| December 31 |
The
Department of Defense Appropriations Act, 2010, Public Law
111-118, was enacted December 19.
Beginning
January 1, the CDA prompt
payment interest rate is 3 1/4 percent. |
| December 30 |
Five new
ASBCA decisions have been published. Three are essentially
requests for reconsideration of earlier decisions. The
Government won its motions for summary judgment dismissing
various claims by Bruce
E. Zoeller because those claims already had been decided
by the Board and the Court of Federal Claims. Corners
and Edges (which is certainly tenacious) lost another
round of various motions for rehearing, recusal, and
reconsideration. SUFI
Network Services lost on most of its grounds in its second
request for reconsideration, but did obtain some additional
monetary relief in a couple of areas.
Mark
O'Connor deals with the Government's liability for cost of
various repairs under the "Restoration" clause of
its military housing lease. R.
L. Bates General Contractor Paving & Assocs. lost on
most of its claims related to road paving and repairs, but did
prove it was entitled to the return of unearned Prompt Payment
discounts improperly deducted from its invoices by the
Government.
By the
way, if you are wondering why I mentioned all five decisions
here, when none of them breaks new legal ground, I am working
on changes to some of my other web pages (including the
"Recent ASBCA Decisions" page, where I normally
would have listed these decisions), and I won't publish those
changes until Monday, so this is a temporary
solution. |
| December 29 |
In Unisys
Corp., the Court of Federal Claims discussed the confusing
recent history of the statutes and regulations governing the
Transportation Security Administration ("TSA") and
concluded that CICA's automatic stay provisions now apply to
protests of TSA procurements at the GAO.
The DoD is
adopting as final (with only a minor change) the interim rule
that amended the DFARS to implement Section 802(a) of the
National Defense Authorization Act for Fiscal Year 2007 (and
DoD policy mandates) to require the DoD to assess long-term
technical data and computer software needs when acquiring
major weapon systems and subsystems.
The Office
of the United States Trade Representative has published the procurement
thresholds applicable to a wide range of trade
agreements. |
| December 25 |
Merry Christmas, everyone! |
| December 24 |
Sometimes
an agency's perseverance (obstinance) prevails. After losing
two GAO protests, the Bureau of Prisons stuck with its choice
for contractor on the second required reevaluation, and Bannum
lost the third GAO protest of that decision. Now, Bannum
loses again at the Court of Federal Claims on the oft-repeated
principle that its mere disagreement with the agency's
evaluation of various factors is not sufficient to sustain the
protest.
Several
DFARS regulations have been published:
DFARS Case
2007-D004, entitled "Allowability of Costs to Lease
Government Equipment for Display or Demonstration," is a
final rule specifying that
monies paid to the Government for the leasing
of government equipment are unallowable, except in the
case of foreign military sales contracts.
DFARS Case
2005-D010, entitled "Definitions of Component and
Domestic Manufacture," revises the definitions of those
terms in order to clarify
the distinction between foreign acquisition policies that
apply only to top-level components
of end products and those that apply to both top-level and
lower-tier components of end products.
DFARS Case
2008-D009, entitled "Statutory Waiver for Commercially
Available Off-the-Shelf Items," adopts as final (without
change) the interim rule conforming the DFARS to the FAR changes implementing the waiver
of the component test of the Buy American Act to contracts
and subcontracts for the acquisition of COTS items. |
| December 23 |
The
Commerce Department's Bureau of Industry and Security
published a final rule to amend certain requirements in the
Export Administration Regulations (EAR) that apply to Albania
and Croatia, based upon the accession of those two
countries to formal membership in NATO on April 1, 2009. |
| December 22 |
The SBA
has issued the following correction
to 13 C.F.R. §121.201 in its small business size regulations:
"[I]n the table [entitled] 'Small Business Size Standards
by NAICS Industry,' under Sector 54, Subsector 541, remove the
three subentries under NAICS code 541712, beginning with the
word 'EXCEPT'."
The GAO
sustained the protest of Coastal
Environments because the agency did not include any but
the highest technically ranked, highest priced proposals in
its tradeoff analysis, even though lower priced proposals were
judged technically acceptable and low risk. |
| December 18 |
The GAO
published the decision it had earlier announced (see
December 14 entry below) sustaining the protests of Navistar
Defense and BAE Systems against the Army's award to
Oshkosh for the production of the family of medium tactical
vehicles because there was no basis in the record for the past
performance evaluation; and the risk evaluation of existing
production capabilities was improper.
|
| December 16 |
The Court
of Federal Claims published several new decisions re contract
disputes--
Digital
Technologies (DTI) is a fascinating case. As a result of a
complicated set of facts and a series of past protests (all of
which are explained in interesting, if lengthy, detail
in the court's opinion), the Government (while originally
intending to award only one ID/IQ contract) ended up with two
of them and specifically included clauses and procedures in
each that guaranteed the contractors the fair opportunity to
compete for task orders to be issued under them. After having
ordered (more than) the minimum amount required by its
contract with DTI, the Government exercised the contract
option only in the second contract and allowed DTI's contract
to expire. DTI filed a contract claim under the CDA, alleging
breach of the duty to give it a fair opportunity to compete
for orders and a bad faith failure to exercise its option. The
Government sought dismissal on the grounds that this was a
thinly disguised bid protest subject to the statutory
limitation on task order protests. The court ultimately
disagreed with the Government. To reach that conclusion, the
court (more than 30 years now after the effective date of the
CDA) became the latest forum (in a very, very long line) to
note that it must examine whether this was a CDA claim because
the CDA does not define that term (which is my pet CDA peeve).
Ultimately, the court concluded that the contractor's
submission was a CDA claim and rejected the Government's
motion to dismiss.
In CBS
Corp., the court held that the proper date to consider a
segment closed under the original version of CAS
413-50(c)(12)(1986) was the date the contractor had closed its
plant and transferred all remaining work on its sole
government contract to another segment rather than the date
its subcontractor had finally completed all its work on the
subcontract, as the Government had contended.
In a companion
case issued the same day, the court examined whether a
segment-closing calculation must include (and whether the
Government is liable for) pension assets and liabilities
transferred to another company in a segment sale. Ultimately,
the court concluded that "the [G]overnment is not liable
to CBS for pension costs attributable to the pension deficit
transferred to [segment buyer] and CBS is not entitled to
payment for that transferred
deficit."
Minor
changes and corrections have been made to (i) the Department
of Homeland Security's regulations prohibiting awards of guard
services contracts to firms owned by convicted felons and
(ii) the Rules
of Procedure for the Civilian Board of Contract Appeals. |
| December 15 |
In McDonnell
Douglas Services, the ASBCA dismissed the Government's
claim for defective pricing against the contractor's sub
because it was time-barred by the CDA's six-year statute of
limitations.
GSAR Case
2007-G507: Effective January 14, 2010, the GSA is revising
Part 511 of the GSAR re "Describing
Agency Needs." |
| December 14 |
Although
the decision has not yet been redacted for public release, the
GAO announced this morning that it had sustained the protest
of Navistar
Defense, LLC and BAE Systems, Tactical Vehicle Systems LP,
B-401865 et al. concerning the
procurement of the family of medium tactical
vehicles because the Army’s evaluation was flawed with
regard to the evaluation of Oshkosh’s proposal under the
capability evaluation factor, and the evaluation of Navistar’s
past performance. |
| December 11 |
The Bureau
of Industry and Security (BIS) has published revisions to the
Commodity Control List (CCL) in the Export Administration
Regulations (EAR) to
implement changes made to the Wassenaar Arrangement’s List
of Dual
Use Goods and Technologies maintained and agreed to by
governments participating in the Wassenaar Arrangement on
Export Controls for Conventional Arms and Dual Use Goods and
Technologies.
Effective
December 28, the Under Secretary of Defense (Acquisition,
Technology, and Logistics) is waiving
the limitation of 10 U.S.C. 2534 (which limits DoD procurement
of certain items to sources in the national technology and
industrial base) for the following defense items produced in
the UK:
1. Air
circuit breakers;
2. Welded
shipboard anchor and mooring chain with a diameter of four
inches or less;
3.
Gyrocompasses;
4. Electronic
navigation chart systems;
5. Steering
controls;
6. Pumps;
7. Propulsion
and machinery control systems; and
8. Totally enclosed
lifeboats.
In Distributed
Postal Consultants, an individual who had properly
executed the original contract with the Postal Service on
behalf of the plaintiff then secretly formed his own company
and fraudulently signed an agreement with the Postal Service
terminating the original contract and executing a new one with
his new company. The Court of Federal Claims held that the
Government did not breach the original contract by relying on
the individual's misrepresented status in terminating
it.
There are two new size appeal decisions from
the SBA's OHA. |
| December 10 |
In Lumbermens
Mutual Casualty, the Court of Federal Claims (i) held that
the Government had impaired the surety's collateral on a
bonded contract by improperly assessing delay damages against
the contractor and (ii) awarded the surety damages under the
theory of equitable subrogation.
Federal
Acquisition Circular (FAC
2005-38) has been published. It includes the following six
items plus technical amendments:
Item I (FAR
Case 2009-017), entitled "Revocation of Executive
Order 13201, Notification of Employee Rights Concerning
Payment of Union Dues or Fees," is a final rule that
deletes FAR
Subpart 22.16 and the corresponding clause at FAR 52.222–39,
Notification of Employee Rights Concerning Payment of Union
Dues or Fees (which had implemented E.O. 13201 and required
contractors to post a notice informing employees of their
rights concerning payment of union dues or fees and detailed
that employees could not be required to join unions or
maintain membership in unions to retain their jobs), because
that E.O. was revoked by E.O. 13496 of January 30, 2009,
entitled "Notification of Employee Rights Under Federal
Labor Laws." See entry at February 4 below.
Item II (FAR
Case 2006-026), entitled "Governmentwide Purchase
Card Restrictions for Treasury Offset Program Debts
," is a final rule (effective February 1, 2010) that
amends the FAR to
restrict the use of the governmentwide commercial purchase
card as a method of payment for offerors with debts subject to
the Treasury Offset Program.
Item III (FAR
Case 2005-041), entitled "Internet Protocol Version 6
(IPv6)," is a final rule that requires IPv6 compliant products to
be included in all new IT acquisitions using IP, which is one
of the primary mechanisms that define how and where
information moves across networks.
Item IV (FAR
Case 2008-017), entitled "Federal Food Donation Act
of 2008 (Pub. L. 110-247)," is a final rule
(adopting the previous interim rule without changes) amending
the FAR to
implement the Federal Food Donation Act of 2008 (Pub. L. 110–247),
which encourages executive agencies and their contractors, in
contracts for the provision, service, or sale of food, to the
maximum extent practicable and safe, to donate apparently
wholesome excess food to nonprofit organizations that provide
assistance to food-insecure people in the United States.
Item V (FAR
Case 2006-021), entitled "Postretirement Benefits
(PRB) FAS 106," is a final rule effective January
11, 2010, which amends the FAR to permit contractors to measure accrued PRB costs
using either the criteria in Internal Revenue Code 419 or the
criteria in FAS 106.
Item VI (FAR
Case 2006-024), entitled "Travel Costs
," is a final rule effective January 11, 2010, which
amends the FAR travel costs principle to ensure a consistent application of
the limitation on allowable contractor airfare costs.
Technical
Amendments in the form of editorial
changes are being made to FAR Parts 6, 8, 15, and 52. |
| December 9 |
The SBA has corrected the faulty urls on its
pages listing NAICS and BDP decisions. All is well again.
The SBA has extended
the comment period for the proposed changes to its JV
affiliation, mentor-protege, and 8(a) rules (see the October
28 entry below) to January 28, 2010.
In Wyoming
Sawmills, the Court of Federal Claims stayed a case for
six months to allow the contractor time to exhaust its
administrative remedies (by petitioning the Secretary of
Agriculture for relief). |
| December 8 |
The
Department of Veterans Affairs has amended its acquisition
regulation (the VAAR) to implement portions of the Veterans Benefits,
Health Care, and Information Technology Act of 2006 (the Act)
and Executive Order 13360, by permitting VA contracting
officers either to restrict competitions to SDVOSBs
or VOSBs or to award sole source contracts to such entities. The VA
also has issued an interim rule authorizing the VA to hear
protests of SDVOSB and VOSB status until the VA and the SBA
have completed the process of executing an interagency
agreement so that the SBA can hear such protests.
In States
Roofing Corp., the Court of Appeals for the Federal
Circuit reversed part of an ASBCA decision because the
contractor's interpretation of an ambiguous contract provision
was within the zone of reasonableness.
In Alatech
Healthcare, the Court of Federal Claims followed the
precedent of the CAFC in the Distributed
Solutions case and held that the Government's involvement
in a procurement by its prime contractor was sufficient to
give the court bid protest jurisdiction. The court also
interpreted the meaning of the word "feasible" in a
federal statute giving preference to domestic condom
manufacturers. |
| December 4 |
GSAR Case
No. 2006-G508: The GSA is proposing to rewrite GSAR
Part 570, entitled "Acquiring Leasehold Interests in
Real Property." Comments are due by February 2, 2010.
The ASBCA
granted the Government's motion for summary judgment denying
the VECP claim by WEDJ/Three
C's, Inc. because the contract already required what the
contractor claimed was covered by its VECP.
Make that
33 successful GAO protests on the merits. The
Analysis Group won its protest because the agency (i)
permitted the successful offeror to improve its offer through
discussions without providing the protester a similar
opportunity and (ii) failed to consider the successful
offeror's "impaired objectivity" organizational
conflict of interest. |
| December 3 |
The Port of
Bellingham won its GAO protest because the agency's
evaluation of the awardee's proposed pier location lacked a
rational basis. By my unofficial count, that's 32 successful
GAO protests on the merits so far this year. |
| December 2 |
Wonderlyn
Lorraine Bell Pinckney lost her request for
reconsideration of the Court of Federal Claims' decision that,
while the Postal Service's default termination of her contract
was improper, it was not made in bad faith. See the
August 5 entry below for a discussion of original
decision. |
| December 1 |
The Court
of Federal Claims decided that the default termination of United
Partition Systems' contract was improper (because the
wrong agency's contracting officer had decided the issue) and
should be converted to a termination for convenience, but that
the Government could reduce the contractor's
termination-for-convenience claim by the amounts required to
replace defective wall materials pursuant to the Government's
rights under the Inspection clause. |
| November 28 |
It's
probably a symptom of OCD, but I feel compelled to note that
the link errors on the SBA's pages listing NAICS and BDP
decisions are still there. I have emailed the SBA, described
the problem, provided the urls of the affected pages, and
explained to them how to correct the situation.
HHS is
publishing a complete revision of its acquisition
regulation (the HHSAR) to reflect statutory, FAR, and governmentwide and
HHS policy changes since the last revision to the HHSAR in
December 2006. The revision will become effective January 26,
2010. |
| November 25 |
Executive
Order 13520 (Nov. 20, 2009), entitled "Reducing Improper
Payments," requires, inter alia, agencies to
publish lists of the entities that have received the greatest
amount of outstanding improper
payments under government contracts, grants, etc.
The State
Department is proposing to amend Section
126.6 of the ITAR (pertaining to U.S. Government transfer
programs and foreign-owned military aircraft and naval
vessels) to clarify the circumstances when a license by
the Directorate of Defense Trade Controls is not required.
Comments are due by January 25, 2010.
In Opportunities
for the Aging Housing Corp. and Opportunities for the Aging
Housing Corp. II, the CBCA dismissed an appeal for lack of
jurisdiction because agreements involving the management of
facilities by public housing authorities, including HAP
agreements, were not covered by the CDA, even though they were
funded and regulated by HUD.
|
| November 24 |
The State
Department is proposing to amend the ITAR (22 C.F.R. §
125.4(b)(9)) to clarify that the exemption for technical
data covers data, regardless of media or format, sent or
taken by a U.S. person who is an employee of a U.S.
corporation or a U.S. Government agency to a U.S. person
employed by that U.S. corporation or to a U.S. Government
agency outside the United States. Comments are due by January
25, 2010.
Medical
Development International, Inc. Government Healthcare Services
lost its pre-award protest against its exclusion from the
competitive range. It argued that the competitive range had
not been established until after the date stated in the
solicitation to which prices must remain firm and that,
therefore, no rational price determination could have taken
place. The court noted that while such a situation was not
optimal, it could be addressed as the competition proceeded.
The interesting aspect of the case, however, is the court's
reasoning that the protester had standing. The court saw the
protest as neither fish (a pre-award protest of a
solicitation) nor fowl (a post-award protest), but held that
denying a protester standing in this situation "could
have the frustrating result of depriving [the protester]
completely of any possibility of judicial
relief." |
| November 23 |
DFARS Case
2009-D010: The DoD has published an interim rule amending
several clauses in Part 252 of the DFARS to add Taiwan
as a designated country to the list of World Trade
Organization Government Procurement Agreement designated
countries, due to the accession of Taiwan to the World Trade
Organization Government Procurement Agreement. Comments are
due by January 22, 2010.
DFARS Case
2008-D039: The DoD has issued an interim rule amending the
DFARS to implement section 825 of the Duncan Hunter National
Defense Authorization Act for Fiscal Year 2009 (Pub. L. 110–417),
which clarifies the Government’s rights in technical data in
the designs of DoD vessels, boats, craft, and components
thereof, and the Vessel Hull Design Protection Amendments of
2008 (Pub. L. 110–434). Comments are due by January 22,
2010. |
| November 20 |
The ASBCA
published three more
decisions yesterday. In Parsons-UXB
Joint Venture, the Board denied the Government's motion to
dismiss, holding that the CDA's statute of limitations did not
begin to run on the contractor's claim for back taxes until it
presented the claim to the Government and the Government
denied it. The Board also noted that, since the claim was in a
sum certain, it satisfied the CDA, even though the contractor
had not yet paid the taxes. |
| November 19 |
The DoD
has adopted five previously interim rules, without any
changes, as final DFARS rules:
DFARS Case
2008-D007 (entitled "Senior DoD Officials Seeking
Employment with Defense Contractors") implements section
847 of the National Defense Authorization Act for Fiscal Year
2008, which addresses requirements for senior DoD officials to
obtain a
post-employment ethics opinion before accepting
compensation from a DoD contractor within two years after
leaving DoD service.
DFARS Case
2008-D012 (entitled "Whistleblower Protections for
Contractor Employees") implements section 846 of
the National Defense Authorization Act for Fiscal Year 2008
and section 842 of the National Defense Authorization Act for
Fiscal Year 2009, which address protections
for contractor employees who disclose information to
government officials with regard to waste or mismanagement,
danger to public health or safety, or violation of law related
to a DoD contract.
DFARS Case
2008-D015 (entitled "Competition Requirements for
Purchases from Federal Prison Industries ") implements
section 827 of the National Defense Authorization Act for
Fiscal Year 2008, which requires the use of competitive
procedures in the acquisition of items for which Federal
Prison Industries has a significant market share.
DFARS Case
2008-D030 (entitled "Pilot Program for Transition to
Follow-On Contracting After Use of Other Transaction
Authority") implements section 824 of the National
Defense Authorization Act for Fiscal Year 2009, which amended
the DoD pilot program for transition to follow-on contracting
after use of other transaction authority, to establish a new
program expiration date and to include items developed under
research projects within the scope of the program. The pilot
program provides that certain items which do not otherwise
meet the definition of ‘‘commercial item’’ may be
treated as commercial items in the award of contracts and
subcontracts that follow an other transaction agreement.
DFARS
2008-D038 (entitled "Steel for Military Construction
Projects") implements section 108 of the Military
Construction and Veterans Affairs Appropriations Act, 2009,
which requires that American steel producers, fabricators, and
manufacturers be given the opportunity to compete for
contracts and subcontracts for the acquisition
of steel for use in military construction projects or
activities.
The ASBCA
published five new
decisions, two of them dismissing appeals for lack of
jurisdiction after the Contracting Officer rescinded his
decision. The most noteworthy of the five, however, is the Kostmayer
Construction case, in which the ASBCA held that the EAJA
does not require a firm to include its affiliates' assets in
determining its net worth for purposes of EAJA eligibility.
The CBCA
has issued two new
decisions on the merits. |
| November 18 |
The Court
of Appeals for the Federal Circuit reversed the Court of
Federal Claims' prior
decision sustaining the protest in the Alabama
Aircraft Industries bid protest. The appeals court ruled
that the lower court was wrong to fault the agency's price
realism analysis because the lower court had judged that
evaluation on the basis of how the court felt the agency
should have addressed the problem of aging aircraft rather
than limiting itself to analyzing whether the agency had
followed the evaluation scheme set forth in the
solicitation.
Usually,
protest attorneys scratch and claw just to uncover one valid
ground for protest. In Health
Net Federal Services, the GAO found a multitude of
prejudicial errors in the procurement, including flawed past
performance, price realism, and staffing risk evaluations, as
well as the appearance of an unfair advantage because a former
high level government official with access to sensitive
information had helped the awardee prepare its proposal. Don't
you wish all protests came gift-wrapped like this
one? |
| November 17 |
In Alsalam
Aircraft Co., the GAO noted it could (and did) recommend
reimbursement of costs in a meritorious protest involving an
FMS procurement. |
| November 16 |
DHS has
issued a final rule amending the Homeland Security Acquisition
Regulation (HSAR) to prohibit awards of Federal Protective
Service guard
services contracts to firms owned, controlled, or operated
by an individual who has been convicted of a serious felony. |
| November 14 |
As of this
morning, the errors in the SBA's pages listing various types
of cases by case number, which I mentioned in the second entry
in the November 9 post below, are still there. For example, if
you try to link from the page listing "msbe"
and "bdp" cases to one of those BDP decisions,
you will receive an error message. To get to the actual case,
you need to revise the linked url address so that the last
occurrence of "bdp" in the address is all caps.
Let's see how long it takes the SBA to catch the errors. I
wonder if anyone from the SBA reads this blog? 
In its
post-award protest, Afghan
American Army Services Corp. proved there were multiple
failings in the Government's evaluation, but the Court of
Federal Claims only awarded it bid and proposal costs rather
than the requested injunction.
In the Phillip
Ozdemir bid protest, the Court of Federal Claims decided
its jurisdiction under 28 U.S.C. 1491(b)(1) was broad enough
to cover a protest that a DOE agency had refused to consider
plaintiff's concept paper after having solicited such papers.
The Government had argued there was no jurisdiction because
there was no "procurement." |
| November 13 |
FAR Case
2008–025, entitled "Preventing Personal Conflicts of
Interest for Contractor Employees Performing Acquisition
Functions," is a proposal to amend the FAR to address personal
conflicts of interest by employees of Government
contractors as required by section 841(a) of the Duncan Hunter
National Defense Authorization Act for Fiscal Year 2009 (Pub.
L. 110–417). Comments are due by January 12, 2010.
The GAO
sustained another protest (could we be heading for a
record-breaking year?), this one against the issuance of a
purchase order to an FSS
contractor for items that were not included on its FSS
contract list. |
| November 11 |
There is a
new CBCA decision out,
which reaffirms that contractors may argue inconsistent
theories of recovery in the alternative on appeal.
In The
Analysis Group, the Court of Federal Claims refused to
reinstate an automatic stay after an agency override during
the pendancy of a GAO protest. The court noted it would reach
the same result regardless whether it used the four-pronged
test of an override decision enunciated in the APA or the
four-pronged analysis announced in the Reilly's
Wholesale Produce case. |
| November 10 |
Yet
another successful GAO protest, this one by Humana
Military Healthcare Services, which established that the
agency's evaluators failed to give it proper credit for
the provider discounts it would be able to obtain in the
region where the contract would be performed. |
| November 9 |
The SBA's
OHA has published six new size decisions. In C.E.
Garbutt Construction, the OHA found a violation of the
ostensible subcontractor rule when the protested firm's only
contribution to the project was its HUBZone status and its
contract was simply a pass through. In Inuit
Services, the OHA upheld an Area Office finding that a
firm was other than small because that is what the materials
it had submitted to the Area Office clearly stated, even
though the firm asserted on appeal, and offered evidence that,
its original submission had been mistaken. The reasoning here
was that the Area Office had to base its decision on the
record before it. In Blue
Cord Construction, the OHA found affiliation between a
newly organized firm and a firm whose key employee and officer
had formed the new firm and which was providing it with
technical and financial assistance, where there was no
fracture.
By the
way, I don't know how long this error will last (probably not
long), but the SBA just reorganized its pages listing various
kinds of decisions in numerical order (like its list of size
decisions), so that the lists would be in descending order
rather than ascending order like they have been previously.
However, in doing that, it introduced errors in the linked
urls on its page of NAICS
decisions, so that, if you click on one of those links (at
least the few I tried), you receive an error message. As best
as I can tell, the error can be corrected for any particular
link by changing the second appearance of the term
"NAICS" in the url to all caps. I just found
the same error for some of the cases (the "bdp"
designations beginning about a third of the way down) on the
SBA list of 8(a)
decisions. |
| November 4 |
In Teknowledge,
the Court of Appeals for the Federal Circuit affirmed the
Court of Federal Claims' decision because a contractor's
software amortization costs were not properly allocable to its
contract and, therefore, were unallowable.
There are
also a couple of new Court of Federal Claims contract
disputes decisions just out. |
| November 3 |
The SBA
has issued a new definition (effective May 3, 2010) of the
term "employee"
for purposes of the HUBZone program. The new definition at 13
C.F.R. 126.103 reads as follows: "Employee means all individuals employed on a full-time, part-time, or
other basis, so long as that individual works a minimum of 40
hours per month. This includes employees obtained from a
temporary employee agency, leasing concern, or through a union
agreement or co-employed pursuant to a professional employer
organization agreement. SBA will consider the totality of the
circumstances, including criteria used by the IRS for Federal
income tax purposes and those set forth in SBA’s Size Policy
Statement No. 1, in determining whether individuals are employees of a concern. Volunteers
(i.e., individuals
who receive deferred compensation or no compensation,
including no in-kind compensation, for work performed) are not
considered employees. However, if an individual has an
ownership interest in and works for the HUBZone SBC a minimum
of 40 hours per month, that owner is considered an employee
regardless of whether or not the individual receives
compensation."
Several
new ASBCA decisions
have been published, the most interesting of which follow.
In HMRTECH2,
LLC (yes, I typed that correctly, and it was fun, too),
the Board held it had CDA jurisdiction over a contractor's
claim that the Government's improper interpretation of a
contract clause would deprive the contractor of access to
future task orders (on the grounds that the contractor/joint
venture had graduated from the SBA's 8(a) program).
In Montage,
the Board refused to dismiss an appeal even though the
contractor had not submitted a document entitled "Notice
of Appeal," but rather had evidenced an intent to appeal
in a document entitled "Status Report" and had
attached the wrong claim to its Complaint.
In DynCorp,
the Board needed more evidence on the question when the
contractor should have known about a mistake for purposes of
determining when its claim accrued. The Board also discussed
the "continuing claim" doctrine in terms of an
option contract: "With respect to the option years, we
believe the claim is subject to the continuing claim doctrine
which we have determined to have application to government
contract cases. Under that doctrine, a "claim must be
inherently susceptible to being broken down into a series of
independent and distinct events or wrongs, each having its own
associated damages." Only the base year was initially
awarded. Each subsequent year was to be separately awarded at
the government’s option. Thus, if the government chose not
to award additional option years, there would be no claim for
those years. Therefore, the portions of the claim attributable
to each option year are distinct events with its own
associated damages."
BearingPoint
involves various interesting disputes concerning cost
allowability and allocability under a cost reimbursable
contract. |
| October 31 |
Happy Halloween!
Several
new CBCA decisions
have been published, including Medtek,
in which the Board imposed severe evidentiary sanctions for
the contractor's refusal to comply with the Board's discovery orders.
In Impresa
Construzioni Geom. Domenico Garufi, which involved
determining the size of an Italian firm for purposes of
assessing its eligibility for an EAJA recovery, the Court of
Federal Claims directed supplementation of the administrative
record when faced with incomplete and, in some cases,
untranslated documents in Italian. |
| October 28 |
The GAO
sustained the protest of RBC
Bearings against a sole source contract award because the
agency's lack of advance planning created the situation.
The SBA is
proposing to amend its joint
venture affiliation, 8(a), and mentor-protege
regulations in many important respects, only a few of
which I have space to mention here. First, whereas the current
rule at 13 C.F.R. 121.3(h) limits joint ventures to submitting
three offers over a two year period, the proposed rule changes
the limit to three awarded contracts over that period.
Moreover, the proposed rule makes clear that it is not
intended as an absolute prohibition against the joint venture
competing for more than three contracts, but only a statement
that its members will be treated as affiliates if it does so.
Secondly, the proposed rule specifically recognizes and allows
the current practice of two entities who have reached the
basic limit forming a new joint venture, but adds this
caution: "At some point, however, such a longstanding
inter-relationship or contractual dependence between the same
joint venture partners will lead to a finding of general
affiliation between and among them. For purposes of this
provision and in order to facilitate tracking of the number of
contract awards made to a joint venture, a joint venture must
be in writing and must do business under its own name. . .
." These same rules will apply to SBA mentor-protege
joint ventures involving an 8(a) protege. Third, the proposed
rule emphasizes that the SBA is the only agency that may
determine there is an exception from affiliation between a
mentor and its protege, even in mentor-protege programs
purportedly established by other agencies, such as the DoD's
and the GSA's programs. There are many other proposed
revisions to the 8(a) and mentor-protege regulations. This is
major proposed rulemaking that should be studied carefully by
all those who may be affected by its changes. Comments are due
by December 28.
Pursuant
to 31 U.S.C. 3511(d), the Federal Advisory Committee Act (Pub.
L. 92–463), as amended, the Federal Accounting Standards
Advisory Board (FASAB) has released
the Exposure Draft on Subsequent Events: Codification of
Accounting and Financial Reporting Standards Contained in the
AICPA Statements on Auditing Standards. AU Section 560,
Subsequent Events, of the AICPA Statements on Auditing
Standards includes accounting and financial reporting guidance
that is not discussed in the authoritative literature that
establishes accounting principles. The objective of the
proposed Statement is to incorporate that guidance into the
authoritative literature of the FASAB. The Exposure Draft is
available here.
Comments are requested by December
28. |
| October 27 |
The
Department of Agriculture has issued a final rule defining the
following nine categories of biobased
products that will receive federal procurement preference
as provided for under section 9002 of the Farm Security and
Rural Investment Act of 2002, as amended by the Food,
Conservation, and Energy Act of 2008: (i) chain and cable lubricants; (ii)
corrosion preventatives; (iii) food cleaners; (iv) forming
lubricants; (v) gear lubricants; (vi) general purpose household cleaners;
(vii) industrial cleaners; (viii) multipurpose cleaners; and
(ix) parts wash solutions. The USDA is also establishing a
minimum biobased content requirement for each of these items.
The GSA is
amending FTR provisions covering premium
class travel and transportation allowances. |
| October 24 |
In
accordance with the Livestock Mandatory Reporting
Reauthorization Act, the Department of Agriculture has issued
proposed rules reviving the Swine
Contract Library. Doubtless you are as pleased as I
am to learn that soon we will be able, once again, to while
away blissful hours, totally oblivious to our worldly cares,
browsing to our hearts' content in the Swine Contract
Library. Comments (all of which I predict will be
ecstatic) are due by December 28.
GSAR Case
2006-G515: the GSA has rewritten GSAR Part 532, Contract
Financing. The GSA has revised the FTR to include an
updated table of meal
cost adjustments for meals furnished by the Government or
included in ticket prices. |
| October 23 |
The GAO
sustained the protest of Frank
A. Bloomer--Agency Tender Official in an A-76
public-private competition because the agency unreasonably :
(i) accepted the private-sector offeror’s revised fringe
benefit ratios in its cost realism analysis;
(ii) accepted the private-sector offeror’s unsupported
assumption that the firm could perform a significant portion
of the workload 10 percent more efficiently; and (iii)
allowed the private-sector offeror to omit the labor cost
associated with the material supply function from its cost
proposal, and these errors prejudiced the protester. |
| October 21 |
The SBA is
proposing to increase the size standards for five industries
in NAICS Sector 72, Accommodation
and Food Services: NAICS 721110, Hotels and Motels (from
$7.0 million to $30 million); NAICS 721120, Casino Hotels
(from $7.0 million to $30 million); NAICS 722211, Limited
Service Restaurants (from $7.0 million to $10 million); NAICS
722212, Cafeterias (from $7.0 million to $25.5 million); and
NAICS 722310, Food Service Contractors (from $20.5 million to
$35.5 million). Comments are due by December 21.
The SBA is
proposing to increase the size standards for 18 industries in
NAICS Sector 81, Other
Services. The explanatory comments for the proposed
changes are quite detailed and lengthy, but you can find a
table listing the specific changes proposed for those 18
industries at 74 Fed. Reg. 53950 (Oct. 21, 2009). Comments are
due by December 21.
The SBA is
proposing to increase the size standards for 48 industries in
NAICS Sector 44-45, Retail
Trade. A lengthy table listing both the industries
affected by the proposed changes and those that will remain
unchanged begins at 74 Fed. Reg. 53929 (Oct. 21, 2009).
Comments are due by December 21.
The SBA
has published
a document entitled "SBA
Size Standards Methodology," which explains the SBA's
process for analyzing and adjusting its size standards. |
| October 20 |
The
Court of Federal Claims granted the motion for summary
judgment by DIRECTV
Group, Inc. in another CAS 413 segment closing case
because "the undisputed evidence demonstrates
that the government received the value of DIRECTV’s CAS 413
segment closing obligation through a cost reduction from the
successor contractors. . . ." Thus, "the existence
of a government agreement in which the government protected
its interest in the pension asset surplus through a novation
agreement or other means is not material."
In its
pre-award protest, Camden
Shipping made all sort of ingenious arguments why its
offer remained open (or was revived) after the 60 day limit it
had checked on the offer form. The Court of Federal Claims did
not buy into any of those arguments and concluded that revival
would harm the competitive process. |
| October 19 |
I still
learn something every day (thank goodness). In The
Centech Group, the SBA's Office of Hearings and Appeals
dismissed a contractor's NAICS protest because the agency that
issued the solicitation, the FAA, is not subject to the Small
Business Act. |
| October 18 |
Two Court
of Federal Claims post-award bid protest decisions discuss, inter
alia, the standards for permitting supplementation of the
administrative record after the Court of Appeals for the
Federal Circuit's decision in Axiom
(discussed in the May 6 entry below): Kerr Contractors and Bannum. In Kerr,
the protester lost even though the court found several errors
in the solicitation process because it concluded they were
"de minimis."
The
Federal Accounting Standards Advisory Board has issued
Statement of Federal Financial Accounting Standard 35,
Estimating the Historical Cost of General Property, Plant, and
Equipment—Amending Statements of Federal Financial
Accounting Standards 6 and 23. The standard is available here.
The DoD is
amending the DFARS to remove
obsolete text addressing a restriction on awards to
foreign entities for DoD research and development, which had
implemented a statutory provision that is no longer in effect. |
| October 17 |
The Postal
Service Board of Contract Appeals (PSBCA) has caught itself up
by issuing a bunch of
decisions covering the period January through September
2009. The two most interesting decisions are: (i) Park
Ridge South Holland Partnership, in which the PSBCA
repeatedly chastised both parties for failing to give it
enough evidence to decide the case and then went ahead and
decided it anyway; and (ii) Webco
Transportation, in which the Board upheld a default
termination on a basis (violation of the Service Contract Act)
of which the Contracting Officer was completely unaware when
he terminated the contract. |
| October 16 |
The GAO
has belatedly issued another decision (originally dated March
25), sustaining the protest of The S.
M. Stoller Corp. because the agency allowed the winning
offeror to propose an approach that did not strictly comply
with the PWS requirements, without alerting other offerors
that such alternative approaches might be considered. |
| October 14 |
FAC
2005-37 has been published and includes the following
seven items (plus technical amendments):
Item I (FAR
Case 2008-035), an interim rule entitled "Registry of
Disaster Response Contractors," implements Section 697 of the
Department of Homeland Security Appropriations Act, 2007 (6
U.S.C. 796), which requires (i) FEMA to establish and maintain
a registry of contractors, who are willing to perform debris
removal, distribution of supplies, reconstruction, and other
disaster or emergency relief activities; and (ii) contracting
officers to consult the Registry during market research and
acquisition planning.
Item II (FAR
Case 2007-008), a final rule entitled "Limiting
Length of Noncompetitive Contracts in Urgent and Compelling
Urgency Circumstances," implements section 862 of the Duncan Hunter
National Defense Authorization Act for Fiscal Year 2009 (Pub.
L. 110–417) (hereinafter the "2009 NDAA") and the
OFPP Administrator’s memorandum of May 31, 2007, by limiting
the length of contracts awarded noncompetitively under unusual
and compelling urgency circumstances to the minimum contract
period necessary to meet the requirements, and no longer than
one year, unless the head of the agency determines that
exceptional circumstances apply.
Item III (FAR
Case 2008-026), a final rule entitled "GAO Access to
Contractor Employees," implements section 871 of the 2009 NDAA,
which allows the GAO to interview current contractor employees
during the audit of the contractor’s records.
Item IV (FAR
Case 2008-034), an interim rule entitled "Use of
Commercial Services Item Authority," implements section 868 of the 2009
NDAA, which provides that purchases of commercial services
that are not offered and sold competitively in substantial
quantities in the commercial marketplace may only be
considered commercial items for the purposes of the FAR if the
contracting officer determines in writing that the offeror has
submitted sufficient information to evaluate, through price
analysis, the reasonableness of the price of such services.
Item V (FAR
Case 2008-031), an interim rule entitled "Limitations
on Pass Through Charges," implements, inter alia, section 866
of the 2009 NDAA to minimize excessive pass-through charges by
contractors from subcontractors, or of tiers of
subcontractors, that add no or negligible value, and to ensure
that neither a contractor nor a subcontractor receives
indirect costs or profit/fee (i.e., pass-through
charges) on work performed by a lower-tier subcontractor to
which the higher-tier contractor or subcontractor adds no, or
negligible, value.
Item VI (FAR
Case 2008-008), an interim rule entitled "Award Fee
Language Revision," implements section 814 of the John
Warner National Defense Authorization Act for Fiscal Year
2007, section 867 of the 2009 NDAA, and the OFPP guidance
memorandum dated December 4, 2007, entitled "Appropriate
Use of Incentive Contracts," and makes an extensive set
of FAR revisions to improve agency decision-making procedures
when using award-fee contracts.
Item VII (FAR
Case 2009-003), a final rule entitled "National
Response Framework," amends the FAR to reflect (i) the January 22,
2008, re-issuance of the FEMA National Response Plan as the
National Response Framework and (ii) the elimination of the
term ‘‘Incident of National Significance.’’
A couple
of new ASBCA decisions
have been issued, the more interesting of which is Yardney
Technical Services, which involves the standards for
rejection under the "Inspection" clause and the
principle that the performance of a pre-existing duty is not
sufficient consideration for a purported change. |
| October 8 |
In Martin
Byrd Quillen, Sr., the Court of Federal Claims discussed
the meaning and calculation of the 12-month CDA time limit for
appealing Contracting Officer decisions to the court. |
| October 7 |
The ASBCA
has issued several new
decisions.
The Taylor
Consultants decision in the Court of Federal Claims is
impossible to summarize. I had to list it on both the bid protest and contract
disputes pages. Basically, after having originally won a
contract, the plaintiff had been disqualified because the SBA
found it to be other than small as a result of a size protest.
The plaintiff reacted by submitting a complicated, rapid-fire
salvo of letters and emails denoted as protests of the
subsequent award to another firm and contract claims for
possible wrongful termination of its contract. Basically, the
court found the plaintiff lacked standing on its protests and
stayed its contract actions (which alleged violations of the
Trade Secrets Act, the Procurement Integrity Act, and the
Contract Disputes Act) in order to allow the plaintiff the
opportunity to submit proper claims to the Contracting
Officer. It doesn't sound like things will get less
complicated anytime soon in this one. See also the
SBA's earlier Taylor Consultants decision, discussed in
the August 30 entry below.
The GSA is
amending Part 503 of its procurement regulation regarding "Improper
Business Practices and Personal Conflicts of Interest."
As a
result of one of those defeats you never forget, after 30
years, I still have a bad taste in my mouth over what I
believe is the Government's, ASBCA's, and court's bungling of
one case involving an assignment to a financial institution
under the Anti-Assignment statute. The HAM
Investments case brought back bad memories. In it, the
Court of Federal Claims held that the Government had not
waived the requirements of the Act and, therefore, was not
deemed to have approved an assignment even though the
Contracting Officer had actively assisted the contractor by
providing encouragement and guidance as to the proper forms
and regulations covering such transactions. |
| October 5 |
FAR Case
2008-027: The due date for comments on the proposed FAR
regulation concerning the Federal
Awardee Performance and Integrity Information System,
which would implement the requirements of section 872 of the
Duncan Hunter National Defense Authorization Act for Fiscal
Year 2009, has been extended to November 5. |
| September 30 |
In an
important decision, the Court of Appeals for the Federal
Circuit held that the CDA's six-year statute of limitations is
subject to the doctrine of equitable
tolling.
Okay, this
is getting downright eerie. The GAO has sustained another
protest! Has its charter been changed and I somehow missed it?
Is it under some sort of spell? In TMI Management Systems, the GAO found that an agency's
misclassification of a procurement in its announcement on the
FedBizOpps website was inconsistent with the requirement to
obtain full and open competition. |
| September 29 |
The SBA's
Office of Hearings and Appeals has issued three new size decisions. The
most interesting of the bunch is the Cox
Construction decision which specifically holds that, for
purposes of determining a firm's size, the SBA's regulations
control over any conflicting FAR regulations. In Cox, a firm
self-certified as small at the time it submitted its initial,
unpriced offer. Subsequently, the Contracting Officer did not
require offerors to re-certify at the time they submitted
priced offers. The OHA upheld the Area Office's determination
that the firm should, nevertheless, have re-certified at that
time and was other than small as of the later date, despite
contrary FAR regulations.
In yet
another successful protest, the GAO found in
OSC
Solutions,
that the cancellation of an RFQ and the issuance
of orders on a sole-source basis to a non-profit agency under
the authority of the Javits-Wagner-O'Day Act was improper
because the acquired items were not on the procurement list
maintained by the Committee for Purchase From People Who Are
Blind or Severely Disabled.
Minor
corrections have been published for FAR Parts 52 and 201. |
| September 28 |
In Alutiiq,
the SBA's Office of Hearings and Appeals reversed an Area
Office's determination that a firm had violated the ostensible
subcontractor rule because the Area Office's failure to notify
the protested firm of that issue and specifically to request
documents related to it constituted a lack of due process. |
| September 25 |
FAR
Case 2009-009: guidance has been published to assist
federal contractors who have contracts that are funded, in
whole or in part, by the American Recovery and Reinvestment
Act of 2009 and that include the FAR clause at 52.204–11,
in understanding the FederalReporting.gov
centralized reporting tool.
The GAO is
on a roll and has sustained another protest, this one by Caddell
Construction Co., because the agency had no basis to
conclude an offeror had met the past experience requirements
of the Security Act.
The CBCA
has issued a couple of new
decisions, one of which (over a strong dissent) dismissed
an appeal because it had been brought by only one member of
the joint
venture/contractor. |
| September 24 |
PAI
lost all three grounds its post-award protest at the Court of
Federal Claims concerning (i) the incumbents' alleged
organization conflicts of interest; (ii) the evaluation of
proposed subcontractors' experience; and (iii) the cost
realism evaluation.
The SBA's
Office of Hearings and Appeals has issued three new decisions: two
"VET" decisions regarding eligibility to participate
as a service-disabled veteran-owned small business concern,
and one "BDP" decision upholding the termination of
a firm from the 8(a) program because its owner falsely stated
on his application that he was not a federal employee at the
time of the application. |
| September 23 |
'Tis the
season for corrections. The FAR has been corrected to
reorganize the subparagraphs in FAR
52.219-9 (the "Small business Subcontracting
Plan" clause) and to reinstate subsection (d)(2)(iv) in
that clause. The DOE has corrected its section
909.405 of its acquisition regulation (concerning the
effect of suspension or debarment) by reinstating section (e).
The
President has determined the Economic
Community of Central African States and Maldives
are eligible to receive defense articles and services.
Unisys
lost its protest at the Court of Federal Claims in part
because the court found that a GSA solicitation for a blanket
purchase agreement under a Federal Supply Schedule contract
pursuant to FAR 8.405-2 did not include the FAR Part 15
requirement that, if discussions are held with one offeror,
they must be held with all. On another issue, the court
refused to conclude that when two offerors receive an equal
number of deficiencies, they must also receive the same
adjectival evaluation rating: "As the government
correctly observes, not all weaknesses are equal. Simply
tallying up the weaknesses accrued by Unisys and Lockheed and
finding that the number each accrued is the same does not
provide a basis for asserting that they should then have
achieved the same adjectival rating. This is all the more true
where, as here, the adjectival ratings being compared are for
two different factors." |
| September 22 |
The DoD has issued a couple of corrections
to Parts 205 and 247 of the DFARS.
In one new
Court
of Federal Claims decision, the plaintiff alleged that the
government had breached a mail delivery contract by agreeing
to its novation to another contractor. The Court of Federal
Claims held against the plaintiff because of a failure of
proof that (i) there was a valid contract between the
plaintiff and the Government at the time of the alleged
breach; (ii) (even assuming there was such a contract) the
Government breached any duties it owed plaintiff under the
contract; and (iii) (even assuming the first two requirements
had been met) plaintiff had proved its claimed damages. It was
this third element that elicited the court's most colorful
language: "These . . . points barely scratch the surface
in illustrating the extent to which [plaintiff's] testimony varied inconsistently over the course of
trial and ultimately was contradicted by other probative
evidence. Accordingly, if the court were required to determine
damages here – which it is not – it would find it
difficult to begin. Finally, in terms of assessing
credibility, the court simply cannot ignore [plaintiff's] past
history of making false statements. . . .Given the telltales
that permeate the record, the court thus totally discounts, as
incredible, plaintiff’s self-serving and entirely
uncorroborated testimony regarding damages. . . .The court
will not gild the lily, for this is not a close case." |
| September 21 |
Effective
within 15 days, the SBA is terminating a waiver of the Nonmanufacturer Rule
for radio
telephones based on the SBA’s recent discovery of a
small business manufacturer. Terminating this waiver will
require recipients of contracts set aside for small
businesses, service-disabled veteran-owned small businesses,
or Participants in the SBA’s 8(a) Business Development
Program to provide the products of small business
manufacturers or processors on such contracts. |
| September 17 |
Effective October 19, the GSA is revising Part
514 of the GSAR regarding Sealed
Bidding.
T-C
Transcription won its GAO protest because the VA
mis-evaluated its technical proposal in so many ways that the
GAO just cited some "examples" of the agency's
problems.
|
| September 16 |
Major
Contracting Services "won" its GAO protest, but
that didn't amount to much. The agency had decided to
recompete its requirements instead of exercising the full
original contract option because the contractor had been
determined not to be an SDVOSBC as it had represented when
bidding for the contract. Therefore, the Government announced
it was extending the original contract for only four months
pursuant to the "Option to Extend Services" clause
(FAR 52.217-9) while it conducted the recompetition. Major
Contracting Services protested that the Government should have
conducted a new solicitation even for that four-month
extension. In its decision, the GAO agreed because (i) the
four-month extension option had not been evaluated at the time
of the original procurement, (ii) the extension, therefore,
could only be justified under FAR Part 6 as a sole-source
extension, and (iii) the agency's delay in making a decision
to re-compete had created the urgency that it said justified
the extension. However, since the GAO's decision did not come
until two weeks before both the extension and the
recompetition will be complete, all the protester won was its
costs of pursuing the protest. My thought as a potential
protester might have been: I'm thinking about protesting a
four-month extension and it will require the GAO four months
to issue a decision, so is protesting worth the effort? |
| September 15 |
The EPA
has issued revisions to the EPAAR to bring its government
property requirements in line with FAR Part 45.
In Raytheon
, the Court of Appeals for the Federal Circuit reversed the
ASBCA's decision on summary judgment that Raytheon's potential
violation of CAS 413 had not caused the Government to pay
increased costs and, therefore, that Raytheon was not liable
for interest. |
| September 14 |
The SBA
has issued an interim rule adjusting various acquisition-related
dollar thresholds to account for inflation. |
| September 11 |
Consistent
with section 202(d) of the National Emergencies Act, 50 U.S.C.
1622(d), the President is continuing for one year the national
emergency declared on September 14, 2001, in Proclamation 7463,
with respect to the terrorist attacks of September 11, 2001,
and the continuing and immediate threat of further attacks on
the United States.
In
accordance with the Small Business Paperwork Relief Act of
2002 (44 U.S.C. 3520), OMB is publishing lists
of (i) the compliance assistance resources available to small
businesses and (ii) the points of contacts in agencies to act
as a liaison between the agency and small business concerns
with respect to the collection of information and the control
of paperwork. |
| September 10 |
L-3
Services won its GAO protest because the Air Force
improperly concluded the awardee had neither "biased
ground rules" nor "unequal access to
information" organizational conflicts of interest. |
| September 9 |
The SBA
has issued several corrections to the small business size
regulations it originally published May 21, 2004,
including a reference to an incorrect NAICS code. |
| September 8 |
Several
new ASBCA
decisions have been published. One of them, Gosselin
World Wide Moving, used the contract's Order of Precedence
clause to resolve an inconsistency between two contract
provisions. |
| September 3 |
FAR
Case 2008-027 is a proposed rule to amend the FAR to
implement Section 872 of the Duncan Hunter National Defense
Authorization Act for Fiscal Year 2009, which requires (i) the
GSA to establish and maintain a data system containing
specific information on the integrity and performance of
covered federal agency contractors and grantees and (ii)
awarding officials to review the data system and consider
other past performance information when making any past
performance evaluation or responsibility determination. The
new data system will be called the Federal Awardee Performance and
Integrity Information System (FAPIIS). Comments are due by
October 5.
In the Salt
River Pima-Maricopa Indian Community case, the CBCA
dismissed an appeal for lack of CDA jurisdiction (under the
"election doctrine") because the identical case was
pending in the Court of Federal Claims. |
| September 2 |
Several SBA OHA
NAICS decisions have been published.
FAR Case
2008-016 is a proposed rule establishing procedures for
contracting officers to report data concerning default
terminations and defective cost or pricing data into the Past
Performance Information System (PPIRS). Comments are due
by November 2. |
| August 30 |
Several SBA OHA size decisions have
been published.
Reading
through them has led me to confess to (at least) one serious mental defect. I
cannot understand any sentence with one negative embedded in
another. My brain short circuits when I see it. I learned this
the hard way on the Law School Admissions Test almost 35 years
ago where one of the questions included such a construction,
and I wasted an inordinate amount of time staring at it before
giving up and moving on. Thus, I was perversely pleased to
read the new SBA OHA decision on the Taylor
Consultants protest and to find the OHA perplexed by the
following section in the SBA's protest regulations listing
which firms have standing to file a size protest, including:
"Any offeror whom the contracting officer has not eliminated for reasons unrelated to size." 13
C.F.R. § 121.1001(a)(2)(i) [the coloring and italics are
mine] I cannot resist quoting the OHA's efforts to parse this
language:
[T]he
language . . . is cumbersome. The regulation employs negative
syntax to delineate its bounds and is dependent on two
successive alternatives: (1) whether a contracting officer has
eliminated an offeror from a procurement; and (2) whether
elimination was related or unrelated to size. The regulation
does not require an offeror to meet the first hurdle to
proceed to the second. Thus, a straightforward reading of the
regulation could rest solely on the second question of whether
an offeror’s disqualification was related to size. Thus,
reasonable men could conclude the language is ambiguous and I
find, depending on how it is read, the regulation could
connote different meanings. The purpose of 13 C.F.R. §
121.1001 is to give standing to businesses whose successful
protest would enable them to compete in the procurement. 67
Fed. Reg. 70,339, 70,345 (Nov. 22, 2002) (discussing proposed
amendment to 13 C.F.R. § 121.1001). The regulation denies
protest standing to offerors who have been eliminated for
reasons unrelated to size since they would be unable to
compete for award even if their protest was successful.
Conversely, the regulation enables firms eliminated based on
size to file size protests since they would be eligible to
compete if the protest is successful and the contracting
officer resolicits the procurement on an unrestricted basis.
Accordingly, a reasonable reading of the regulation allows
businesses who have been eliminated due to size to file a
protest. If the offeror was disqualified for reasons related
to size, the protest may proceed; where if an offeror is
eliminated for reasons unrelated to size, they have no
standing to file a size protest. Despite the text of 13 C.F.R.
§ 121.1001(a)(2)(i), the right of other than small businesses
to file a size protest is still limited by 13 C.F.R. §
121.1001(a)(1)(iv), which states: "A concern found to be
other than small in connection with the procurement is not an
interested party unless there is only one remaining offeror
after the concern is found to be other than small."
I feel
your pain, judge. |
| August 28 |
Pursuant to the requirements of
Executive Order 13502, effective September 28 HUD is removing
a regulation that prohibits the use of project
labor agreements on federal construction projects.
Northrop
Grumman Information Technology won its GAO protest, in
part because the agency failed to discriminate among proposals
even though the solicitation stated that they would be
evaluated on "the extent to which" they exceeded a
solicitation requirement. |
| August 27 |
Four ASBCA decisions have been
published. |
| August 25 |
FAR
Case 2009-009: registration at federalreporting.gov is
now available for contractors required to register by FAR
52.204-11 pursuant to the American Recovery and Reinvestment
Act.
With the
publication of Bulletin
10-01, the GSA has revised the per
diem rates for use in the continental United States for
fiscal 2010.
The Court
of Appeals for the Federal Circuit reversed the Court of
Federal Claims decision enjoining the Government in a bid
protest case because the protester (Labatt
Food Service) lacked standing to protest. The facts
are somewhat complicated, but, basically, the Court of Federal
Claims had found Labatt had standing because the Government
had allowed all the competitors to submit offers by an
unauthorized method (email). The Federal Circuit holds that
non-prejudicial errors in a bid process do not automatically
invalidate a procurement: "Labatt tautologically argues
that it was harmed by the method of transmission error because
it would have a substantial chance of receiving the contract
award in a rebid. By conflating the standing requirements of
prejudicial error and economic interest, Labatt would create a
rule that, to an unsuccessful but economically interested
offeror in a bid protest, any error is harmful. Under this
radical formulation there would be no such thing as an error
non-prejudicial to an economically interested offeror in a bid
contest. We decline to adopt such a rule." Or, as
the court says a bit more succinctly later in the decision:
"All errors are not equal" (and Labatt had been
eliminated from the procurement for submitting a late bid, not
for submitting a bid by email). |
| August 24 |
The
comment period for the proposed FAR rule concerning the use
of Project
Labor Agreements on federal construction projects has been
extended to September 23. |
| August 21 |
Two new
Court of Federal Claims decisions on contract disputes have
been published. In Kenney
Orthopedic, the court held that the contractor's breach
claim appeal was not untimely because it was based on
different facts from an unappealed default termination. KI
Liquidation involved cross motions for summary judgment
(both of which were denied) on issues concerning a bankruptcy
trustee's liability under the False Claims and forfeiture
statutes.
After a
very long dry spell, the SBA's OHA finally has published some
new NAICS and VET decisions.
In Command
Languages, the OHA upheld a finding that a
service-disabled vet controlled a company's operations even
though he lived 900 miles from the company's headquarters:
"(1) corporate location within the United States; and (2)
the location of the service-disabled veteran within the United
States are irrelevant to the issue of control when a concern
performs the majority of its contracts overseas. Instead, the
key, under 13 C.F.R. § 125.10, is whether the Record
establishes the service-disabled veteran actually controls the
SDVO concern. In the instant case the Record confirms [the
SDV] built [the company] to its current level of success and
that he controls its operations through his hard work, nearly
incessant travel, and use of modern electronic
communications."
Today, the
Office of Legal Counsel (OLC) of the Department of Justice
issued a memorandum
that (i) disagreed
with the GAO’s analysis in the Mission Critical Solutions
and International Program Group Protests, (ii) concluded that
the SBA’s interpretation is a permissible construction of
the relevant statutes, and (iii) stated that the OLC Opinion
is--and GAO’s decisions are not--binding on the executive
branch. |
| August 20 |
As
required by the National Defense Authorization Act for Fiscal
2008, the Air Force announced it will publish (within 30 days)
the inventory of its service
contracts.
A proposed
rule (FAR Case 2008-020) would amend the FAR to change the
procedures for close
out of contract files. Comments are due by October 19. |
| August 17 |
The
Department of Homeland Security has issued an interim rule
amending Parts 3025 and 3052 of its acquisition regulations
(HSAR) to reflect restrictions in the American Recovery and
Reinvestment Act on the purchase of certain foreign
textile products (HSAR Case 2009-004). To be considered in
connection with the final rule, comments must be submitted by
September 16. |
| August 14 |
Export
control regulations: in a notice issued yesterday,
President Obama continued for one year Executive Order 13222,
which declared a national emergency with respect to the
unusual and extraordinary threat to the national security,
foreign policy, and economy of the United States in light of
the expiration of the Export Administration Act of 1979, as amended (50 U.S.C. App. 2401 et seq.).
Effective
September 14, the GSA is amending the GSAR by adding a Part
519.70 to establish a mentor-protege
program (i) to
encourage GSA prime contractors to assist small businesses,
including veteran-owned small businesses, service-disabled
veteran-owned small businesses, HUBZone, small disadvantaged
businesses, and women-owned small businesses, in enhancing
their capabilities to perform contracts and subcontracts for
GSA and other Federal agencies; (ii) to increase the base of
small businesses eligible to perform GSA contracts and
subcontracts; and (iii) to foster long-term business
relationships between GSA prime contractors and small business
entities and to increase the overall number of small business
entities that receive GSA contracts, and subcontract awards. |
| August 11 |
The Court
of Appeals for the Federal Circuit reversed Weeks
Marine's Court of Federal Claims bid protest victory
because the Fed Circuit (i) found the agency had a rational
basis for its procurement plan to utilize an ID/IQ contract
and (ii) refused to second-guess the agency's rationale. Just
as interesting as the ultimate holding, however, is the
court's discussion of the appropriate test for a protester's
standing in a pre-award protest. The court settles on
the following standard (after considering several
alternatives): "standing is established by alleging 'a
non-trivial competitive injury which can be redressed by
judicial relief.'"
It was not
a good day for protesters in federal court. NEQ
lost its protest at the Court of Federal Claims, which
described its arguments as "overblown" and not in
accordance with the facts. The court also scoffed at the
protester's position that it need not meet the tests for
injunctive relief because it was only seeking a reevaluation.
Federal
Acquisition Circular (FAC) 2005-36 has been published. It
includes the following six items (plus technical amendments):
Item I
(FAR Case 2008-038), a final rule entitled "Federal
Technical Data Solution (FedTeDS)" retires that
system, removes all references to it from the FAR and
substitutes references to the Governmentwide Point of Entry
(GPE) system.
Item II
(FAR Case 2007-021), a final rule entitled "Fair
Labor Standards Act and Service Contract Act Price Adjustment
Clauses" specifically requires the inclusion of FAR
52.222-43 and 52.222-44 in time-and-materials and labor-hour service
contracts that are subject to the Service Contract Act.
Item III
(FAR Case 2009-014), an interim rule entitled "New
Designated Country--Taiwan" implements the designation of Taiwan under the
World Trade Organization Agreement on Government Procurement
(which took effect on July 15, 2009) and allows contracting
officers to purchase goods and services made in Taiwan without
application of the Buy American Act if the acquisition is
covered by the World Trade Organization Agreement on
Government Procurement.
Item IV
(FAR Case 2008-004), a final rule entitled "Prohibition
on Restrictions on Business Operations in Sudan and Imports
from Burma" implements
Section 6 of the Sudan Accountability and Divestment Act of
2007, which requires certification in each contract entered
into by an executive agency that the contractor does not
conduct certain business operations in Sudan. In addition, in
accordance with Executive Orders 13310 and 13448, Burma is
added to the list of countries from which most imports are
prohibited.
Item V
(FAR Case 2006-013), a final rule entitled "List
of Approved Attorneys, Abstractors, and Title Companies"
updates the
procedures for the acceptance of a bond with a security
interest in real property because the DOJ has discontinued
maintenance of its former list of approved abstractors,
attorneys, and title companies.
Item VI
(FAR Case 2007-002), a final rule entitled "Cost
Accounting Standards (CAS) Administration and Associated FAR
Clauses" converts (without change) the interim rule
that revised FAR
30.201–4(b)(1) and FAR 52.230–1 through 52.230–5 to
maintain consistency between the FAR and CAS regarding the
administration of the CAS Board’s rules, regulations and
standards. |
| August 10 |
The DoD's
Per Diem, Travel and Transportation Allowance Committee has
published Civilian Personnel Per Diem Bulletin Number 265,
which lists revisions in the per
diem rates prescribed for U.S. Government employees for
official travel in Alaska, Hawaii, Puerto Rico, the Northern
Mariana Islands and U.S. Possessions.
Although
the Court of Appeals for the Federal Circuit's holding in Vantage
Associates is nonprecedential, the following language is
interesting: "[I]f the government had not cancelled the
purchase order, Vantage would not have furnished the cases in
accordance with the terms of the contract. Vantage argues,
nevertheless, that the government prematurely cancelled its
purchase order at 3:27 a.m. on August 18, 2006—hours before
the purchase order would have lapsed by its own terms. In
other words, despite its inability to perform, Vantage
contends it can recover all of its costs because, just before
the delivery deadline that it admits it would not have met, it
received notice of the purchase order’s cancellation. We do
not think that, under these circumstances, Vantage is entitled
to damages for the costs it incurred in preparation to deliver
the cases." |
| August 7 |
FAR Case 2009-013, entitled
"Nonavailable Articles," is a proposal to revise the
list of nonavailable
articles at FAR § 25.104(a) to which the Buy America Act
restrictions do not apply. Comments are due by October 6.
The GSA (GSAR Case
2008-0501) is revising Part 502 of the GSAR concerning definitions
of words and terms. |
| August 6 |
An
extensive set of proposed revisions and clarifications to
various FAR government
property provisions has been published (FAR Case
2008-011). Comments are due by October 5.
The State
Department is amending the ITAR to add an exemption for the
temporary export of body
armor for exclusive personal use to destinations not
subject to restrictions under the ITAR § 126.1 and to
Afghanistan and Iraq under specified conditions.
Three
interesting ASBCA decisions have been published. FitNet
survived a government motion to dismiss its appeal of a
default termination as untimely because "the contracting
officer’s [subsequent] decision on the merits of [a] claim,
rather than summarily denying it on the basis of his prior
termination decision, was in effect a reconsideration of the
termination whether he consciously intended that effect or
not."
The
Government fared better in the other two decisions--winning
summary judgments (i) upholding the default termination of a concession
contract and (ii) dismissing certain "Changes"
claims because the COR did not have the authority to order
changes and because nobody with authority ratified those
changes. |
| August 5 |
The Court
of Federal Claims held that Wonderlyn
Lorraine Bell Pinckney's Postal Services contract should
not have been terminated for default because the Government
did not prove that the contractor had returned from the
postal route one day with deliverable but undelivered mail.
Unlike Keeter
Trading, however, the contractor did not establish a bad
faith termination. The decision is a highly fact-specific
(often fascinating) examination of the credibility of various
witnesses as to the conditions along the mail route, e.g.:
"Plaintiff
testified that one resident on Brown Pelican Loop has some kind
of an attack dog, but that resident informed plaintiff that
she could blow her horn and he would come out and get the
mail."
The Coast
Guard convinced the Court of Federal Claims to dilute the
language in its original decision a bit in the Global
Computer Enterprises protest (see July 30 entry
below), from requiring the Government to recompete a protested
procurement using "fair and open competition," to
the following: "The
Coast Guard must procure these services in accordance with the
law and in a manner that preserves the integrity of the
procurement process, exercising its discretion in a reasonable
manner."
Belatedly,
I noticed an April decision by the GAO's Contract Appeals
Board. In Inventory Discount
Printers, that board held that it lacked jurisdiction over
a contractor's appeal because the contractor's vague assertion
to the contracting officer was not sufficient to put him on
notice of the claim the contractor eventually asserted on
appeal. |
| August 4 |
The SBA is
proposing to terminate the nonmanufacturer waiver for radio
telephones. Comments are due by August 19. The SBA is also
proposing to eliminate the class waiver under PSC 9130 for Liquid
Propellants--Petroleum Base. Comments are due by August
21. |
| August 3 |
The State
Department has amended the ITAR regarding Congressional
certification for South Korea, which is now in the same
category as the countries in NATO, Japan, Australia, and New
Zealand requiring certification to Congress prior to granting
any license for export of major defense equipment sold under a
contract in the amount of $25,000,000 or more, or for defense
articles or defense services sold under a contract in the
amount of $100,000,000 or more. |
| July 31 |
There are
several new CBCA decisions
out. The most interesting of the bunch is EBS/PPG
Contracting. In that case, the Government kept requiring
the contractor to re-submit (and provide more information for)
its termination settlement proposals. Finally fed up, the
contractor sent a letter stating it expected a contracting
officer's decision on its prior proposals by a date certain
and would treat a failure to decide by that date as a denial.
The Board held this letter was sufficient to turn the prior
submissions into a claim. However, the contractor subsequently
acquiesced in the contracting officer's request to submit
still more information in a revised format, and the Board
found the latter submission was again not a CDA claim,
dismissing the subsequent appeal for lack of CDA jurisdiction.
The Board wrote as follows: "It is apparent that in its effort
to get some sort of action from the BOP on any of its
settlement proposals EBS became caught up in the nuances
associated with CDA jurisdictional practice. Nevertheless, we
find that by the time EBS was finished resubmitting and
withdrawing its settlement proposals, it had neither a
proposal nor a claim before the contracting officer."
Thirty years into the CDA's existence, contractors are still
being trapped by the "nuances associated with CDA
jurisdictional practice." I would phrase it this
way: thirty years in, there are still some kinks to work out
of the statute. |
| July 30 |
Global
Computer Enterprises won its protest because the Court of
Federal Claims determined that work added by the Government to
a contract was outside its scope and should have been
competed. The interesting thing about the decision, however,
is the court's finding that the Coast Guard repeatedly
overstated the harm it would suffer if it were required to
compete rather than proceed as it wished. Often, the court is
much more deferential to an agency's avowals of the dire
consequences of an injunction, regardless how overwrought such
predictions may be.
In a
decision originally made in September 2008, but just now
published, the GAO sustained the protest of Radiation
Oncology Group because the agency permitted the awardee to
submit proposal revisions after the deadline for receipt of
proposals and failed to document the bases for its evaluation. |
| July 29 |
Busy, busy
day--
Global
Computer Enterprises succeeded in its efforts to
supplement the record extensively in its bid protest at the
Court of Federal Claims over objections that its submissions
contained impermissible lay opinions and hearsay (e.g.,
non-agency RFP summaries and material from various web pages).
Todd
Construction concerns the scope of, and limits on, (i) the
Court of Federal Claims' power to remand a case to the agency
with "proper and just" directions for further
consideration of the agency's faulty performance
evaluation of a contractor and (ii) the types of relief a
contractor may request of the court in such a situation. The
court's discussion of the history of its remand power is
fascinating, and I recommend you take a few minutes out of
your busy days to read this one.
OK's
Cascade tried to enforce relatively favorable decisions it
had obtained from the Contracting Officer on uncertified
claims exceeding $100,000. The court found the Contracting
Officer's decisions bound neither the agency nor the court in
these circumstances.
A bunch of
DFARS amendments have been published--
DFARS Case
2008-D035, entitled "Peer
Reviews of Contracts," is a final rule that adds, inter
alia, a DFARS section 201.170 ("Peer Reviews"),
which (i) specifies that the Office of the Director, Defense
Procurement and Acquisition Policy, will organize teams of
reviewers and will facilitate Peer Reviews for all
solicitations valued at $1 billion or more and for all
contracts for services valued at $1 billion or more and (ii)
requires the military departments, defense agencies, and DoD
field activities to establish procedures for pre-award Peer
Review of solicitations valued at less than $1 billion, and
postaward Peer Review of contracts for services valued at less
than $1 billion.
DFARS Case
2008-D003, entitled "Restriction
on Acquisition of Specialty Metals," is a final rule
that implements Section 842 of the National Defense
Authorization Act for Fiscal Year 2007 and Sections 804 and
884 of the National Defense Authorization Act for Fiscal Year
2008 by addressing restrictions on the acquisition of
specialty metals not melted or produced in the United States.
DFARS
Case 2008-D010, entitled "Clarification
of Central Contractor Registration and Procurement Instrument
Identification Data Requirements," is a final rule
addressing requirements for ensuring the accuracy of
contractor information in the CCR database and in contract
documents and clarifying the requirements for proper
assignment of procurement instrument identification numbers.
DFARS Case
2007-D006, entitled "Contract
Reporting," is a final rule that updates DFARS text
addressing reporting of contract actions to remove references
to obsolete reporting form DD 350 and to address current DoD
procedures for reporting of contract actions in the Federal
Procurement Data System ("FPDS").
DFARS Case
2007-D020, entitled "Government
Property," is a final rule that extensively updates
text throughout the DFARS addressing the management of
government property in the possession of contractors. The updates are consistent with changes made to the FAR.
DFARS Case
2007-D008, entitled "Protection
of Human Subjects in Research Projects," is a
final rule that adds DFARS policy (i) addressing requirements
for the ethical treatment of human subjects involved in
research projects, (ii) adding a clause for use in contracts
involving human subjects in research, and (iii) informing
contractors of their responsibilities for compliance with 32
CFR Part 219; DoD Directive 3216.02; applicable DoD component
policies; 10 U.S.C. 980; and, when applicable, FDA policies
and regulations.
DFARS Case
2008-D029, entitled "Requirements
Applicable to Undefinitized Contract Actions," is a
final rule that (i) requires DoD departments and agencies to
submit semi-annual reports regarding undefinitized contract
actions exceeding $5 million and (ii) establishes requirements
for (a) obligation of funds for the undefinitized period
consistent with the contractor’s proposal for that period
and (b) compliance with existing DFARS policy relating to
profit computation for undefinitized contract actions.
DFARS Case
2008-D046, entitled "Trade
Agreements--Costa Rica and Peru," is an interim
rule that amends trade agreement provisions and clauses in
DFARS Part 252 to implement the Dominican Republic-Central
America-United States Free Trade Agreement with respect to
Costa Rica, and the United States-Peru Trade Promotion
Agreement, which were approved by Congress in the Dominican
Republic-Central America-United States Free Trade Agreement
Implementation Act (Pub. L. 109–53) and the United
States-Peru Trade Promotion Agreement Implementation Act (Pub.
L. 110–138) (19 U.S.C. 3805 note). Comments are due by
September 28.
DFARS Case
2008-D040, entitled "Motor
Carrier Fuel Surcharge," is an interim rule to
implement Section 884 of the National Defense Authorization
Act for Fiscal Year 2009, which requires the DoD to ensure
that fuel-related adjustments in contracts for carriage are
passed through to the person bearing the cost of the fuel to
which the adjustment relates. Comments are due by September
28. |
| July 28 |
Effective
August 12, the EPA is amending its acquisition regulation (the
EPAAR) to revise the prescription for and the content of the "Technical
Direction" clause by adding and defining two terms:
(i) contracting officer technical representative and (ii) task
order.
The ASBCA
published six new
decisions. After reviewing an extensive and complex motion
for reconsideration by SUFI,
the Board more than doubled the quantum of its recovery in its
original
decision and granted its request for claim preparation
costs and consulting fees, although not at the rate the
contractor desired. There was a split decision in the American
Renovation and Construction appeals. One default
termination was upheld because, even though the Contracting
Officer received "marching orders" from the
customers to terminate, she showed great patience with the
contractor and exercised careful discretion in finally doing
so. A related termination was overturned because the
Government waited more than a reasonable time after final
acceptance to rescind that acceptance. |
| July 25 |
In LAI
Services (LABAT-Anderson
below), a decision involving several issues of contract
interpretation, the Court of Appeals for the Federal Circuit
reversed the ASBCA and held that a contractor performing
materiel distribution services should be compensated for
"minimum military packing" of off-base
transshipments under CLIN 002 rather than CLIN 001 of the
contract. In the interests of judicial economy, the court also
determined the appropriate method of billing under CLIN 002
(per-package versus the per-item payment claimed by the
contractor), an issue not addressed by the Board. |
| July 23 |
Red
River Holdings won its post-award protest at the Court of
Federal Claims because of a defective evaluation, but the
winner got to retain the contract for the base period because
of national security needs, so Red River received both partial
equitable relief and the right to recover its proposal costs.
The court spent quite a bit of space analyzing whether it had
jurisdiction because the contract was a maritime contract
which raised the issue whether even the protest should be
under the exclusive admiralty jurisdiction of a federal
district court.
Public
Communications Services won its GAO protest against a
flawed evaluation that did not treat offerors equally. |
| July 22 |
Effective
August 21, the Department of Energy is issuing an extensive
set of technical
amendments and corrections to its acquisition regulations
(the DEAR).
Effective
today, the SBA has issued an interim final rule
implementing provisions of the American Recovery and
Reinvestment Act that pertain to the Surety
Bond Guaranty (SBG) Program. Specifically, until September
30, 2010, the SBA is authorized (i) to guarantee bonds on
contracts of up to $5,000,000 (or up to $10 million based upon
the certification of a federal contracting officer) and (ii)
to partially deny liability under its bond guarantee (but not
on the basis of material facts disclosed to SBA in a guarantee
application submitted under the Prior Approval Program). The
rule also revises the size standard for participation in the
SBG Program.
The GAO
sustained another protest regarding an OMB
Circular A-76 procurement because the agency failed to
reasonably consider whether agency tender's material and
supply costs were realistic. |
| July 21 |
In Canal
66 Partnership, the Court of Federal Claims denied motions
for summary judgment because it found both parties'
interpretations of an ambiguous contract reasonable and
concluded that extrinsic evidence will have to be examined to
resolves the issue.
The DFARS (section
212.207(b)) has been corrected by adding the words "commercial
item" in two places to clarify the particular
definition to which that section is referring in specifying
the types of services to which the rule applies.
Effective August 20, the
GSA is amending the FTR to update the list of travel
purpose identifiers and incorporate new descriptive
language for each identifier to enhance how travel costs are
identified by Federal agencies. |
| July 17 |
The DoD
has issued an interim final rule adding a Part 159 to 32
C.F.R. entitled "Private
Security Contractors Operating in Contingency
Operations," which "establishes policy, assigns
responsibilities and provides procedures for the regulation of
the selection, accountability, training, equipping, and
conduct of personnel performing private security functions
under a covered contract. It also assigns responsibilities and
establishes procedures for incident reporting, use of and
accountability for equipment, rules for the use of force, and
a process for administrative action or the removal, as
appropriate, of" private security contractors and their
personnel.
The GAO
sustained a protest by the agency's tender
official in an OMB Circular A-76 procurement. |
| July 15 |
In
response to the SBA's request for reconsideration, on July 6,
the GAO reaffirmed
its decision in the Mission Critical Solutions protest that
HUBZone program set-asides are mandatory when the statutory
conditions are met. (The original decision is discussed at the
May 7 entry below). However, on July 10, the OMB issued a Memorandum
(M09-23) directing all executive agencies to disregard the
GAO's position in both the Mission Critical Solutions and
International Program Group protests while the matter was
under legal review.
Several
DFARS regulations have been issued--
DFARS
Case 2008-D011 is an interim rule amending the DFARS to
implement Sections 805 and 815 of the National Defense
Authorization Act for Fiscal Year 2008. It lists the
conditions under which (i) a time-and-materials or labor hour
contract may be used for the acquisition of commercial items
and (ii) major weapon systems and subsystems may be treated as
commercial items.
DFARS
Case 2006-D013 is a final rule implementing statutory provisions
relating to the leasing of vessels, aircraft, and combat
vehicles. It applies to long-term leases and charters and to
contracts with a substantial termination liability.
DFARS
Case 2006-D051 is an
interim rule implementing Section 802 of the National
Defense Authorization Act for Fiscal Year 2008, which places
limitations on the award of new contracts for lead system
integrator functions in the acquisition of major DoD systems.
DFARS
Case 2008-D044 is a final rule implementing Section 803 of
the National Defense Authorization Act for Fiscal Year 2009,
which requires the DoD to identify and evaluate, at all stages
of the acquisition process, opportunities for the use of
commercial computer software and other nondevelopmental
software.
DFARS
Case 2008-D005 is an interim rule implementing Section 801
of the National Defense Authorization Act for Fiscal Year
2008, which requires internal controls for procurements made
by non-DoD agencies on behalf of DoD.
The DoD (DFARS
Case 2007-D011) is also proposing revisions to the DFARS
to clarify requirements regarding definitization of letter
contracts and to specify that DoD letter contracts will be
definitized using the DFARS procedures applicable to all other
undefinitized contractual actions. Comments are due by
September 14.
In its
latest Ashbritt
protest decision, the Court of Federal Claims clarified its
use of the term "reprocure" in its original decision
(see July 1 entry below) granting the protest and
ordering the agency to reprocure certain items. The court
stated as follows: "The Court used the word 'reprocure'
in its broadest sense to permit Defendant to effect a remedy
of the procurement errors at any stage in the reopened
procurement process that the agency deems appropriate.
Defendant has asked whether the Corps could reopen discussions
and evaluate revised proposals or whether it must issue a new
solicitation. Reopening discussions and proceeding from that
point in the reprocurement effort will comply with the Court’s
order, so long as the agency corrects the errors identified in
the opinion. As this Court emphasized, the agency has
discretion in taking corrective action, and 'it is not for
this Court to dictate the particulars of each step the agency
should take to remedy what transpired.' " |
| July 14 |
FAC
2005-35 has been published. It includes one item, FAR
Case 2009-015, entitled "Revocation of Executive
Order 13202." The item removes all references in the FAR
to Executive Order 13202, which had prohibited the Government from
requiring or prohibiting the use of project labor agreements
by its construction contractors and subcontractors. Similarly, a proposed rule (FAR
Case 2009-005) would implement President Obama's Executive
Order 13502 by adding (i) a new FAR Subpart 22.5, Use of Project Labor
Agreements for Federal Construction Projects; (ii) a new
solicitation provision, entitled "Notice of Requirement
for Project Labor Agreement," to be included in
solicitations where the agency has exercised its discretion to
require a project labor agreement; and (iii) add a new
contract clause entitled "Project Labor Agreement."
Comments are due by August 13.
Effective
July 29, the SBA is waiving the nonmanufacturer
rule for 13 Watt CFLs, 26 Watt CFLs, and Occupancy Sensors
Dual Technology.
The SBA
has also published an interim final rule that implements
certain provisions of the American Recovery and Reinvestment
Act of 2009 affecting small
business investment companies (SBICs). These provisions
increase the maximum amount of SBA leverage available to an
SBIC, change the calculation of the maximum investment size
that an SBIC is permitted to make, and simplify the
requirement for an SBIC to devote a portion of its investment
activity to smaller enterprises.
L-3
Communications EOTech lost its protest at the Court of
Federal Claims because the agency's decision to eliminate the
protester from the competitive range (leaving only one
competitor in the competitive range) survived the
"close" scrutiny such an action entails. L-3 was
eliminated from further consideration primarily because its
bid samples were not satisfactory to the agency. |
| July 13 |
Although
I'm still working out the kinks, I have published the 2009
Procurement Review through today. Of course, I will
continue updating it through the end of the year. If you spot
typos, I would really appreciate it if you would email me and let
me know about them. |
| July 10 |
The GAO's
decision granting the protest of AINS,
Inc., is interesting because it goes into much more depth
and detail than the GAO normally is willing to undertake in
analyzing the protester's proposal and the agency's flawed
evaluation of it.
In Pixl,
Inc., the CBCA held that a contractor's request that the
Contracting Officer reconsider his decision made more than 90
days after the contractor had received that decision did not
toll or re-establish the 90-day period for appealing the
original decision, and, therefore, the Board dismissed the
contractor's subsequent appeal to the Board as untimely. |
| July 8 |
In Leader
Communications, the SBA's OHA held that amounts paid for
the New Mexico gross receipts tax and a GSA funding fee should
not be excluded in determining a firm's annual receipts. |
| July 7 |
Two Court
of Federal Claims decisions on contract disputes have been
published. In United
Surety & Indemnity Co., the court dismissed a surety's
complaint for failure to state a claim upon which relief could
be granted because the surety had not provided the Government
with proper notice of the contractor's default or imminent
default on its Miller Act bond and, therefore, the Government
did not owe a surety a duty under the doctrine of equitable
subrogation. In IMS
Engineers-Architects, the court held that a Government's
oral assurances during settlement negotiations under one
contract that it would order larger quantities under two other
contracts did not create rights under the latter two contracts
because they were ID/IQ contracts and the Government did order
the required minimums under each. The question of the
Government's good faith and fair dealing under the contract on
which the release was executed is still open, however.
The VA
announced it intends to deviate from the FAR 32.905 by adding
an interim clause to the VA Acquisition Regulation, which will
allow vendors to voluntarily submit invoices
electronically.
I consider
myself fairly internet savvy for an old man, but once in
awhile, something happens that makes me feel my age. The news
that the GAO is now on Twitter
is one such event.
The GAO
sustained Ashbury
International Group's protest because the agency
failed to test the awardee's submittal as it was supposed to
and failed to engage in meaningful discussions with the
protester. |
| July 2 |
The Prompt
Payment interest rate for the period from July 1 to
December 31 is 4 7/8 percent.
The ASBCA
has published four new
decisions, each of which involves application of the rules
of contract interpretation to various situations. |
| July 1 |
The DoD is
seeking comments (by July 31) concerning its upcoming revision
of the Commercial
Item Handbook.
Federal
Acquisition Circular (FAC) 2005-34 has been published. It
includes three items. Item I (FAR Case 2006-022), a final rule
effective today entitled "Contractor Performance
Information," implements the President's March 4
Memorandum on Government Contracting by promoting the use of a
standard performance information reporting system, the Past
Performance Information Retrieval System (PPIRS). Item II
(FAR Case 2008-009), an interim rule effective today entitled
"Prohibition on Contracting with Inverted Domestic
Corporations," implements Section 743 of Division D of
the Omnibus Appropriations Act, 2009 (Public Law 111–8),
which prohibits the award of contracts using appropriated
funds to any foreign incorporated entity that is treated as an
inverted
domestic corporation or to any subsidiary of one. An
inverted domestic corporation is one that used to be
incorporated in the United States, or used to be a partnership
in the United States, but now is incorporated in a foreign
country, or is a subsidiary whose parent corporation is
incorporated in a foreign country, the purpose being to avoid
United States taxes on business income generated in foreign
countries. Comments are due by August 29. Item III (FAR Case
2008-028), a final rule effective July 31 entitled "Role
of Interagency Commission on Debarment and Suspension"
implements Section 873(a)(1) and (2) of the National Defense
Authorization Act for Fiscal Year 2009. The rule clarifies the
role of the Interagency
Committee on Debarment and Suspension when more than one
agency has an interest in the debarment or suspension of a
contractor.
The GAO
sustained Carahsoft's
protest because the agency issued a delivery order in
response to a proposal that failed to meet one of the minimum
technical requirements of the solicitation's specification.
The Court
of Federal Claims awarded Ashbritt
a declaratory judgment and a permanent injunction on its
post-award protest because of serious errors by the agency in
the price evaluation and because the agency treated offerors
unequally during discussion by giving one offeror
significantly more information and opportunities to improve
its proposal. |
| June 29 |
Anyone
with even a rudimentary knowledge of the CDA and the doctrine
of sovereign immunity should have seen this one coming from a
mile away. Certainly, the ASBCA should have. In FloorPro,
the Court of Appeals for the Federal Circuit reversed the
ASBCA and held that a subcontractor claiming to be a third
party beneficiary of a bilateral modification between the
Government and the prime did not have CDA jurisdiction to
bring a claim directly against the Government based on an
alleged breach of that mod.
Sitco,
however, evinced an even more fundamental misunderstanding of
the CDA when it tried to file a complaint in the Court of
Federal Claims without first having submitted a written,
certified claim to the Contracting Officer. Needless to say,
that went over like a lead balloon.
Academy
Facilities Management lost its post-award bid protest at
the Court of Federal Claims, after the court requested an
advisory opinion from the GAO. The decision is notable not so
much for any particular holding on the various evaluation
errors the protester alleged, but for the fact that the judge
seems to cite every case under the sun for each step in his
analysis. If you ever want a starting point for analyzing the
standards applicable to a bid protest at the court, this would
be one good place to begin your education. |
| June 26 |
Over a
strong dissent, the Court of Appeals for the Federal Circuit
reversed parts of a Court of Federal Claims decision on Bell
BCI's cumulative impact delay claims because the appeals
court found that the language "attributable to this
modification" in a release unambiguously barred certain
claims.
Four new SBA OHA size decisions have
been published, three of which reverse a determination by an
SBA Area Office. In KVA
Electric, the OHA faulted the Area Office for relying on a
firm's self-serving post-offer statements contracting clear
evidence in the resumes submitted in its offer of excessive
reliance on a firm that the OHA found should have been
considered its affiliate under the ostensible subcontractor
rule. In Henderson
Group Unlimited, the OHA found a firm had rebutted a
presumption of affiliation by establishing a that a
"clear fracture" existed between two firms. Btw, I'm
not usually a fan of regulatory jargon, but "clear
fracture" appeals to me for some reason. |
| June 24 |
The SBA
published a comprehensive list of all the currently approved
class waivers from the nonmanufacturer
rule.
The GAO
sustained TFab
Manufacturing's protest against a solicitation's
requirements concerning the applicability of the
"Limitations on Subcontracting" clause. |
| June 23 |
The EPA is
proposing to amend various provisions in the EPAAR concerning government
property in order to consolidate the EPAAR physical
property clauses (Decontamination, Fabrication, and Government
Property), re-designate the prescription number in the data
clause, and update the roles and responsibilities of the
contractor, DCMA and CPC. Comments are due by July 23.
Five ASBCA decisions have been
published. In denying DMJM
H&N, Inc.'s claim, the Board wrote: "It is simply
unreasonable for appellant to declare at the project halfway
point, that it should be compensated for any changes not
'effortless.' " |
| June 17 |
A couple of new ASBCA decisions have been
published. |
| June 15 |
Federal
Acquisition Circular 2005-33 has been published. It
includes two items. Item I (FAR
Case 2008-036) is an interim rule, which allows
contracting officers to purchase the goods and services of
Costa Rica, Oman, and Peru without application of the Buy
American Act if the acquisition is subject to the applicable
trade agreements. Item II, entitled Contractor's
Request for Progress Payments (FAR Case 2005-032), is a
final rule that incorporates improvements related to requests
for progress payments and the Standard Form 1443, Contractor’s
Request for Progress Payments, used to request those progress
payments. |
| June 10 |
Rhinocorps
finally lost its protest at the Court of Federal Claims
because the agency had a rational basis for concluding, as a
result of a market analysis, that there were not two,
responsible small businesses available to justify setting
aside a procurement. Rhinocorps had argued that the market
analysis was a sham undertaking meant only to reinforce a
decision the Government already had made. The court concluded
as follows: "And, although the administrative record
reveals that the Air Force reluctantly performed the required
analysis under FAR 19.502-2(b), and only did so after
plaintiff forced the issue, the FAR does not require the Air
Force to negate evidence of a predisposition."
Systore
Companies proved the Government breached a license
agreement, but it was a hollow victory because the ASBCA also
found that Systore failed to prove its damage claim (for lost
profits). |
| June 8 |
Effective
June 23, the SBA is waiving the nonmanufacturer rule for PSC
9130--Liquid Propellants--Petroleum Base Manufacturing.
Also, the SBA is considering granting a waiver for 13 Watt Compact
Fluorescent Lamps (CFLs), 26 Watt CFLs, and Occupancy
Sensors Dual Technology. Comments are due by June 23.
Cochran
Lumber Co. lost its appeal at the CBCA concerning a timber
sales contract because the board rejected the contractor's
method of calculating the difference between the Government's
estimates and the actual amounts available. |
| June 5 |
The
applicability date for the employment
eligibility verification rules has been delayed yet again
to September 8.
The
Court of Federal Claims somewhat reluctantly dismissed Datapath's
protest, citing 28 U.S.C. § 1491(b)(3) for the
proposition that courts must "give due regard to the interests of
national defense and national security and the need for
expeditious resolution of the action." Datapath did,
however, recover certain costs associated with pursuing its
protest, in a somewhat unusual manner, as revealed in footnote
5 to the court's opinion: "Recognizing that the court has
authority to award bid preparation and proposal costs, in the
event DataPath prevailed in this protest, following oral
argument, L-3 Global, the incumbent contractor and primary
beneficiary of this contested Solicitation, agreed to the
court’s request to reimburse DataPath for certain costs
incurred to date. Since the issues raised by this bid protest
are complex and
were well presented by DataPath’s counsel, this
accommodation by L-3 Global is appropriate, as it serves the interest of an
'expeditious resolution of the action.' 28 U.S.C. §
1491(b)(3)." |
| June 4 |
Effective
July 6, the NSF is implementing final regulations covering the
Program
Fraud Civil Remedies Act. |
| June 3 |
The
Court of Appeals for the Federal Circuit upheld the Court of
Federal Claims' decision sustaining the default termination of
McDonnell Douglas and General Dynamics on the A-12
Avenger program.
Engineering
& Management Integration won its GAO protest because
the agency had rejected its proposal for failing to identify
(as required) the percentage of its proposed staffers
that were certified, when it had provided the number that were
certified. |
| June
1 |
Effective
today, the GSA (GSAR Case 2008-G514) is amending Part 546 of
the GSAR (Quality
Assurance).
|
| May
29 |
Effective June 29, the GSA will
remove Part 547 (Transportation)
from the GSAR.
Effective
today, NASA has amended its FAR Supp regulations concerning
its mentor-protege
program, inter alia, expand it to cover Veteran-owned,
HUBZone, and NASA Small Business Innovation Research (SBIR)
Phase II small businesses.
In General
Dynamics, C4 Systems, the ASBCA (by analogy to option
exercise case law) strictly construed the ordering clause
under an ID/IQ contract and held that delivery orders issued
by email (when the contract did not permit such means of
delivery) were changes entitling the contractor to an
equitable adjustment.
|
| May
28 |
Effective today, the GSA has
rewritten GSAR Part 513 re Simplified
Acquisition Procedures.
There are three new SBA OHA 8(a) business development
program decisions out.
American
K-9 Detection Services won its GAO protest because, in
taking corrective action in response to a prior protest, the
agency did not engage in meaningful discussions.
|
| May
20 |
The Court
of Appeals for the Federal Circuit reversed the ASBCA's
summary judgment in favor of Tecom
and held that the contractor could not recover the costs of
defending against, and settling, a private suit for sexual
harassment unless the contractor could show the original
plaintiff had very little chance of succeeding on the merits.
|
| May
19 |
Comments
are due by July 20 on a proposed regulation (FAR Case
2008-023) that would clarify the requirements that have to be
met for a sole
source award to a service-disabled veteran-owned small
business (FAR 19.1406). The proposed rule also would modify
the language in the regulation concerning sole source awards
to HUBZone small businesses (FAR 19.1306) to make it
consistent with the changes to the SDVOSB regulations. The
proposed rules respond to the GAO's decision in the matter of MCS
Portable Restroom Service, B–299291, March 28, 2007.
The GSA is
proposing to amend GSAR Part 541 (Acquisition
of Utility Services). Comments are due by July 20.
The Court
of Federal Claims reissued (as corrected) two earlier
decisions in the Rhinocorps bid protest. The first corrected
decision involves jurisdictional
matters; the second is the one granting
the preliminary injunction.
The CBCA's
decision in the Sectek
case gave me a headache. Moreover, I can't shake the feeling
the decision is wrong. The Government sought to extend the
term of a services contract for a third option year when, in
fact, the contract only permitted two option years. The
contractor submitted proposed labor rates for the
"third" option year; the Government ignored those
rates, and, after the end of the actual contract term, sent a
bilateral modification with the old rates, which the
contractor signed, purporting to extend it for the third
option year pursuant to the "Option to Extend the Term of
the Contract" clause. The contractor argued that it could
not be bound by that modification because there was no legal
authority under the "Option to Extend the Term of the
Contract" clause to enter into it. The Board got around
this with some fairly lame references to the policy behind the
contract's "Option to Extend Services" provision,
which would have allowed the parties to extend the contract
for six months, even though the Government had not complied
with that clause's notice provision and had not cited it as
authority for the modification at issue. (As a side
note, although the contractor's name is "Sectek,"
the url for the case includes the name "Sectex.")
There are
a couple of other newly published CBCA cases.
|
|
May 18
|
Effective
June 17, the Department of Energy Acquisition Regulation
(DEAR) is being amended to revise the security
clause used in all contracts and subcontracts involving
access authorizations to specifically require background
reviews, and tests for the absence of any illegal drug, as
defined in DOE regulations of uncleared personnel (employment
applicants and current employees), who will require access
authorizations. Background reviews will not be required for
applicants for DOE access authorization who possess a current
access authorization from another Federal agency.
|
|
May 14
|
Four new ASBCA decisions are out.
Coincidentally, two involve default terminations for failure
to delivery military equipment to Iraq (machine
guns and cargo
trucks), and both of those involve the contractor's
difficulty in obtaining End User Certificates. The machine gun
supplier lost its appeal; the cargo truck contractor's appeal
survives after the Board denied cross motions for summary
judgment.
In Trace
Inc., the ASBCA sustained an appeal involving the
contractor's allegations that the Government had improperly
deducted amounts based on improvidently issued Contractor
Deficiency Reports. Judge Van Broekhoven scolded both parties,
however, for an incomplete and unclear record, quoting from a
Seventh Circuit case: "Judges are not like pigs, hunting
for truffles buried in briefs."
|
|
May 11
|
The SBA is
considering waiving the nonmanufacturer rule for PSC 9130--Liquid
Propellants--Petroleum Base. Comments are due by May 26.
|
|
May 7
|
The GSA
has rewritten GSAR
Part 549 (Termination of Contracts). The effective
date is June 8.
Mission
Critical Solutions won its protest against a sole source
award because the agency made the award without
considering whether it could obtain competition from two or
more HUBZone small businesses as required by the HUBZone
statute, the provisions of which the GAO recognized as
"mandatory." Interestingly, the SBA fought
against the protester's position in the protest (so the GAO
decided against the SBA's interpretation).
|
|
May 6
|
The Court
of Appeals for the Federal Circuit reversed the Court of
Federal Claims' prior
decision in the Axiom
bid protest case because the appeals court did not believe
it appropriate for the Court of Federal Claims to have set
aside a contract award based solely on its suspicion that the
Contracting Officer would not enforce Lockheed's OCI
mitigation plan. The Federal Circuit also found fault with the
lower court's decision to allow supplementation of the
administrative record without a showing that such
supplementation was necessary for necessary for effective
judicial review.
The GSA
has rewritten GSAR
Part 525 (Foreign Acquisition). The effective date is July
6.
|
|
May 5
|
There is a
proposed rule (FAR Case 2008-015) that would change the
withholding requirement for payments under fixed-price
architect-engineer contracts from 10% to an amount
determined by the Contracting Officer as being necessary to
protect the Government's interests. Comments are due by July
6.
The GSA
has rewritten GSAR
Part 537 (Service Contracting). The effective date is June
4.
The Postal
Service has published the final revisions to the rules
of practice for the Postal Service Board of Contract
Appeals. The final rules are effective June 1.
|
|
May 2
|
Three new ASBCA decisions are
out, all of which involve interesting cost issues. To me, the
most interesting of the three is the ATK
Launch Systems decision, which involved a contractor's
claim that the Government breached the Allowable Cost and
Payment clause by failing to adjust interim billing rates to
include certain allowable costs. The Board wrote, in part, as
follows: "While we agree with the government that under
the ALLOWABLE COST AND PAYMENT clause the CO or authorized
representative is responsible to set interim billing rates,
there is nothing in the clause -- or anywhere in the contract,
regulations or case law for that matter -- that would forbid a
contractor from filing a claim under the CDA challenging this
CO determination. The parties often use billing rates for
years until final rates are agreed upon, or litigated and
determined by a court or board. An erroneously low billing
rate may cause loss to a contractor throughout this period.
Subsection (e) of the ALLOWABLE COST AND PAYMENT clause
provides that the billing rates "shall be the anticipated
final rates." This means that they must include all
properly allowable and allocable costs, and failing mutual
agreement a contractor may claim under the CDA that the CO did
not include such costs and hence violated this contract
provision and the ALLOWABLE COST AND PAYMENT clause." The
Board also held that the Allowable Cost and Payment clause
does not prohibit the award of damages for its breach.
|
|
May 1
|
Recall the
CBCA's irritation with the VA in the Ocwen Loan Servicing case
(see the entry at March 26 below)? In the latest
decision, the Board granted
the contractor's appeal because the VA refused another
opportunity to provide the appraisals the Board had ordered it
to produce. Judge Daniels' opinion of the VA's actions has not
improved: "Once again, the Board has thrown the [VA] a
lifeline, and the agency has used that rope to hang
itself."
|
|
April 29
|
The Bureau
of Industry and Security (BIS) is proposing to amend its
regulations (at 15 C.F.R. Part 701) concerning the reporting
of offset
agreements in sales of weapon systems or defense-related
items to foreign countries or foreign firms in order to update and provide
clarification with regard to the information U.S. companies
are required to submit each year to BIS to support the
preparation of the annual report to Congress on offsets in
defense trade. Comments are due by June 29.
Savantage
could not convince the Court of Federal Claims that the
Government's actions are violating the court's previous
injunction against proceeding with a sole-source award to
Oracle. Reading the decision, some of you may feel (as I do)
that Savantage lost only because of its high burden of proof
and that the Government probably is doing what Savantage
suspects (i.e., maneuvering to get around the court's earlier
injunction).
|
|
April 24
|
Blackwater
Lodge & Training Center lost its post-award protest at
the CoFC, but Judge Wheeler certainly gave the protester's
complaints against the technical and past performance
evaluations and the trade-off evaluation a full and fair
analysis. One wishes all judges were that thorough.
The GAO
published seven protest decisions today--deny,
deny,
deny,
deny,
deny,
deny,
deny.
Still a tough row to hoe.
|
|
April 23
|
The Cost
Accounting Standards (CAS) Board is soliciting comments
concerning whether the "overseas
exemption" from CAS for contracts performed entirely
outside the United States should be retained, eliminated or
revised and, if revised, how so. Comments are due by May 26.
The SBA is
waiving the nonmanufacturer
rule for Conductor and Control Cable (Aluminum); Conductor
and Control Cable (Copper); Truck Trailer; All terrain
vehicles (ATVs), wheeled or tracked; Snowmobiles and parts;
Off-road ATV, wheeled or tracked; Noncurrent-Carrying Wiring
Device Manufacturing, i.e., dead
end tees and connectors, guy strain and link assemblies, bolts, washers,
turnbuckles, twisted clips, steel angle assemblies, yoke
plates, compression T connectors, press dies, anchor shackles,
Y clevis ball and Y clevis sockets, yoke plates, and grounding
clamps.
|
|
April 22
|
Although
the CoFC's latest opinion in the long-running Veridyne
fraud case is just a ruling on the Government's motion to
amend its answer and counterclaim, the recited facts of the
case continue to amaze me. Veridyne (an 8(a) small business at
the time) and the Government jointly devised a way to extend
its 8(a) subcontract for five additional one-year options
beyond its original term without competition by stating that
the estimated cost was less than $3,000,000 (the amount that
would have required a new competition) even when it was
apparent to both that the probable cost was much more than
that. Part way through Veridyne's performance, the Government
apparently had second thoughts and came at Veridyne with both
guns blazing, alleging fraud and demanding all its money back,
even though Veridyne was successfully performing the work.
Veridyne's current suit ensued. If this all strikes you
as a bit disingenuous on the Government's part, the court
apparently shares your feelings. Witness its footnote nine
from the current opinion: "[D]uring oral argument the
court discussed candidly with both parties the vulnerabilities
in their respective cases. Each time the court has been asked
to review the merits of this case, it has been evident that
[the Government] may not be able to prevail at trial, and
[Veridyne] may well succeed."
|
|
April 21
|
Two new CBCA decisions are out:
DSS Services and Tarheel Specialties. |
| April
17 |
The applicability
date for the employment
eligibility verification rules in the FAR has been pushed
back to June 30.
New per
diem rates have been published for travel by government
employees in Alaska, Hawaii, Puerto Rico, the
Northern Mariana Islands and United States Possessions.
The CBCA's decision
denying the Government's motion for summary judgment in West
Ridge LLC is interesting for the following tantalizing
footnote: "West Ridge asserts that '[w]here the
Government accepts an offer that it could have rejected as
non-responsive, the award constitutes acceptance of a
counter-offer and binds the Government to the terms of that
counter-offer.' . . . In support of this proposition, the
lessor cites Bob
Vandiver Office Equipment Co., GSBCA 4138, 75-1 BCA ¶ 11,004
(1974). While the proposition
may be valid, Vandiver does not bind us. That decision
was issued under the small claims procedure and therefore has
no value as precedent. . . . We will appreciate further
briefing as to the legal implications of the Government’s
acceptance of a non-responsive offer." Stay tuned.
Take a look at the last
page of the Vastec
Group decision by the SBA's OHA. Is it just me, or does
the "Analysis" section of the opinion seem a bit
perfunctory? (EDIT--they fixed it; it was much more humorous
the old way--the "Analysis" section was originally
blank).
|
|
April 16
|
I have corrected the
headings at the top of the SBA
OHA decisions page so that they will link correctly to the
various sections on that page. There are several new SBA OHA decisions out today. Forterra
and Val-Coast
are the new size decisions, and Dynamac
Corp. is a new NAICS decision.
|
|
April 14
|
The GSA has issued a
rewrite of GSAR Part 528, entitled "Bonds
and Insurance."
The ASBCA has issued
a couple of new decisions.
|
|
April 13
|
Proposed revisions
would conform the FAR to changes in the SBA's regulations
concerning the HUBZone
program. Comments are due by June 12.
The Court of Federal
Claims found Rhinocorps
had standing to continue its protest despite the fact that the
company did not bid on the protested solicitation because the
protest had been pending since well before the solicitation
was issued and the protester claimed the solicitation was
issued as a pretext to keep it from being awarded a follow-on
contract.
|
|
April 10
|
Effective today, the
GSA has amended the Federal Travel Regulation to clarify that travelers
must deduct the appropriate amounts from their meals
and incidental expense allowance when meals are part of a
registration fee or otherwise paid for by the Government, in
conjunction with attendance at conferences or other events
while on official travel. The amendments also clarify that in
limited instances, agencies may allow employees to claim the
full allowance for meals when employees are unable to consume
meals furnished by the Government.
Effective
May 11, the GSA has clarified the meal and incidental expense
allowance for travel in
excess of 12 hours but less than 24 hours.
|
|
April 9
|
I just discovered that the links to federal
regulations issued prior to April 2008 in the 2007 and 2008
blogs and the 2007
and 2008
procurement reviews were broken because those web
addresses have been changed. I have fixed the problems
so the links should be working again. I've also fixed several
broken links on the Statutes page.
|
|
April 8
|
The Department of Transportation has
issued several proposed rules concerning its Disadvantaged
Business Enterprise (DBE) program, relating to (i)
counting items obtained by a DBE subcontractor from its
prime contractor; (ii) encouraging "unbundling" of
contracts to facilitate participation by small businesses,
including DBEs; (iii) improvements to the DBE application
form; (iv) program oversight; (v) facilitating
certification for firms seeking to work as DBEs in more than
one state; and (vi) limitations on the discretion of prime
contractors to terminate DBEs for convenience, once the prime
contractor has committed to using the DBE as part of its
showing of good faith efforts. |
| April 6 |
Sorry
for the gap in the blog--I've been too busy for my own good
the past few days. There are several new Court of Federal
Claims decisions out that I have listed in the CoFC bid protests page. The
most interesting of the bunch is the temporary restraining
order issued by the court in favor of Datapath,
enjoining a contract award because the Government's J & A
was sketchy at best; the Government had contributed to the
delay responsible for the emergency buy; the Government did
not have the administrative record available for review by the
protester before the proposed time of contract award; and the
court was mindful of President Obama's memorandum
to executive agencies of March 4 re government contracting
policies and requirements. It didn't take long for that
memorandum to have an effect. |
| April 1 |
In D
& F Marketing, the ASBCA found that nobody in the
entire Navy had the authority to enter into the type
of contract the appellant claimed existed. |
| March 31 |
There are a couple of interesting
new Court of Federal Claims decisions. In the court's decision
on the NEQ
post award protest, Judge Allegra refused to go as far as some
other judges appear to in allowing supplementation of the
administrative record. He wrote, in part: "The court will
not repeat itself here except to reiterate, in particular, its
refusal to supplement the record, via discovery, with more
information regarding the agency’s reasoning for an award,
or to otherwise add to the record evidence, not previously
possessed by the agency, designed supposedly to improve the
court’s 'understanding' of a case." The Tecom
decision involves a slew of different categories of damage
calculations for government breach, including costs of REA
preparation, lost profits, prime contractor profit on a claim
sponsored by the prime for the sub, and many specific labor
and material cost categories.
Federal
Acquisition Circular 2005-32 has been published.
It contains six regulations, the first five of which are
issued under the American Recovery and Reinvestment Act of
2009 (the "Recovery Act"):
Item I, an interim
rule effective today, entitled "Buy
American Act Requirements for Construction Materials"
(FAR Case 2009-008), prohibits the use of funds
appropriated or otherwise made available by the Recovery Act
for any project for the construction, alteration, maintenance,
or repair of a public building or public work unless all of
the iron, steel, and manufactured goods used in the project
are produced in the United States.
Item II, an interim rule effective today, entitled "Whistleblower
Protections" (FAR Case 2009-012), prohibits
federal employers from discharging, demoting, or
discriminating against employees as a reprisal for disclosing
information concerning violations of the Recovery Act.
Item III, an interim
rule effective today, entitled "Publicizing
Contract Actions" (FAR Case 2009-010), amends
the FAR to reflect new requirements for (i) posting
of presolicitation notices; (ii) announcing contract awards;
(iii) entering awards into the Federal Procurement Data
System (FPDS); and (iv) actions that are not fixed-price or
competitive.
Item IV, an interim
rule effective today, entitled "Reporting
Requirements" (FAR Case 2009-009), which implements
the portion of the Recovery Act known as the ‘‘Jobs
Accountability Act,’’ requires contractors that
receive awards (or modifications to existing awards) funded,
in whole or in part, by the Recovery Act to report quarterly
on the use of the funds.
Item V, an interim
rule effective today, entitled "GAO/IG
Access" (FAR Case 2009-011), adds
alternate clauses to FAR 52.214–26, "Audit and Records–Sealed
Bidding," FAR 52.212–5, "Contract Terms and
Conditions Required to Implement Statutes or Executive Orders–Commercial
Items," and FAR 52.215–2, "Audit and
Records-Negotiation." Moreover, FAR 12.504(a)(7) is
amended for contracts using Recovery Act funds to apply 41
U.S.C. 254d(c) and 10 U.S.C. 2313(c), Examination of Records
of Contractor, to commercial item subcontracts that are
otherwise exempt when subcontractors are not required to
provide cost or pricing data. Likewise, FAR 13.006(d) is
amended for contracts using Recovery Act funds to apply 52.215–2,
"Audit and Records-Negotiation" to contracts and
subcontracts which are otherwise exempt because they are under
the simplified acquisition threshold.
Item VI, an interim
rule effective today, entitled "GAO
Access to Contractor Employees" (FAR Case 2008-026),
implements Section 871 of the Duncan Hunter National Defense
Authorization Act for Fiscal Year 2009 (NDAA) (Pub. L. 110–417), which
allows the GAO to interview current contractor employees
during the audit of the contractor’s records. FAR 52.215–2(d)(1)
"Audit and Records-Negotiation," is revised to allow
for the required access by inserting before the period: "‘and
to interview any current employee regarding such
transactions." FAR 52.214–26(c) "Audit and
Records-Sealed Bidding" is revised to allow for the
required access by inserting before the period: ‘‘and also
the right to interview any current employee regarding such
transactions."
|
| March 30 |
The Office
of Labor Management Standards of The Department of Labor has
rescinded the regulations at 29 C.F.R. Part 470, which had
required government contractors and subcontractors to post
certain notices
concerning the rights of union workers. This action is the
result of President Obama's Executive Order 13496, which
rescinds Executive Order 13201.
|
| March 26 |
The DoD is
soliciting suggestions from contractors concerning its
acquisition strategy to fulfill the requirement that
contractors working outside the United States have Defense
Base Act insurance to provide workers compensation
benefits in accordance with Section 843 of the National
Defense Authorization Act for Fiscal Year 2009. Comments are
due by April 3.
I highly
recommend the CBCA's decision in the Ocwen
Loan Servicing case as a thoroughly entertaining read. The
Board imposed sanctions against the Department of Veterans
Affairs after it repeatedly refused both the contractor's
discovery requests and the Board's orders to provide certain
documents critical to the Government's own claim against the
contractor. The opinion is chock full of great zingers from
the Board; here is just one taste to whet your appetite. The
Board had issued an order requiring the Government's
response by March 10. The VA filed a "preliminary
response" on March 5, noting that it would file a full
response by March 11. The Board replied (with palpable
sarcasm) that it "appreciates respondent's attentiveness
to the order and assumes that the reference to '11 March' is a
typographic error, since respondent must realize that it is
not the province of a party to determine when it will respond
to a Board order." The Government, nevertheless, did not
file its response until March 11, which caused the Board to
disregard it completely. Umm, VA, in case you haven't figured
it out yet, you ain't winning this battle.
Three
additional CBCA
decisions have been
published.
|
| March 25 |
The GSA
(GSAR Case 2006-G512) has published its final rule revising
Part 509 (Contractor
Qualifications) of the GSAR. The rule is effective April
24.
|
| March 24 |
Three new ASBCA decisions are
out, covering, inter alia, EAJA awards, deductive
changes, and the requirements for a CDA claim.
ACCESS
Systems won its GAO protest because the agency's
evaluators did not attempt to justify a task order award to a
higher priced offeror.
|
| March 23 |
The
National Technology Information Service of the Department of
Commerce is accepting orders for the 2009 edition of the Export
Administration Regulations, which should be available to
ship by approximately April 5.
Barrios
Distributing alleged that, upon the return of beverage
dispensers it had leased to the DOJ, it discovered that the
Government had damaged them. The CBCA, however, found that (i)
the contract placed the risk of loss on Barrios; (ii) even
assuming that were not the case, the company had not proved
the equipment was damaged; (iii) assuming it were damaged, the
company had not proved who was responsible for the damage; and
(iv) the company had signed for the re-delivered equipment as
having arrived in "good condition." The arcane Latin
legal phrase describing the Government's position in this case
is "slam dunk winner."
|
| March 20 |
The GSA
(GSAR Case 2006-G506) is proposing to rewrite Part
523 of he GSAR. One of the proposed revisions changes the
title of that part to "Environment, Energy and Water
Efficiency, Renewable Energy Technologies, Occupational
Safety, and Drug-Free Workplace," to correspond to the
title in FAR Part 23. Comments are due by May 19.
In Per
Diem Bulletin 09-05, the GSA revises the Federal Travel
Regulation CONUS maximum
per diem rates for Idaho, Maryland, and South
Carolina.
Pond
Security Group prevailed in its application for costs at
the GAO based upon its protest of a defect in a solicitation
despite the fact that its subsequent proposal later was
determined to be noncompliant. The GAO said the award of costs
in such protests is not dependent on post-protest events in
the competition.
|
| March 19 |
Federal Acquisition Circular 2005-31
has been published. It includes the following six items:
Item I, a
final rule entitled "Small Business Size
Rerepresentation" (FAR Case 2006-032), implements the
Small Business Administration's (SBA) final rule published on
November 15, 2006 (71 FR 66434), entitled "Small Business
Size Regulations; Size for Purposes of Governmentwide
Acquisition Contracts, Multiple Award Schedule Contracts and
Other Long-Term Contracts; 8(a) Business Development/Small
Disadvantaged Business; Business Status Determinations."
The new rule adopts (with several changes) the interim rule
originally published at 72 FR 36852 (July 5, 2007) and applies
to solicitations issued and contracts awarded on or after
April 20, 2009. Moreover, all long-term contracts as defined
in the rule, awarded to small business concerns prior to June
30, 2007, that have not yet been modified to include FAR
52.219-28, must be modified to include FAR 52.219-28 within 90
days after the effective date of this final rule. Basically,
the new rule requires businesses to re-certify
their status as small at various points during long-term
contracts.
Item II,
an interim rule entitled "Clarification of Submission of
Cost or Pricing Data on Non-Commercial Modifications of
Commercial Items" (FAR Case 2008-012), implements Section
814 of the National Defense Authorization Act for Fiscal Year
2008, which requires the harmonization of the
threshold for cost or pricing data on non-commercial
modifications of commercial items with the Truth In
Negotiation Act (TINA) threshold for cost and pricing data. The new threshold is $650,000, and
it will be adjusted as necessary to maintain the required
consistency in the future. The interim rule is effective today.
Item III,
a final rule entitled "Amendments
to Incorporate New Wage Determinations" (FAR Case
2008-014), amends the FAR to preclude a possible
scenario where a contracting officer has to unnecessarily
reevaluate proposals already eliminated from a competition.
The new rule corrects the
inconsistency at FAR 22.404-5(c)(3) by changing the language
to indicate a contracting officer shall amend solicitations to
incorporate new wage determinations and furnish the wage rate
information to all offerors that have not been eliminated from
the competition, if the closing date for receipt of offers has
already passed. The rule is effective April 20.
Item IV, a
final rule (effective today) entitled "Least
Developed Countries that are Designated Countries"
(FAR Case 2008-021), amends FAR 25.003's lists of designated
and least-developed countries and the contract clauses at FAR
52.225-05 and 52.225-11.
Item V, an
interim rule (effective today) entitled "Federal Food
Donation Act of 2008 (Pub. L. 110-247)" (FAR Case
2008-017), to implement the Federal
Food Donation Act of 2008, which encourages executive
agencies and their contractors, in contracts for the
provision, service, or sale of food, to the maximum extent
practicable and safe, to donate apparently wholesome excess
food to nonprofit organizations that provide assistance to
food-insecure people in the United States. Comments are due by
May 18.
Item VI
entitled "Technical Amendments" makes miscellaneous editorial
changes to the FAR.
In Sundt
Construction, the ASBCA held it had jurisdiction to
enforce a term of a settlement agreement by which a contractor
dropped certain claims in return for the Government's
agreement to provide it with a specified performance rating.
The existence of the agreement was proved by an affidavit
submitted by the former contracting officer who made the
agreement.
|
| March 18 |
The
Department of Homeland Security is proposing to amend the
Homeland Security Acquisition Regulation (HSAR) to prohibit
DHS from awarding a Federal Protective Service (FPS) contract
for guard services to a business concern that is owned,
controlled, or operated by an individual who has been
convicted of a serious
felony. The rule is necessary to implement the provisions
of Public Law 110-356, the Federal Protective Service Guard
Contracting Reform Act of 2008. Comments are due by April
17.
|
| March 17 |
Effective
April 1, the SBA is terminating its waiver of the
nonmanufacturer rule for PSC 3930, Warehouse
Trucks and Tractors, Self-Propelled based on SBA’s
recent discovery of small business manufacturers of these
items.
In Texas
National Bank f/k/a Mercedes National Bank, the Court of
Federal Claims discussed the "accrual suspension
rule" for determining whether the six-year statute of
limitations has been tolled: ". . .'[a]ccording to the
accrual suspension rule, the accrual of a claim against the
United States is suspended, for purposes of 28 U.S.C. 2501,
until the claimant knew or should have known that the claim
existed.' Young v. United States, 529 F.3d 1380, 1384 (Fed.
Cir. 2008) (quotation omitted). 'To achieve such suspension
the plaintiff must either show that the defendant has
concealed its acts with the result that plaintiff was unaware
of their existence or it must show that its injury was
inherently unknowable at the accrual date.' Id. (quotation
omitted). The phrase 'inherently unknowable' has been
construed to mean that the factual basis for the claim is
'incapable of detection by the wronged party through the
exercise of reasonable diligence.' Ramirez-Carlo v. United
States, 496 F.3d 41, 47 (1st Cir. 2007)." In this case,
the actions were readily ascertainable rather than inherently
unknowable. Thus, the rule did not apply.
|
| March 13 |
The DOE
has published lengthy, detailed regulations concerning the
federal procurement of energy
efficient products pursuant to the National Energy
Conservation Policy Act. The final rule becomes effective
April 13.
|
| March 12 |
GWU just
published two ASBCA
decisions from mid-February. Every time I notice that no
decisions have been published for an inordinate period of time
and email GWU to inquire, the response always is that they
publish them when they "get around to it." Dear
ASBCA, there are many of us out here who are more interested
than that and who would happily publish your decisions the
same day you sent them to us. Just fyi. :)
CBCA
decisions are published much more promptly than those of the
ASBCA (do you hear me, ASBCA?). In Navigant
Satotravel, the CBCA found the one witness the contractor
had called to try to prove a negative left much to be desired:
"NST called Mr. Stec as its only witness to prove a lack
of knowledge of receipt of the SF 1449 by all of NST's
personnel. We find, however, that '[w]hen the persons having
the greatest familiarity with events are not called, but a
litigant seeks to rely on second-hand, hearsay evidence, a
tribunal may draw an inference that the testimony of the
persons not called would not support a litigant's position . .
. .' TDC Management Corp., DOT BCA 1802, 91-2 BCA ¶
23,815, at 119,259. . . . Nothing in the record would suggest
that Mr. Stec was the only person available who could have
testified as to the circumstances surrounding receipt of the
SF 1449."
|
| March 11 |
The GAO
sustained Arc-Tech's
protest because the agency excluded its proposal from the
competitive range without evaluating its cost and without any
documentation showing the proposal was technically
unacceptable.
|
| March 10 |
Several
new SBA OHA size decisions
are out. The most interesting is Cummings
Construction, in which the OHA overruled the determination
of the Area Office and found that the one person who had a
majority membership interest of a limited liability company
had the power to control it, despite that fact that he and
another individual had made equal capital contributions
(because capital contributions are not a factor in determining
control).
|
| March 9 |
The
SBA is considering waiving
the nonmanufacturer rule for aluminum and copper conductor
and control cable; all terrain vehicles (ATVs), wheeled or
tracked; snowmobiles and parts; off-road ATVs, wheeled or
tracked; and non current-carrying wiring device manufacturing,
i.e., dead end tees and connectors, guy strain and link
assemblies, bolts, washers, turnbuckles, twisted clips, steel
angle assemblies, yoke plates, compression T connectors, press
dies, anchor shackles, Y clevis ball and Y clevis sockets,
yoke plates, and grounding clamps. Comments are due by March
24.
|
| March 6 |
President
Obama's Memorandum
of March 4, entitled "Government Contracting,"
suggests we may be seeing fewer cost reimbursement contracts
and less reliance on limited competition (including sole
source) contracts and outsourcing.
In
Southern
Scrap Metal, the Government tried (without success) to
convince the Civilian Board of Contract Appeals that
amendments to requests for equitable adjustment that formed
the basis for later claims appealed to the Board from the
Contracting Officer's failure to decide them within the
statutory time period had tolled that 60-day time period. The
Board reasoned that the contractor had not amended the claims,
themselves, and that the amendments to the original requests
for equitable adjustment were for different periods of alleged
delay and were based on a different theory than that which
underlay the claims being appealed.
Flexing
its judicial muscles in Libbey
Physical Medicine Center and Hot Springs Health Spa, the same Board noted it wasn't bound
by decisions of the D.C. Circuit and was co-equal with the
Court of Federal Claims in the interpretation of the Contract
Disputes Act and then held that the CDA applied to a concession
contract, one component of which involved "construction,
alteration, repair, and maintenance of real property, title to
which vested in the
Government," which gave the Board jurisdiction to
determine the valuation of the leasehold surrender interest
under an expired concession contract.
Gardner
Zemke was stuck with an increased tax imposed by the
Navajo Nation because (i) the Government had not represented
the tax would not change; (ii) the Government had not changed
it; and (iii) the Government employees who allegedly promised
to do something about it had no actual authority to change the
contract.
Honeywell
Technology Solutions won its GAO protest because the
agency's Past Performance evaluators were unreasonable in
relying on a contract that was too small to be considered
relevant.
|
| March 5 |
In
Scott
Timber, the Court of Federal Claims held the Government's
suspensions of timber sales contract breached them, despite
the presence of a suspension of work clause in the contracts,
because (i) the Government failed to disclose its superior
knowledge to bidders concerning ongoing lawsuits that had a
significant potential to delay the work and (ii) unreasonably
continued one such suspension.
|
| March 2 |
SP
Systems originally won a NASA award, but, after the GAO
sustained a protest against the evaluations of cost realism,
management approach, and past performance that led to that
award, the agency followed the GAO's specific recommendations
for corrective action and (after re-evaluation) awarded the
contract to a competitor. SP Systems then filed suit in the
Court of Federal Claims, which found both the GAO's decision
and the agency's decision to follow it, reasonable, even
though there were other ways the agency might have
re-evaluated proposals.
|
| February 24 |
In
L-3
Communications EOTech , the Court of Federal Claims held
that the Government did not violate any law or regulation in
awarding a sole-source bridge contract to the
protester's competitor pending the completion of a competition
for a follow-on contract because protester's product was not
"type classified" (even though the Government
previously had awarded contracts for the items to the
protester, among others).
Carahsoft,
too, lost its protest involving a bridge contract
because the Court of Federal Claims was "simply
dumbstruck" by the protester's theory that certain terms
from a bridge contract had been incorporated in a subsequent
follow-on contract despite a contractor's explicit exclusion
of them--terms that would have required the agency to pay
twice for the same items.
|
| February 21 |
In Daewoo
Engineering, the Court of Appeals for the Federal Circuit
affirmed the CoFC's decision that a contractor's certified CDA
claim, which was was baseless and intended only as a
negotiating ploy, was fraudulent.
|
| February 19 |
Because it
exceeded its 5% contracting goal in 2008, the DoD has
suspended its 10% price
evaluation adjustment for small disadvantaged businesses
from March 13, 2009 to March 12, 2010.
The GAO
has issued Principles
of Federal Appropriations Law, Third Edition, Volume
III, which supersedes (in the always entertaining logic of the
Federal Government) Volume IV, Second Edition, published in
2001.
|
| February 13 |
In Rhinocorps,
the Court of Federal Claims ruled on a preliminary skirmish in
an incumbent small business's challenge of the Air Force's
decision not to re-compete its small-business, set-aside
contract in favor of adding essentially the same work to an
ongoing contract being performed by a large business. The
court held that the plaintiff's challenge to the adequacy of
the Government's D&F supporting the decision not to
re-compete was sufficient to survive a motion to dismiss. In
doing so, the court considered the import of the Federal
Circuit's recent decision in the Distributed
Solutions case concerning what constitutes a
"procurement" that can be protested.
|
| February 12 |
The SBA
proposes to terminate
the waiver of the Nonmanufacturer Rule for PSC 3930, Warehouse
Trucks and Tractors, Self-Propelled because there are small business manufacturers of
these items. Terminating this waiver will require recipients
of contracts set aside for small businesses, service-disabled
veteran-owned small businesses, or participants in SBA's 8(a)
program to provide the products of small business
manufacturers or processors on such contracts. Comments are
due by February 27.
|
| February 11 |
The Postal
Service has published proposed
rules for the Postal Service Board of Contract Appeals,
which was re-established by Section 847 of the National
Defense Authorization Act for Fiscal Year 2006. Comments are
due by March 13.
Executive
Order 13502 authorizes federal agencies to require project
labor agreements (collective bargaining agreements) on large
scale construction projects (those whose cost to the federal
government equals or exceeds $25 million) when certain
criteria are met.
In CHARO
Community Development Corp., on reconsideration, the SBA's
Office of Hearings and Appeals reversed itself and decided
that the SBA had established a de novo hearing
under the APA at the OHA as the means of review for firms
believing themselves aggrieved by actions of the SBA under WBC
program cooperative agreements. See also entry at
January 16 below.
SMARTnet
won its GAO protest because of a solicitation requirement that
exceeded the agency's minimum needs.
|
| February 10 |
The Court
of Federal Claims awarded Keeter
Trading Co. breach damages for the Postal Service's bad
faith default termination of its contract. "Bad
faith" by government officials is very difficult for a
contractor to prove, but Keeter did it, with room to
spare. According to the court, the Postmaster meddled
(the best way to put it) in the contract, required an improper
change to it, and then essentially engineered the termination
by the official who had the authority to make that decision.
The same
court awarded Alabama
Aircraft Industries, Inc. - Birmingham about $1 million in
bid and proposal costs as a result of its earlier,
successful protest (about half the amount it had claimed).
|
| February 9 |
The
agency's "considerable ineptitude in managing" a
delivery order to DLT
Solutions did not rise to the level of a bad faith
termination according to the ASBCA. For an appeal that
involved less than $10,000 in claimed damages, this one
certainly kept everybody busy. In a 26-page opinion, the Board
had to decide whether the fact that payments were to be made
to a financing institution under an assignment agreement
precluded the claim under the Severin doctrine (it did
not) and whether some of the claims involved alleged
misrepresentation and fraudulent inducement by the Government
as a third-party tortfeasor over which the Board lacked
jurisdiction (they did).
Speaking
of hoary doctrines, the ASBCA also has issued a decision in
which the Fulford doctrine saved the contractor (RO.VI.B. Srl--you read that right)
from a tardy appeal of a default termination.
|
| February 5 |
WRS
Infrastructure & Environment is a Court of Federal
Claims case in which the plaintiff challenges a size
determination by the SBA's Office of Hearings and Appeals.
Three ASBCA decisions
have been published, the most interesting of which is the ALKAI
Consultants case, which converts a default termination to
a termination for convenience in part because the contractor
officer ordered the contractor to de-mobilize based on a
mistaken understanding of what the completion date was.
|
| February 4 |
Pursuant
to the devilishly arcane strictures of 28 U.S.C. 1500, the
Court of Federal Claims dismissed the complaint in Lan-Dale
Co. because the suit had been filed simultaneously in the
CoFC and in Arizona district court. In several passages
guaranteed to make attorneys cringe and vow to pay more
attention in their next CLE class, the court described not
only the plaintiff's mistake in the original filing but also
the plaintiff's failure to avail itself of several
opportunities the court gave it to find a way out of the mess.
The Court
of Appeals for the Federal Circuit upheld the Court of Federal
Claims' decision dismissing the protest of The
Centech Group because, in its offer, it had not agreed to
comply with a material requirement of the solicitation.
Executive
Order 13494 makes unallowable the costs of "any
activities undertaken to persuade employees—whether
employees of the recipient of the Federal disbursements or of
any other entity—to exercise or not to exercise, or
concerning the manner of exercising, the right to organize and
bargain collectively through representatives of the employees’
own choosing." Executive
Order 13495 requires service contracts to include a clause
requiring a follow-on service contractor to give the previous
contractor's employees a right of first refusal to continue
work on the contract. Executive
Order 13496 requires government contractors and
subcontractors to post notices informing employees of their
collective bargaining rights. Failure to do so can result in
contract termination and debarment.
More and
more, redactions are delaying and eroding access to judicial
and administrative decisions. Now, we are having to wait for
redacted versions of SBA OHA decisions. Witness the belated
issuance of Baldt,
Inc., is an interesting size decision analyzing
affiliation even ignoring all the "x's."
|
| February 3 |
The Office
of U.S. Citizenship and Immigration Services in the Department
of Homeland Security is extending until March 4 the date for
comments on the interim final rule originally published
December 17, 2008 concerning the types
of documentation acceptable for employment eligibility
verification. The interim final rule, itself, is extended
until April 3.
|
| January 30 |
FAR Case
2007-013: The effective date of the employment
eligibility verification regulations has been moved back
to May 21, 2009.
In Zoltek
Corporation, the Court of Federal Claims allowed a
plaintiff who had filed a patent infringement claim against
the Government under 28 U.S.C. 1498 over which the court
lacked jurisdiction to transfer the case to federal district
court because the Court of Federal Claims believed the case
could easily be re-formulated by substituting the infringing
government contractor for the Government as the defendant and
using 35 U.S.C. 271(g) as the jurisdictional hook instead of
28 U.S.C. 1498.
The CBCA
dismissed an appeal by Corners
and Edges for failure to prosecute because the contractor
stated it would not file its complaint unless and until the
Board provided it with a free copy of the hearing transcript
in another of the contractor's appeals.
|
| January 27 |
There are
four new SBA Office of
Hearings and Appeals VET decisions out. One dismisses a
protest of VOSB
status because regulations governing such appeals have not
yet been promulgated. So much for the old saw: "Where
there is a wrong, there is a remedy."
|
| January 26 |
The GSA is
proposing an extensive and lengthy rewrite of GSAR
Part 538, entitled "Federal Supply Schedule
Contracting." Comments are due by March 27.
|
| January 24 |
Critical
Process Filtration protested the terms of six
solicitations because the DLA did not list a product's salient
features to allow offers of other than the specified brand
name. The agency countered that it was using simplified
acquisition procedures. That argument worked in five of the
solicitations, but the protester won the sixth because the
total estimated quantity exceeded the simplified acquisition
threshold. The agency argued unsuccessfully that each of its
orders would be less than the threshold, but the GAO said the
agency could not split orders simply to avoid competition
requirements.
|
| January 23 |
Robinson
Quality Constructors completed its construction contract
(except for punch list items) by June 1, 1999 and submitted a
CDA claim for various construction delays on June 2, 2005. The
ASBCA dismissed the claim as barred by the six year statute of
limitations. The Board reasoned that the events that gave rise
to the delay claim must have accrued sometime before June 1,
1999.
|
| January 21 |
The GAO
sustained a protest by Tiger
Truck because the agency failed to conduct meaningful
discussions and also failed to follow proper procedures with
regard to offered items that were not compliant with the
requirements of the Trade Agreements Act.
|
| January 20 |
I was born
in Mississippi in 1947. I remember visiting my grandmother in
Jackson when I was eight or nine years old and watching her
silently get up from her rocking chair and turn off the
television simply because an African-American appeared on the
screen. I remember my uncle (who still lived in Mississippi at
the time) telling me in 1970 that the races should always be
schooled separately so that the white students would not catch
venereal diseases simply by using the same public restrooms as
students of other races. I remember one of the partners at the
first law firm I worked at after law school in 1979 opining
that a Black quarterback could never lead a college team to a
national championship. This is a great moment for our
country. So, I'll be glued to the TV screen instead of
updating the site today, and, this time, nobody's going to
shut off the TV.
|
| January 16 |
In its
first decision relating to the Women's Business Center (WBC)
awards program, the SBA's Office of Hearings and Appeals threw
out the SBA's decision not to renew the CHARO
Community Development Corp.'s award because the SBA had
not established any procedures for notice of, or opportunity
to contest, such decisions, thus violating the the
petitioner's due process rights.
In North
Star Alaska Housing, one Court of Federal Claims judge
read the bad faith exception to the American Rule for fee
apportionment very narrowly and refused to award attorneys
fees and litigation expenses to the plaintiff despite some
fairly egregious conduct by the Government before and during
litigation.
|
| January 15 |
This is a
busy day for FAR and DFARS regulations.
FAR
FAC 2005-30 has been published. It
includes the following nine items:
Item I, a
final rule entitled "Federal Procurement Data System
("FPDS")" (FAR Case 2004-038), (i) establishes
the FPDS
as the single authoritative source of all procurement data for
a host of applications and reports, such as the Central
Contractor Registration (CCR), the Electronic Subcontracting
Reporting System (eSRS), the Small Business Goaling Report
(SRGR), and Resource Conservation and Recovery Act (RCRA)
data; and (ii) requires contracting officers to verify the
accuracy of contract award data prior to reporting the data in
FPDS.
Item II, a
final rule entitled "Commercially Off-the-Shelf
("COTS") Items" (FAR Case 2000-305), (i)
amends the FAR to implement Section 4203 of the Clinger-Cohen
Act of 1996 (41 U.S.C. 431) with respect to the
inapplicability of certain laws to contracts and subcontracts
for the
acquisition of COTS items, (ii) establishes a new FAR
section 12.103, which outlines the treatment of COTS
items, and (iii) provides a new definition of a COTS item and
revised definitions of "domestic end product" and
"domestic construction material."
Item III,
a final rule entitled "Exemption of Certain Service
Contracts from the Service Contract Act
("SCA")" FAR Case 2001-004, (i) revises the
current SCA
exemption in the FAR and adds an SCA exemption for
contracts for certain additional services that meet specific
criteria and (ii) adds to the "Annual Representations and
Certifications" clause at FAR 52.204-8, the conditions
under which each listed provision applies or (for the more
complex cases) a check-off for the contracting officer to
indicate whether the provision is applicable to the
solicitation.
Item IV,
an interim rule entitled "Public Disclosure of
Justification and Approval Documents for Noncompetitive
Contracts-Section 844 of the National Defense Authorization
Act for Fiscal Year 2008 (Interim)" (FAR Case 2008-003),
(i) implements Section 844 of the National Defense
Authorization Act for Fiscal Year 2008; (ii) amends FAR 6.305
to require agencies to make available for public inspection
within 14 days after contract award the
justification required by FAR 6.303-1, on the website of
the agency and at the FedBizOpps
website or (in the case of a contract award permitted under
FAR 6.302-2) a posted justification within 30 days after
contract award; and (iii) requires contracting officers to
screen all justifications for contractor proprietary data and
remove all such data prior to publication.
Item V, a
final rule entitled "SAFETY Act: Implementation of DHS
Regulations" (FAR Case 2006-023), implements the
provisions of the
SAFETY Act, which provides incentives for the development
and deployment of anti-terrorism technologies by creating a
system of "risk management" and a system of
"litigation management."
Item VI, a
final rule entitled "Electronic Products Environmental
Assessment Tool ("EPEAT")" (FAR Case 2006-030),
adopts the previous interim rule without change so as to (i)
require use of EPEAT when acquiring personal
computer products such as desktops, laptops, and monitors
pursuant to the Energy Policy Act of 2005 and Executive Order
13423, (ii) revise FAR Subpart 23.7 and (iii) prescribe a
clause at 52.223-16 (also included in 52.212-5 for acquisition
of commercial items) in all solicitations and contracts for
the acquisition of personal computer products, services that
require furnishing of personal computer products for use by
the Government and services for contractor operation of
government-owned facilities.
Item
VII, a final rule entitled "Combating Trafficking
in Persons" (FAR Case 2005-012), (i) implements Section
3(b) of the Trafficking Victims Protection Reauthorization Act
(TVPRA) of 2003, (ii) requires that contracts contain a clause
allowing the agency to terminate the contract if a contractor,
contractor employees, subcontractor, or subcontractor
employees engage in severe forms of trafficking
in persons or procures a commercial sex act during the
period of performance of the contract, or uses forced labor in
the performance of the contract, and (iii) provides that the
contracting officer may consider whether the contractor had a
Trafficking in Persons awareness program at the time of a
violation as a mitigating factor when determining remedies;
and a website where the contractor may obtain additional
information about Trafficking in Persons and examples of
awareness programs.
Item VIII,
a final rule entitled "Trade Agreements--New
Thresholds" (FAR Case 2007-016) adopts the previous
interim rule without change and adjusts the
thresholds for application of the World Trade Organization
Government Procurement Agreement and the Free Trade Agreements
as determined by the United States Trade Representative,
according to a formula set forth in the agreements.
Item IX is
an editorial change to FAR
15.101-2.
DFARS
A final
rule entitled "Clean Air Act and Clean Water Act
Exemptions" (DFARS Case 2007-D022) establishes the
procedures for awarding
a contract to a contractor that is otherwise
excluded from Federal procurement programs due to a violation
of the Clean Air Act or the Clean Water Act.
A final
rule entitled "Contract Actions Supporting Contingency
Operations or Facilitating Defense Against or Recovery From
Nuclear, Biological, Chemical, or Radiological Attack"
(DFARS Case 2008-D026) lowers the
required level of DoD approval for determinations with
regard to the use of emergency acquisition flexibilities for
contract actions supporting contingency operations or
facilitating defense against or recovery from nuclear,
biological, chemical, or radiological attack.
A final
rule entitled "Delegation of Authority for Single Award
Task or Delivery Order Contracts" (DFARS Case 2008-D017)
specifies that the authority to award of a
single source task or delivery order contract exceeding $100
million may not be delegated below the level of the senior
procurement executive.
A final
rule entitled "DoD Law of War Program" (DFARS Case
2006-D035) includes requirements for DoD contractors to
institute effective programs to prevent violations of the law
of war by contractor
personnel authorized to accompany U.S. Armed Forces
deployed outside the U.S.
A final
rule entitled "List of Firms Owned or Controlled by the
Government of a Terrorist Country" (DFARS Case 2008-D025)
establishes procedures
for notifying the appropriate DoD office that a firm or
its subsidiary may be owned or controlled by the government of
a terrorist country.
An interim
rule (with a request for comments) entitled "Pilot
Program for Transition to Follow-On Contracting After Use of
Other Transaction Authority" (DFARS Case 2008-D030)
amends the DoD pilot program addressed in DFARS Subpart 212.70
"Pilot Program for Transition to Follow-On Contracting
After Use of Other Transaction Authority" by establishing
a new program
expiration date of September 30, 2010, and adding items
developed under research projects in accordance with 10 U.S.C.
2371 to the types of items to which the program applies.
A final
rule entitled "Security-Guard Functions" (DFARS Case
2006-D050) adopts without change the previous interim rule
extending until September 30, 2012, the period during which contractor
performance of security-guard functions at military
installations or facilities is authorized to fulfill
additional requirements resulting from the terrorist attacks
on the United States on September 11, 2001.
An interim
rule (with a request for comments) entitled "Senior DoD
Officials Seeking Employment With Defense Contractors"
(DFARS Case 2008-D007) amends the DFARS to implement Section
847 of the National Defense Authorization Act for Fiscal Year
2008, section 847 of which addresses requirements for senior
DoD officials to obtain a
post-employment ethics opinion before accepting a position
from a DoD contractor within two years after leaving DoD
service.
A final
rule entitled "Separation of Senior Roles in Source
Selection" (DFARS Case 2008-D037) requires the military
departments and defense agencies to certify every two years
that no senior leader has performed multiple
roles in the acquisition of a major weapon system or major
service.
Another
interim rule (with a request for comments) entitled
"Statutory Waiver for Commercially Available
Off-the-Shelf Items" (DFARS Case 2008-D009) implements a
determination made by the Administrator for Federal
Procurement Policy on February 14, 2008, in accordance with 41
U.S.C. 431, that the Buy
American Act domestic component test is inapplicable to
acquisitions of COTS items so that a COTS item will be treated
as a domestic end product if it is manufactured in the U.S.,
without the need to track the origin of the item’s
components.
An interim
rule (with a request for comments) entitled "Steel for
Military Construction Projects" (DFARS Case 2008–D038)
requires that American steel producers, fabricators, and
manufacturers be given the opportunity to compete for
contracts and subcontracts for the
acquisition of steel for use in military construction projects
or activities.
A final
rule entitled "U.S.-International Atomic Energy Agency
Additional Protocol" (DFARS Case 2004-D003) adds a
contract clause for use in contracts for research and
development or major defense acquisition programs involving
fissionable materials, other radiological source materials, or
technologies directly related to nuclear power
production, requires a contractor to notify DoD if the
contractor is required to report its activities under the U.S.-International
Atomic Energy Agency Additional Protocol.
An interim
rule (with a request for comments) entitled
"Whistleblower Protections for Contractor Employees"
(DFARS Case 2008–D012) addresses protections for contractor
employees who disclose information to government officials
with regard to waste
or mismanagement, danger to public health or safety, or
violation of law related to a DoD contract.
|
| January 14 |
FAC
2005-29, Amendment
1 (FAR Case 2007-013, "Employment Eligibility
Verification"): The effective and applicability dates of
this FAR case have been delayed to January 19 and February 20,
respectively. Beginning February 20, contracting officers
shall (i) include the new clause at 52.222-54, entitled
"Employment Eligibility Verification," in
solicitations in accordance with the prescription at FAR
22.1803; and (ii) modify, on a
bilateral basis, existing
indefinite-delivery/indefinite-quantity contracts in
accordance with FAR 1.108(d)(3) to include the clause for
future orders if the remaining period of performance extends
beyond August 20, 2009, and the amount of work or number of
orders expected under the remaining performance period is
substantial. See also the blog entry at November 14, 2008,
below.
In National
Housing Group, the contractor complained because HUD
assigned it fewer properties to manage (and withdrew certain
properties from its services in a shorter time frame) than it
had anticipated based on certain historical information
provided with the Government's solicitation. The Civilian
Board of Contract Appeals found for the Government because (i)
the solicitation clearly called for an ID/IQ contract; (ii)
the Government provided the required minimum quantities; and
(iii) the solicitation clearly allowed the Government to
remove properties from the contractor's management. On a
related claim, however, the Board held that a partial
settlement agreement did not operate as an accord and
satisfaction because it contemplated future negotiations on
open issues.
|
| January 13 |
GSA
Bulletin 09-02 clarifies the Federal Travel Regulation by
describing the situations in which those on travel may be
reimbursed for various
special fees, including fees for checked baggage and seat
assignments. The bulletin, itself, may be found by scrolling
down to the "Bulletins" section on this
page.
In Vantage
Assocs., the contractor argued unsuccessfully that
cancellation of its purchase order was improper because a
notice it allegedly had sent stating it could not perform on
time was a forgery. The ASBCA, however, found the notice was
irrelevant--the company had not performed the purchase order
by the revised delivery date, which justified the
cancellation, even absent any notice.
|
| January 12 |
In Teknowledge
Corp., the Court of Federal Claims held that a company's
software development costs were not allocable to its
government contracts because there was no nexus between the
software and any government contract work or benefit from the
software to such work.
|
| January 10 |
The SBA is
extending (until March 13) the comment period concerning the
list of industries that will be eligible for women-owned
small business federal contract assistance.
|
| January 9 |
A proposed
rule (FAR Case 2007-021) would amend the FAR to explicitly
require the use of the "Fair Labor Standards Act and
Service Contract Act-Price Adjustment (Multi-Year and Option
Contracts)" clause and the "Fair Labor Standards Act
and Service Contract Act-Price Adjustment" clause in
time-and-materials and labor-hour contracts that are subject
to the Service
Contract Act. The explanatory statements note that the
clauses are widely used in such contracts now but that the
absence of a specific prescription in the FAR leads to some
inconsistencies. Comments are due by March 10.
The saga
of the Information
Sciences Corp. (ISC) protests continues. After the Court
of Federal Claims twice invalidated a GSA award under a
competitive solicitation because of faulty evaluation
procedures, the agency (stubbornly) awarded a sole-source
contract to its contractor-of-choice. Rather than protest a
third time, Information Sciences filed suit on the basis that
the latest "award [i] violated FAR requirements to
conduct business with integrity, fairness, and openness, and
[ii] breached an implied-in-fact contract with ISC."
ISC's Complaint did not request that the sole-source award be
set aside. Instead it sought monetary damages for
"employee time, labor, material, and expert time involved
in pursuing the two prior solicitations." The court
dismissed the Complaint because neither of the prayers for
relief was a proper request for bid and proposal costs
cognizable under the Administrative Dispute Resolution Act,
but noted that the contractor could refile for such costs.
In Multiservice
Joint Venture, during a break in a deposition, a version
of an exhibit containing handwritten notes mysteriously
disappeared and was replaced with a "clean" version
of the exhibit. After the plaintiff's deponent,
representatives, and attorneys all failed or refused to
explain the situation to defendant's counsel and (later) the
judge, the Court of Federal Claims barred the deponent from
testifying at trial and ordered the plaintiff's attorneys
personally to pay the defendant's costs of filing the motion
for sanctions.
Effective
today, the GSA (GSAR Case 2008-G513) has rewritten GSAR Part
543 regarding contract
modifications. Effective February 9, the GSA (GSAR Case
2008-G512 ) is rewriting GSAR Part 542 regarding contract
administration and audit services.
Nortel
Government Solutions won its GAO protest against a DEA
award because the agency failed to adequately address the
awardee's potential organizational conflict of interest.
|
| January 8 |
The DoD
has issued revised per
diem travel rates for its civilian employees for travel in
Alaska, Hawaii, Puerto Rico, and the Mariana Islands, and
possessions of the United States.
|
| January 7 |
The GAO
sustained a protest by Master
Lock because the Contracting Officer and the Source
Selection Official improperly raised the awardee's evaluation
scores in the socioeconomic and JWOD evaluation factors from
the "poor" rating given by the source evaluation
panel to "neutral." The GAO concluded the agency
had, in effect, ignored these two evaluation factors simply
because the awardee was a small business, which violated the
evaluation scheme set forth in the solicitation.
|
| January 5 |
The
Department of Commerce's Bureau of Industry and Security (BIS)
is seeking public comments on whether U.S.
export controls influence manufacturers' decisions to use
or not use U.S.-origin parts and components in commercial
products and the effects of such decisions. BIS is interested
in obtaining specific information about whether such a
practice occurs, and if so, its economic effects in order to
assess the effectiveness of export controls as well as the
impact of export controls on the U.S. economy. Comments are
due by February 19.
|
| January 2 |
The IRS
and the GSA
standard relocation mileage rate for privately owned vehicles
has been reduced to $0.24 per mile for calendar year 2009.
|
| January 1, 2009 |
Time to
begin anew. You can find the entire 2008
Blog by following this link.
You might find it easier to peruse the 2008
Procurement Review or the 2007
Procurement Review than to search through the old
blogs.
|
|
The 2008 blog can be found here.
|
|