procurement preference:
disposable tableware; expanded polystyrene foam recycling
products; heat transfer fluids; ink removers and cleaners;
mulch and compost materials; multipurpose lubricants; office
paper; topical pain relief products; and turbine drip oils;
and (ii) to establish minimum required biobased contents for
each of these items. Comments are due by April 12. |
| February 8 |
The
VA has adopted as final, without changes, an interim
final rule that implements portions of the Veterans Benefits,
Health Care, and Information Technology Act of 2006, which
requires the VA to verify
ownership and control of veteran-owned small businesses,
including service-disabled veteran-owned small businesses. The
final rule defines the eligibility requirements for businesses
to obtain ‘‘verified’’ status, explains examination
procedures, and establishes records retention and review
processes. In the same document, the VA also has implemented
new interim final requirements, that eligible owners work
full-time in the business for which they have applied for
acceptance in the Verification Program, changes the time
period for issuance of reconsideration decisions from 30 to 60
days, and changes the distribution of profits for limited
liability companies and employee stock ownership plans and
solicits comments on these regulatory amendments only.
Comments on the interim portions of these new rules are due by
March 10. |
| February 5 |
Esterhill
Boat Service Corp. lost its protest at the Court of
Federal Claims because the firm waited until after offers were
submitted to claim a solicitation requirement unduly
restricted competition.
The
GAO published decisions sustaining three protests. AINS,
Inc., won its protest because of a lack of meaningful
discussions; specifically, the agency's request for a new
project schedule did not adequately apprise the firm that the
agency's evaluators considered its original project schedule
too short. You ought to make a note of this unusual decision
because there are hundreds of prior decisions where the GAO
has said that meaningful discussions only require the agency
to alert offerors to the general areas in which their
proposals are found wanting. C2C
and Cahaba
Safeguards won companion protests because the GAO was not
satisfied with the agency's evaluation of a mitigation plan
for a possible organizational conflict of interest submitted
by the successful offeror. |
| February 4 |
The GAO
published two decisions sustaining protests by Velos, Inc.
Velos won the first protest because, during discussions, the
agency misled
it into believing its proposed terms for a software license
were acceptable, when the agency subsequently found them
unacceptable. Then, after the GAO's original decision had
forced the agency to reevaluate, the GAO found the reevaluation
unreasonable because the Source Selection Official had (i)
ignored the technical evaluation panel on one issue in favor
of the opinion of a consultant who had reviewed only the
response to one discussion question rather than evaluating the
proposals as a whole and (ii) downgraded Velos' performance
risk solely on the basis of the date of the D&B report it
had submitted.
A proposed
rule would (i) amend the FAR to implement Section 807 of the
Ronald W. Reagan National Defense Authorization Act for Fiscal
Year 2005, which requires an adjustment every 5 years of acquisition-related
thresholds for inflation using the Consumer Price Index
for all urban consumers (except for Davis-Bacon Act, Service
Contract Act, and trade agreements thresholds) and (ii) use
the same methodology to change nonstatutory FAR
acquisition-related thresholds for adjustment in 2010.
Comments are due by April 5. |
| February 2 |
GSAR
Case 2008-G504: Effective March 4, the GSA is revising Part
512 of the GSAR regarding the "Acquisition of
Commercial Items."
In
Rahil
Exports, the ASBCA dismissed an appeal by a subcontractor
for lack of jurisdiction because the subcontractor had no
privity of contract with the Government either through an
alleged agency relationship (with the prime allegedly acting
on behalf of the Government) or through a quantum meruit
recovery via an implied-in-fact contract.
In Mach
II, the standard procedure under an ID/IQ contract was for
the Contracting Officer to send the contractor an unsigned,
proposed delivery order, which the contractor would sign and
return, after which the Contracting Officer was to sign and
formally issue it. The contractor claimed the Contracting
Officer was often late in this second step, which was just a
formality. The Government refused to pay for some orders which
the contractor shipped without the Contracting Officer having
signed the delivery orders. The ASBCA denied the contractor's
subsequent appeal. Make sure all the "i's" are
dotted when you deal with the Government.
Somebody's
not getting the message. In Free
& Ben, Inc., the ASBCA denied the contractor's second
motion to reconsider the Board's denial of the contractor's
first motion for reconsideration of the Board's denial of the
contractor's motion for summary judgment.
On the
other hand, some victories on dispositive motions can only be
seen as temporary. In UniTech
Services Group, the ASBCA denied the Government's motion
for judgment on the pleadings after the contractor's complaint
alleged the Government had breached (or, at least, had
terminated for convenience) an implied-in-fact requirements
contract for laundry services, after the Government declined
to extend the last in a series of such contracts going back 35
years, because the Government had finally decided to opt for
disposable uniforms for work involving radiation. Something
tells me the contractor should not get its hopes up on this
one.
The CBCA
upheld a default
termination because, after the contract's original
completion date had passed, the contractor did not submit a
new schedule, forcing the Contracting Officer to issue one
unilaterally, after which she terminated the contractor
because she reasonably determined (after issuing show cause
and cure notices) that the contractor could not complete the
work within the remaining time. |
| February 1 |
I have
added cases for 2006 to the Court of Federal Claims Contracts
Disputes and Bid
Protest pages, and I have divided the former page into
subject areas. Towards the end, I was bleary-eyed, so if you
spot mistakes, please let me know.
In K-Mar
Industries, the Court of Federal Claims held that the
agency did not act irrationally in giving the awardee's
staffing plan a technically-acceptable rating (despite the
plaintiff's contention the awardee misclassified workers in
violation of Service Contract Act) because (i) the awardee did
not manifest an affirmative intention not to be bound by that
Act and (ii) the specific SCA evaluation advocated by the
protester was not in the solicitation evaluation plan.
In
DMS
All-Star Joint Venture, the same court held that the price
discussions with offerors were fair, were not unequal, and did
not improperly alert one offeror that it must lower its price
in a particular area. |
| January 27 |
The GAO
sustained two protests: one by American
Security Programs against a task order outside the scope
of an FSS contract; and another by LIS,
Inc. against a flawed best value analysis lacking in a
documented rationale for its conclusions. |
| January 26 |
The ASBCA
issued three decisions. It upheld a default termination in ZIOS
Corporation. It held the Government did not unreasonably
delay consideration or improperly reject a subcontractor's
submittals in a construction contract in Clark
Construction. Finally, in Smoke
Blotter, it found it lacked CDA jurisdiction over a
contractor's protest of the issuance of a delivery order to
its competitor. |
| January 23 |
In
companion decisions, the GAO sustained protests by McKissack+Delcan
JV II and PMO
Partnership Joint Venture after the DOT had found the
accounting systems proposed by two joint ventures for a cost
reimbursable contract unacceptable simply because each
proposal was based on using the individual indirect rates of
the JV partners. The GAO thought this was a matter of
responsibility rather than responsiveness, rejected the
agency's unsupported conclusion that CAS 401 demanded a single
overhead rate for the JV, and found no other rational basis
for the agency's conclusion.
The
President has issued a Memorandum
that begins the process of collecting information to assess
the extent of, and then to address, the problem of firms who
are delinquent in paying federal taxes being allowed to bid on
government contracts. |
| January 22 |
Although
this is not exactly on topic, pursuant to one of President
Obama's initiatives, various government agencies are
posting a bunch of previously unavailable data
to the internet. The new data collections will be available at
data.gov. |
| January 20 |
DFARS Case
2009-D003: The DoD is proposing (i) to amend the DFARS to
implement Section 807 of the Ronald W. Reagan National Defense
Authorization Act for Fiscal Year 2005 (which provides for
adjustment every 5 years of statutory
acquisition-related thresholds) and (ii) to review
nonstatutory acquisition thresholds. Comments are due by March
22.
DFARS Case
2008-D046: The DoD is converting the interim rule issued July
29, 2009, to a final rule without any changes. The rule amends
the DFARS to implement the Dominican
Republic—Central America—United States Free Trade
Agreement with respect to Costa Rica, and the United States-Peru Trade Promotion Agreement by waiving the
applicability of the Buy American Act for some foreign
supplies and construction materials and specify procurement
procedures designed to ensure fairness.
DFARS Case
2006-D051: The DoD also is converting the interim rule issued
January 10, 2008, to final without change. The rule implements
Section 802 of the National
Defense Authorization Act for Fiscal Year 2008, which places
limitations on the award of new contracts for lead
system integrator functions in the acquisition of major
DoD systems.
I'm
gradually adding more decisions to the Court of Federal Claims
Contract Disputes page and the Court of Federal Claims Bid
Protest page. This morning, I noticed the following conclusion
of a 2006 decision
in which Judge Allegra held against the Government on a
suretyship issue. Enjoy--
"The refrain of a 15th century
English ditty, known as the 'Riddle Song,' goes –
I have four
brothers over the sea,
Perry merry
dictum domine,
They each
sent a present unto me,
Perry merry
dictum domine,
Partum
quartum pare dissentum
Perry merry
dictum, domine.
One supposing that these lyrics say
something profound about the power (domine) of dictum would be disappointed, as the
rhyming 'Latin' employed is prattle. While it might be too
harsh to say the same of defendant’s dictum-driven
attempt to reinvent the law of subrogation, the fact of the
matter is that its theory lacks not only precedential support,
but a doctrinal foundation (with the latter undoubtedly
contributing to the former). With this theory now having been
rejected by a sextet of decisions, a prolonged fermata perhaps
is in order." |
| January 19 |
The DoD is
contemplating a Reciprocal Defense Procurement Memorandum of
Understanding with the Czech
Republic. Comments are due by February 18. |
| January 15 |
The Army
Corps of Engineers is proposing an interim "Continuing
Contracts" funding clause for use only on specially
designated civil works projects, which is designed (i) to provide
options for funding contracts spanning more than one fiscal
year after the enactment of statutory restrictions to the
Corps’ continuing contract authority and (ii) to allow
Congress more oversight over continuing contracts and better
control over the rate at which funds are spent on projects so
that contracts will obligate funds in close alignment with
prerogatives reflected in budget documents and appropriations
acts. Comments are due by March 16.
DFARS
Case No. 2009-D038: The DoD is proposing to amend the
DFARS to improve the effectiveness of DoD oversight of
contractor business systems by (i) defining contractor
business systems as accounting systems, estimating systems,
purchasing systems, earned value management systems (EVMS),
material management and accounting systems (MMAS), and
property management systems, and (ii) implementing a business
systems clause which includes payment withholding that allows
administrative contracting officers to withhold a percentage
of payments, under certain conditions, when a contractor’s
business system contains deficiencies, including (a) interim payments under cost reimbursement
contracts, incentive type contracts, time-and-materials
contracts, or labor-hour contracts; (b) progress
payments; or (c) performance-based
payments. Comments are due by March 16. |
| January 13 |
There are
a couple of new ASBCA decisions out. After the Government did
not seek to extend a stay covering a fraud investigation, Unconventional
Concepts won most of its claims on summary judgment, and
the Board dismissed several government claims because they
were not the subject of a Contracting Officer's
decision. COSTAR lost its claims on a host of bases: the lack
of authority of the government official allegedly requiring
changes; extra work covered by bilateral modifications;
performance of work as a volunteer; and a failure of proof as
to alleged damages. |
| January 12 |
The SBA is considering granting a waiver of
the Nonmanufacturer Rule for Compressed
and Liquefied Gases, PSC 6830, NAICS code 325120. Comments
are due by January 27.
Off topic
rant: One of the items that appears likely to be included in
the final version of the new health care reform act is a 40%
tax on so-called "Cadillac" health insurance plans.
It is intended to target those individuals who have plans that
include such things as no (or extremely low) deductibles and
concierge doctor service. The problem is that the way the
current bill identifies those plans is simply by including all
plans that cost over a certain amount (more than $8500 per
year for individuals). That amount might buy a 24-year-old
person working for a large company a Cadillac plan. I can tell
you from painful and ongoing personal experience that it does
not buy anything close to a Cadillac plan for a 62-year-old,
self-employed lawyer who gets his insurance through the State
Bar of Texas Insurance Trust. People like me pay an
astronomical amount just for basic insurance with a very high
deductible and large co-payments. Adding a 40% tax on top of
that is not what I would call health care "reform."
:) |
| January 11 |
The SBA
has announced additional
public meetings in Miami (January 14) and Los Angeles
(January 19) as part of its consideration of proposed
revisions to its 8(a) and size regulations the agency
first announced October 28, 2009. |
| January 8 |
In Government
Technical Services, the Court of Federal Claims held that
the Government's failure to exercise an option under an ID/IQ
contract did not establish bid protest jurisdiction in
the court.
There are
seven new size decisions listed at the top of the size
decisions on the SBA OHA
web page. The most interesting of the bunch is Alutiiq
International Solutions, which overturned the Area
Office's finding that a firm violated the ostensible
subcontractor rule. The OHA noted that the firm's associations
to which the Area Office objected were with its parent rather
than a subcontractor and also fell within the ANC exemption to
the SBA's affiliation rules.
I have
redone the SBA OHA Recent
Decisions page so that the size decisions are now
organized by general subject matter to help you search them
more easily. Clicking on either the general headings at the
top of the page or the specific headings in the table
underneath the Size Appeals section will take you to the
appropriate part of the page.
While
working on revising that web page, I belatedly noticed
something. The SBA's published decision re a NAICS appeal by
Inklings Media instructs us (mistakenly, I assume) to
cite it as: NAICS Appeal of Inklings Media Company, LLC, SBA No. SIZ-4850 (2007). See
the very top of the first page of the decision. However, it is
a NAICS decision, and, in the actual case caption (on that
same page, just below the previously-quoted instruction), the
citation is "SBA No. NAICS-4850," instead of SBA No.
SIZ-4850. I assume the second is the correct title of the
case, but the SBA's url address for it also identifies it as
SIZ-4850. Confusing enough for you? My only point is that, if
you are looking for SIZ-4850, you will actually find a NAICS
decision. |
| January 7 |
The Department
of Energy (DOE) is proposing to amend the DOE Acquisition
Regulation (DEAR) Subchapters E (General Contracting Requirements),
F (Special Categories of Contracting), and G (Contract
Management), to conform to the FAR, remove out-of-date
coverage, and update references. Comments are due by
February 8.
I have
reorganized the Recent
Successful GAO Protests (2005-Present) page into subject
areas, so that it matches the Successful
GAO Protests (2000-2004) page.
While
we're on the subject of the GAO, it sustained a protest by C&B
Construction because the agency did not adequately
document its rationale for selecting a higher-priced quote in
response to a solicitation for the award of a task order under
a BPA. |
| January 6 |
Effective
today and applicable to official travel performed on or after
January 1, the GSA's FTR per-mile
reimbursement rates for official travel are as follows:
privately-owned automobiles ($.50); privately-owned
motorcycles ($.47); and privately-owned airplanes ($1.29).
DFARS
Case 2009-D012: The DoD is proposing to amend the DFARS to
implement (i) the July 9, 2009 waiver (issued by the Deputy
Secretary of Defense) of the section 302(a) of the Trade
Agreements Act of 1979, as amended (which generally prohibits
acquisitions of products or services from nondesignated
countries) in order to allow acquisition from the nine South
Caucasus/Central and South Asian (SC/CASA) states; and (ii)
the Deputy Secretary's determination of inapplicability of the
Balance of Payments Program evaluation factor to offers of
products (other than arms, ammunition, or war materials) from
those SC/CASA states to support operations in Afghanistan.
Comments are due by March 9. |
| January 5 |
Executive
Order 13256 (dated Dec. 29, 2009, but published today)
"prescribes a uniform system for classifying,
safeguarding, and declassifying national security information,
including information relating to defense against
transnational terrorism." It is accompanied by a memorandum
to agencies containing directions for implementing the E. O.,
as well as a document
listing those officials who are authorized to classify items
as SECRET or TOP SECRET. |
| January 4, 2010 |
Happy New
Year!
You may
access the complete 2009 blog here.
I've also
made what I hope you will agree are a few improvements to the
website:
First, I
have added a page that lists successful
GAO protests (by general subject areas) from 2000-2004. Of
course, the website still includes the page listing successful GAO
protests from 2005-present.
I have
also added more, earlier cases to both the Federal Circuit
protest decisions page and the Federal
Circuit contract disputes decisions page, so that each
page now covers decisions from the beginning of 2000 to the
present.
I have
reorganized the cases on the recent ASBCA decisions
page into subject areas to help you search those decisions
more easily.
Finally,
to eliminate some clutter, I have broken out all the Winstar-related decisions and
put them on their own, separate page.
I hope to
gradually extend the decisions listed on other pages back to
2000, but that probably will take awhile now that the
Christmas season is over, and I don't have nearly as much time
on my hands. Maybe next Christmas. . . .
At any
rate, I hope the changes help you find information that may be
useful to you. |
| |
The complete 2009 blog
can be found here. |
|